Elkan v. Sebastian Bridge Dist.

291 F. 532, 1923 U.S. App. LEXIS 2853
CourtCourt of Appeals for the Eighth Circuit
DecidedJune 6, 1923
DocketNos. 5980-5982
StatusPublished
Cited by15 cases

This text of 291 F. 532 (Elkan v. Sebastian Bridge Dist.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elkan v. Sebastian Bridge Dist., 291 F. 532, 1923 U.S. App. LEXIS 2853 (8th Cir. 1923).

Opinion

STONE, Circuit Judge.

This is a bill by Elkan against the Sebastian Bridge District to cancel a contract and for an accounting covering the value of the work done by plaintiff thereunder in partially constructing a bridge across the Arkansas river at Ft. Smith, Ark.

The answer of the district included a cross-bill praying that the contract be affirmed, that the Fidelity & Deposit Company of Maryland, surety on Elkan’s construction contract bond, be made a party, and that recovery for failure to perform the contract be given it against Elkan and against the surety. The surety answered praying discharge from the bond. By subsequent pleadings the issues were settled and a trial on the merits resulted in a decree dismissing Elkan’s bill for want of equity and sustaining recovery on the cross-bill in the sum of $101,082.67.

From this decree, all three parties have separately appealed.

The 'bases of the bill were fraudulent misrepresentations and mutual mistake concerning the sub-soil conditions where the excavations for the bi'idge supports were to be made and concerning the presence of gravel which would be useful to the contractor in the portions of the structure to be formed from concrete. The basis of the cross-bill was failure to perform the contract. The basis of the answer of the surety was release for the reasons set forth in Elkan’s bill and also for certain changes, alterations in and deviations from the contract.

The errors here urged by Elkan are:

(1) In holding that the contractor, under the plans and specifications, assumed the risk of sub-surface conditions and that the presence of quicksand and the absence of soft shale and soapstone constituted no misrepresentation or breach of warranty.

(2) In holding there was no misrepresentation by the district with reference to the availability of gravel to be used in mixing the concrete.

(3) In holding that the requirement of the engineer that the part of the piers between the footing and spring line of the arches should be constructed of a higher grade of cement was no deviation from the contract.

(4) In holding that successive changes in the construction of pier No. 2 required by the district engineer were not deviations from the contract.

The errors here urged by the surety are the four just stated and also:

(5) In holding that construction of the west or Oklahoma side approach to the bridge was not a variation in the contract.

The errors urged by the district .are that the court held the west approach to the bridge not within the contract and that the court entered a final decree for $101,082.67, based upon estimates of the cost necessary to complete the bridge by contractors who had replaced Elkan, instead of waiting until the bridge was completed and securing the actual total loss which would then be ascertainable.

Because of the nature of the questions presented by the appeal of the district, we will consider first the appeals of Elkan and of the surety company with the view of determining whether the decree was for the proper party.

[535]*535In the consideration of these two appeals, attention will be given first to the points involved in the Elkan appeal, as they are also involved in the surety company appeal; and if the decree is determined to be proper as to Elkan, examination will then be made of those contentions peculiar to the surety company.

The district was organized under a specific statute of the state of Arkansas for the purpose of constructing and empowered to construct a bridge across the Arkansas from a point in Et. Smith, Ark., to the Oklahoma side. Elkan contracted to build this bridge and the surety company executed the required bond to secure performance of this contract. After he had constructed a considerable portion of the bridge, Elkan ceased work and brought this action for cancellation of the contract and for accounting in relation to the 'work done. In the printed brief, his counsel state the substance of the grounds for the suit to be that:

“He charged that false representations were made with regard to sub-surface conditions at and before the, execution of the contract and that the contract as entered into between himself and the Bridge District was executed under a mutual mistake of fact as to the subject matter of the contract. He claimed that the false representations and mistake consisted in the positive representations of the engineer as to the truth of the matter shown on the boring sheet with reference to the sub-surface and under-water conditions and that these conditions were untrue, particularly with reference to the material for the excavations for the abutments and bents for the approach and as to the location of the soft shale and soapstone in the bed of the river.”

The points urged here are (1) that the contract was based upon certain representations to the contractor concerning sub-soil conditions which he would encounter in his work and that these representations were mistakenly or fraudulently untrue; (2) that it was falsely represented that a sufficient supply of gravel suitable for concrete mixture was near the bridge site; (3) that the requirement by the engineer that portions of the piers (above the footing and below the spring line of the arches) he constructed of a more expensive concrete mixture was a deviation from the contract; (4) that changes in the construction of pier No. 2, required by the engineer, were deviations from the contract. A careful examination of' the pleadings and the issues made thereby reveals that Elkan claimed the right to annul the contract and recover on a quantum meruit. This is his only claim. That claim is based solely upon misrepresentations as to sub-soil and gravel conditions. Therefore, although Elkan has presented to this court the points of the concrete mixture and of changes in construction of pier No. 2, they can and will be considered only from the standpoint of the surety company, which properly raised those issues.

Sub-Soil.

The sub-soil conditions involved are of two general classes: Presence of quicksand, which was encountered at the site of the abutment A, on the east end of the bridge, and at the site of one of the pedestals supporting the approach to the east end of the bridge; absence of soft shale and soapstone immediately overlying the bedrock upon which certain of the piers were to rest. The bearing of these sub-soil conditions upon the work is that it was much more difficult and expensive to go through quicksand to bedrock in the construction of abutment A [536]*536than through clay and other soft sustaining substances which was what was anticipated at this Jxfint; that the presence of quicksand at the pedestal site required the contractor to go much deeper at materially greater expense in order to find a suitably solid base for the pedestal; that the absence of soft shale and soapstone overlying the base rock at the pier sites made unsuitable the cofferdam method of construction which would have been entirely suitable to this overlying soft rock and which method the contractor had adopted and was employing because of the supposed presence of the soft rock, thus greatly and expensively changing working conditions.

Recognizing the materiality and importance of these sub-soil conditions, we turn to the claims of Elkan and the surety company respecting the liability therefor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S & M Constructors, Inc. v. City of Columbus
434 N.E.2d 1349 (Ohio Supreme Court, 1982)
L. J. McNulty, Inc. v. Village of Newport
187 N.W.2d 616 (Supreme Court of Minnesota, 1971)
Craig v. Thompson
177 F.2d 457 (Eighth Circuit, 1949)
Scherrer v. State Highway Commission
80 P.2d 1105 (Supreme Court of Kansas, 1938)
Commissioners of Sewerage of Louisville v. Davis
88 F.2d 797 (Sixth Circuit, 1937)
In re Cuban-Atlantic Transport Corp.
57 F.2d 963 (Second Circuit, 1932)
Johnston v. Ouachita Nat. Bank of Monroe
40 F.2d 604 (Eighth Circuit, 1930)
Wolfberg v. State Mut. Life Assur. Co. of Worcester
36 F.2d 171 (Eighth Circuit, 1929)
Mansbach v. United States
11 F.2d 221 (Third Circuit, 1926)
Sebastian Bridge Dist. v. Hedrick
4 F.2d 346 (Eighth Circuit, 1925)
E. J. Lord v. Territory of Hawaii
27 Haw. 792 (Hawaii Supreme Court, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
291 F. 532, 1923 U.S. App. LEXIS 2853, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elkan-v-sebastian-bridge-dist-ca8-1923.