Bush Building Co. v. City of Barbourville

155 F. Supp. 394, 1957 U.S. Dist. LEXIS 2945
CourtDistrict Court, E.D. Kentucky
DecidedOctober 9, 1957
DocketNo. 725
StatusPublished
Cited by2 cases

This text of 155 F. Supp. 394 (Bush Building Co. v. City of Barbourville) is published on Counsel Stack Legal Research, covering District Court, E.D. Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bush Building Co. v. City of Barbourville, 155 F. Supp. 394, 1957 U.S. Dist. LEXIS 2945 (E.D. Ky. 1957).

Opinion

HIRAM CHURCH' FORD, Chief Judge.

On May 19, 1950, the City of Barbour-ville, Kentucky, hereinafter referred to as “City”, entered into a contract with a firm of civil engineers of Cincinnati, Ohio, doing business as a partnership under the firm name of Alfred LeFeber <& Associates, which consisted of Alfred LeFeber, as principal, and Howard J. Kern, and Horace H. Mace, as associates, hereinafter referred to as “LeFeber”, to prepare the necessary plans, specifications and cost estimates of a coordinated program for water and sewerage improvements for the City, to receive and tabulate proposals and to assist the City in awarding construction contracts and to furnish general supervision of construction and all professional engineering services required to protect the City’s interest.

Pursuant to the contract, LeFeber prepared plans and specifications for the fulfillment of the coordinated program setting out in detail the specific plans, specifications and requirements for the ■construction of water mains, water storage reservoir, water treatment plant, sewers and pumping stations and a sewage treatment plant, together with numerous general provisions covering the program, all of which, with the construction contract, are bound in one volume filed in the record.

On August 13, 1952, the plaintiff Bush Building Company, a Tennessee corporation, hereinafter referred to as “Contractor”, entered into a single contract with the City, by the terms of which the ■Contractor covenanted and agreed, in consideration of the payment specified, to furnish at its own cost and expense all labor and materials necessary to complete the construction as provided by the plans, specifications and general provisions prepared by LeFeber. The different improvements embraced in the program are described as Contracts Nos. 1, 2, 3, 4 and 5, with further provisions showing the parties intended the improvement program to be completed ready for operation and use “as a whole”.

In the fall of 1952, the Contractor entered upon the performance of the work.

On May 6, 1954, plaintiff Contractor filed its original Complaint alleging full and complete construction of the water mains, storage reservoir, water treatment plant and sewage treatment plant, referred to as Contracts Nos. 1, 2, 3 and 5, respectively, and alleging final approval and acceptance thereof by the resident engineer and consulting engineer assigned to the work. This original Complaint did not claim completion of the sewers and pump stations. After having amended the original Complaint, plaintiff, on November 9, 1954, filed its Substituted Complaint in the place and stead of its original Complaint as amended, by which it alleged full and complete performance of all the improvements in strict conformity with the provisions of the contract documents; that the necessary prerequisite to final payment in the form of Engineer’s certificates of final acceptance and approval had been complied with; that the decision of the Engineer in these matters is final and binding upon the parties; that there was a balance due and payable to plaintiff in the sum of $60,949.05, exclusive of the amount retained by the City as a guaranty. It further claimed that the City was indebted to it in the additional sum of $4,143.82 for work and labor done in addition to that required under the contract documents, and it sought judgment for the total sum of $65,092.87.

On October 3, 1955, plaintiff filed its final Supplemental and Amended Complaint alleging that on September 7 and September 13, 1955, LeFeber directed plaintiff to perform certain work in re[397]*397speet to the contracts referred to in its substituted Complaint in order for plaintiff to be entitled to the payment of the 3% guaranty fund provided for in the contract documents, and that on September 15, 1955, the defendant wrongfully prevented the plaintiff from performing such work which it was ready and willing to perform, and reiterated and reaffirmed all the allegations of its substituted Complaint and asserted the right to receive the additional balance retained by the City under the guaranty provisions of the contract and sought judgment for the total sum of $98,797.77.

By Answers, as amended and supplemented, the defendant put in issue all the material allegations of the plaintiff’s pleadings, and filed its counterclaim against the plaintiff for damages in the sum of $500,000 on account of alleged failure of plaintiff to perform its agreements. Defendant also filed a Third Party Complaint against LeFeber asserting that if it be determined that LeFeber had executed the final certificates evidencing final completion and acceptance of full and complete performance of the contracts by the plaintiff and by reason thereof plaintiff was entitled to recover judgment against the defendant, and the counterclaim of the defendant was denied, LeFeber was liable to the City for damages in the sum of $ifo0,000 by reason of fraud, negligence and fraudulent collusion in executing such certificates of final approval and acceptance, and defendant sought judgment against LeFeber for such damages. LeFeber filed Answer putting in issue the allegations of the Third Party Complaint.

Upon the evidence presented at the trial, which began on October 3, 1955, and concluded on February 10, 1956, the Court’s Findings of Fact and Conclusions of Law are hereinafter stated.

The total amount agreed to be paid for all improvements covered by the contract was the sum of $694,098.09 allocated to the several improvements as follows :

Contract No. 1 — Water Mains $ 94,259.98
Contract No. 2 — Storage Reservoir 32,244.40
Contract No. 3 — Water Treatment Plant 159,668.49
Contract No. 4 — Sewers and Pumping Stations 312,458.87
Contract No. 5 — Sewage Treatment Plant 95,448.35

Prior to the institution of the action, upon monthly estimates made by the Engineer, the City had paid plaintiff $598,-444.14 leaving an unpaid balance of $95,-653.95 including $34,704.90, the amount retained by the City under the guaranty provision of the contract.

The provisions of the contract which seem pertinent in considering the problems presented are as follows:

“General Provisions

“1. Definitions:

* * * * * •»

“Wherever the word ‘Engineer’ occurs herein it shall be taken to mean Alfred LeFeber, Consulting Engineer, or a duly accredited representative thereof. (P. 25)

* * * * * *

“3. Engineer’s Duties and Authority:

The Engineer shall have authority to appoint such assistants and inspectors as may be necessary to represent him in his absence from the work; they shall keep the Engineer informed as to the progress of the work, the character of the materials furnished and the manner in which the work is being done; they shall call the attention of the Contractor to any infringement upon the plans or specifications; they shall have authority to reject defective materials and to suspend any work which is being improperly [398]*398done, subject to the final decision of the Engineer. Neither the Engineer nor his assistants are authorized to revoke, alter, enlarge or relax the provisions of these specifications. (P. 25)

******

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McGovney & McKee, Inc. v. City of Berea, Ky.
448 F. Supp. 1049 (E.D. Kentucky, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
155 F. Supp. 394, 1957 U.S. Dist. LEXIS 2945, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bush-building-co-v-city-of-barbourville-kyed-1957.