Commissioners of Sewerage of Louisville v. Davis

88 F.2d 797, 1937 U.S. App. LEXIS 3249
Court of Appeals for the Sixth Circuit·Decided March 5, 1937·No. Nos. 7411, 7412·Published·Cited by 7 cases

Opinion

HICK.S, Circuit Judge.

On August 24, 1928, A. A. Davis and E. D. Davis, citizens and residents of Oklahoma City, and copartners doing business as A. A. Davis & Co. (herein called the Company), entered into a contract with the Commissioners of Sewerage of the City of Louisville (hereinafter called the Commission), for the construction of 8,544.54 linear feet of concrete sewer in open trench. The sewer, called the Highland Park-Beechmont Sewer, varied in size at different points but required the excavation of a trench roughly 18 feet wide and 15 to 25 feet deep, with a shallow trench 6 to 8 inches deep in the floor of a portion of it for an underdrain. The contract [798] called for its completion in 270 days, with a penalty of $25 per day for each day taken in excess thereof; 206 extra days were taken, although about 40 of these were allowed by the engineer on account of bad weather.

On or about July 1, 1928, the Commission advertised in trade journals that on July 20 it would receive bids or proposals for the construction of the sewer. The advertisement stated that the work would involve approximately “9,470 Lin. ft.— Earth Excavation in open trench. * * * Payment for earth excavation will be by the linear foot and cubic yard, concrete by the cubic yard and steel by the pound.” The description of the project was contained in a printed book of nearly 200 pages, copies -of which were used by the Commission for all its sewer jobs, of which it had many. Blanks were left in the books into which the separate specifications and figures for each job could be inserted by hand. Much of the printed material, of course, applied to all jobs, but inapplicable portions were crossed out with ink. This particular issue of the book bore on its cover, among other things, the notation that it applied to “Contract 40” and that it contained “Information for Bidders” and “Specifications for the Construction of Highland Park-Beechmont Sewer.” On the sixth page under the heading “Drawings,” and under the general heading “Information for Bidders,” appeared this statement : “The location and the general character of the work to be done under this Contract are shown upon Drawings in the office of the Commission entitled Contract No. 40 * * * dated June 15, 1928, and numbered” (listing sixteen numbers) “which are to be a part of this contract.”

On page 7, under the same general heading and under the specific heading “Quantities,” this appeared:

“The following is an approximate statement of the engineer’s estimate of the extent of the work required. * * *
“Item la. Earth excavation and hack-fill for 12' 2" x 7' 9" rectangular sewer from Sta. 1 plus 12.03 to Sta. 10 plus 24.34 —912.31 linear feet.” (Italics ours.)

Then followed five other items aggregating (exclusive of a section later left out of the contract by agreement) the linear feet of earth excavation and backfill upon which bids were asked. The quantities of concrete were set up in other items on a cubic yard basis and reinforcing steel on a pound basis. In the second general section entitled “Proposals,” the bidder was directed to quote prices on these same items of “earth excavation and backfill” at dollars and cents per linear foot and the concrete on the cubic yard basis and the iron on a pound basis. On page 95 under the general heading “Specifications” appeared the most disputed language in the contract:

“Earth Excavation

“Earth Defined.

“Section 1.1. The word 'earth,’ when used in these Specifications, shall mean all kinds of materials including old masonry, excavated or which are to be excavated. except rock as hereinafter defined:”

The line struck out was originally a part of the printed specifications but was crossed out with ink and a period placed in ink after the word “excavated.”

On page 94, for instance, the word “rock” was struck out everywhere it appeared under the section “Payment Line.” And elsewhere in the specifications all references to rock were scrupulously deleted by crossing out.

Prior to completion of the drawings and calling for bids, employees of the Commission made 19 borings along the line of the work. On account of street traffic only one of the borings was made on the center line of the sewer. The others ranged from 8 to 31 feet on one side or the other of the center line, and the exact location of each was indicated on the drawings. The borings were made with a sand or earth auger similar to a posthole digger type of auger, so that the samples of the material through which it passed could be brought up, noted, and preserved. All of these materials, such as cinders and gravel in filled ground, yellow clay, and various shades and consistencies of blue clay, etc., were recorded on the drawings, along with the thickness of each stratum thereof. Twelve of these borings were carried to subgrade or lower. Seven, namely, Nos. 8, 9, 10, 11, 1*2, 15, and 18, were stopped by a hard substance before reaching subgrade. These borings were stopped respectively at .2 feet, 5 feet, 7.2 feet, 2.8 feet, 2.2 feet, 4.5 feet, and 1.4 feet higher than subgrade. In each instance the auger, which with extensions weighed roughly 100 pounds, was smashed and churned against the obstructing material, so that small pieces were splintered off and brought to the surface. The samples from each hole were placed in separate' fruit jars and were carefully [799] labeled to show the name of the project to which they were related, the number of the boring at which they were taken with the station, the depth at which they were encountered, and their nature (as “Yellow Clay”). In each instance where the boring did not penetrate to subgrade, the substance that stopped it was marked on the drawings as “shale” and the samples thereof placed in the jars were likewise so labeled.

The borings were made by a crew of men under the general supervision of Howard F. Stolz, junior engineer with the Commission. The samples obtained were then carried to the Commission’s chemical laboratory and kept on display along with samples of borings from numerous other projects.

Free access — add to your briefcase to read the full text and ask questions with AI

Commissioners of Sewerage of Louisville v. Davis, 88 F.2d 797, 1937 U.S. App. LEXIS 3249 (6th Cir. 1937).

88 F.2d 797 (Commissioners of Sewerage of Louisville v. Davis) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related