Stanton v. Morris Construction Co.

199 N.W. 104, 159 Minn. 380, 1924 Minn. LEXIS 644
CourtSupreme Court of Minnesota
DecidedMay 23, 1924
DocketNo. 23,923
StatusPublished
Cited by5 cases

This text of 199 N.W. 104 (Stanton v. Morris Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stanton v. Morris Construction Co., 199 N.W. 104, 159 Minn. 380, 1924 Minn. LEXIS 644 (Mich. 1924).

Opinion

Holt, J.

The controversy in this case relates to a concrete bridge at Willow River which the Morris Construction Company, a corporation, agreed to build for the county of Pine for the sum of $3,120. It appears that in response to an invitation by the county for proposals to construct 5 concrete bridges along State Trunk Highway No. 1, the Morris Construction Company, with other contractors, responded in February, 1918. This company was the lowest bidder and received the contract. It acceptably constructed 4 of the bridges and a certain balance due therefor is agreed to. It began the construction of the Willow River bridge, but difficulties in excavating for the piers or abutments were encountered in that, instead of the material to be moved being sand and gravel, as it is claimed the county represented, it consisted of logs, slabs, large rocks and debris of various kinds. This made it exceedingly difficult to sink cofferdams and prevent water entering. After building the south pier or abutment, and partly preparing for the other at the cost or outlay of over $7,000, and not being able to obtain any written agreement for additional compensation, the company ceased work. Later the county employed another concern to complete the bridge at a cost of over $8,000.

Thereafter one who had furnished material to the construction company for the bridge began this action against it, its bondsman and the county, to secure payment therefor. The county obtained leave to file a complaint of intervention against its codefendant, the construction company, for damages. To this complaint the company answered, alleging in substance that for the purpose of furn[382]*382ishing information to bidders upon which they could rely, and with intention that bidders should rely thereon so that the county might obtain the lowest possible bids, the county prepared plans and specifications whereon it was positively stated and represented that the soil to be excavated was clear sand and gravel; that said information was false in that instead of being clear sand and gravel it turned out to be boulders and what is commonly known as “mill hog feed,” consisting of butts of trees, slabs of wood, etc., making the excavation thereof exceedingly slow, difficult and expensive; that when the true condition was discovered the construction company took the matter up with the county for adjustment, but pending such adjustment, when the county refused to pay the balance for the bridges already constructed, the construction company ceased work. Counterclaims for extra work were also set up, but the validity and amounts thereof were stipulated at the trial and need not be noticed. The company also alleged the value of its work on this bridge in a sum of over $7,400, and asked that the contract be' canceled by the court on the ground of mutual mistake, that reimbursement be awarded for said sum expended, and that it have such other legal and equitable relief as might be just. The reply denied the representations and the right of the bidders to rely upon statements contained in the plans and maps exhibited to them, and also averred that, after the construction company was aware of the condition of the material where the excavations were to be made, it continued with the work and thereby affirmed the contract, notwithstanding the misrepresentations or mutual mistake, if any.

Before the trial, plaintiff’s claim was paid, so that the issues tried were solely those made by the pleadings between the county and the construction company and the former may be referred to hereinafter as plaintiff and the latter as defendant.

Certain assignments of error relate to the admissibility of testimony of statements or representations by the county engineer. .It appears that previous to calling for bids the county engineer had made surveys for the location of the bridges, and plans and specifications. The State Highway Commission furnished forms upon which the engineer entered the result of his work. This is known [383]*383as bridge survey, plans and specifications. All were in the custody of. the engineer, and to him the bidders came for information. The county had caused him to make the survey, and, no doubt, he was-authorized to give to persons intending to bid not only the information he had reduced to writing, but also such as he had gained in making the survey and which would likely tend to secure low or favorable bids for the county. The oral inducements or representations thus held out by the engineer we think properly received in evidence. But even if not, the error should not reverse, for the oral information added nothing of substance to that conveyed' by the survey map referred to.

Complaint is also made of admission in evidence of statements made in an open meeting of the county board by members thereof when defendant urged its claims for additional compensation, after it discovered the character of the excavation. Even if the statements made did not bind the county, evidence thereof was admissible on the issue whether or not defendant waived the false representations by continuing work after knowledge of the truth.

An engineer was asked as an expert whether there was ánything on the profile, showing the plan of this bridge, or the data contained thereon which would negative the statement that the material is sand and gravel. The record indicates that the so-called bridge survey map was meant. This was objected to on the ground that the exhibit spoke for itself. The answer was: “The indications are that it is sand and gravel that would be encountered in the excavation.” The evidence could not have prejudiced, because we think no other conclusions can be arrived at from an inspection of the exhibit by even a nonexpert.

The determination of this appeal is controlled by these propositions: (a) Did the bridge survey constitute a representation as to the character of the excavation for the abutments of the bridge upon which defendant had a right to rely? and (b) being untrue, did the defendant establish its right to rescission so as to recover the reasonable value of the work done?

Although the bid and contract embraced 5 bridges, a specific price was named for each. The contract may therefore be treated [384]*384here a.s if made for the Willow River bridge alone. Already attention has been called to the fact that the advertisement for bids was made in the middle of winter when the ground was frozen and covered with deep snow, so that no examination could well be made to ascertain condition; that plaintiff had caused a so-called bridge survey map to be made which contained statements as to the character of the soil to be dealt with, and that this was not only for its own information, but also for the information of prospective bidders. In this situation the authorities almost invariably support the proposition that the bidders have a right to rely upon positive representations respecting conditions to be found, unless a mere inspection reveals their falsity. The court could well conclude that, at the time plaintiff invited bids, no ordinary inspection would have disclosed the character of the material to be excavated. True, no active fraud or even negligence is claimed, in imparting the information that was given to bidders by either the bridge survey map or the oral statements of the engineer; but the court found, as defendant claimed, that a mutual mistake existed in regard to the condition of the excavation. This permits equity to grant the relief of rescission.

Courts have so held in cases on facts similar to the case at bar. Long v. Athol, 196 Mass. 497, 82 N. E. 665, 17 L. R. A. (N. S.) 96; Faber v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zontelli & Sons, Inc. v. City of Nashwauk
373 N.W.2d 744 (Supreme Court of Minnesota, 1985)
Enviro-Fab, Inc. v. Blandin Paper Co.
349 N.W.2d 842 (Court of Appeals of Minnesota, 1984)
United States v. Reserve Mining Company
394 F. Supp. 233 (D. Minnesota, 1974)
L. J. McNulty, Inc. v. Village of Newport
187 N.W.2d 616 (Supreme Court of Minnesota, 1971)
McCree & Company v. State
91 N.W.2d 713 (Supreme Court of Minnesota, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
199 N.W. 104, 159 Minn. 380, 1924 Minn. LEXIS 644, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stanton-v-morris-construction-co-minn-1924.