Scherrer v. State Highway Commission

80 P.2d 1105, 148 Kan. 357, 1938 Kan. LEXIS 193
CourtSupreme Court of Kansas
DecidedJuly 9, 1938
DocketNo. 34,007
StatusPublished
Cited by5 cases

This text of 80 P.2d 1105 (Scherrer v. State Highway Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scherrer v. State Highway Commission, 80 P.2d 1105, 148 Kan. 357, 1938 Kan. LEXIS 193 (kan 1938).

Opinion

The opinion of the court was delivered by

Smith, J.:

This was an action for money. Judgment was for defendant sustaining a demurrer to the petition. Plaintiff appeals.

The petition first stated the formal allegations necessary. It then alleged that plaintiffs on June 13,1936, entered into a contract with defendant to construct a portion of the state highway system. Under the terms of the contract the advertisement, proposal, bond, specifications and plans were all made a part of the contract and were made a part of the petition. The petition then stated that defendant, in its request for bids, stated:

“Detailed information of the work to be done may be had by an examination of the plans and specifications on file ... at the offices of the State Highway Commission.”

The petition also stated that the contract price provided was to be the fixed price per cubic yard for all material moved without [358]*358consideration as to whether this material might be earth or rock; that as a basis for computing the bid upon such work, and to arrive at an unclassified bid for the removal of all material of every kind it was necessary that such bidders have information as to the character of material to be moved and for the proportionate amount of each class so as to determine a fair average cost of the moving of all of such material as a whole at a fixed unclassified price per cubic yard.

The petition then stated that plaintiffs procured from defendant the plans, profiles and cross sections showing in detail how the work was to be constructed, and the amount of earth, rock and other material that would be encountered and the different character and classifications of it; that from such plans ’and cross sections furnished by the defendant and in reliance thereon plaintiffs computed the cost of moving each of the different classes of materials of the kind thereof in the amounts as shown in such plans, and from such amounts and costs computed the average cost of moving such material and from such computation so made plaintiffs submitted to the defendant a proposal to move all of such material at a cost of thirty cents per cubic yard, which was a fair and reasonable price based upon the quantities and proportions of the various classes of material involved, as shown by such plans and cross sections. The petition then alleged the completion of the contract and its acceptance by defendant. It also alleged that by the plans and specifications defendant represented the material to be moved was in accordance with the figures shown on these plans and profiles and cross sections, but that the information thus furnished was incorrect because it was represented that there were 54,850 yards of rock, while, as a matter of fact, plaintiffs were required to move 93,386.4 yards; that the fair value of the labor of moving this rock was 75 cents a cubic yard, or $70,039.80. The petition then alleged that plaintiffs relied solely upon these plans and cross sections; that they had no independent information of the classes of material to be moved, and that they would not have made the bid at the price that was in the contract had they known that proportions of the different classes of material to be moved were different from the amount represented; that as a result of the erroneous information received plaintiffs were required to perform additional labor that was not apparent from the erroneous cross sections; that they made an inspection of said premises and as a result of said inspection [359]*359found nothing out of the ordinary, and from the length of time allowed to make said bid had no other independent means of ascertaining the amount of rock to be moved at said place other than from said plans and cross sections; that these plans were prepared by agents of defendant after making borings and other technical lists and that defendant and its agents knew, or by the exercise of reasonable care should have known that the plans were misleading. The petition then alleged that the plans showed the following amounts of material to be moved:

Cu. yds.
Earth ..................................... 98,254
Borrow pit ................................ 74,161
Channel .................................. 83,071
Total 255,756
Rock ..................................... 54,850
Special ................................... 15,342
Total 325,948

The petition then alleged that they have been paid $102,461.31 for removing 341,537.7 yards of earth and rock; that this amount was computed as follows:

Cu. yds.
Earth ................................... 87,518.6
Borrow pit .............................. 83,106.3
Channel ................................ 69,037.7
Total 239,682.6
Rock ................................... 93,386.4
Special .................................. 8,468.7
Total ..........................,...... 341,537.7
341,537.7 cu. yds. @ 30tf =$102,461.31.

The petition alleged that they should have been paid as follows:

170624.9 cu. yds. @ .20............................. $34,124.98
Channels and Special 77506.4 cu. yds. @ .225........ 17,438.94
Rock, 93386.4 cu. yds. @ 75 ......................... 70,039.80
Total .......................................... $121,603.72

Plaintiffs prayed judgment for the difference between $121,603.72 and $102,461.31 or $19,142.41.

The demurrer of defendant to this petition was sustained on the ground that it did not state facts sufficient to constitute a cause of action. The appeal is from that judgment.

The story told by the petition is that defendant told plaintiffs [360]*360how much rock and how much earth there was to be moved; that plaintiffs had a right to rely on this statement; that they calculated the labor necessary to move this much rock and this much earth in the proportions given and made the bid accordingly; that when there was so much more rock than they figured on, this threw their calculations off, with the result that their bid was lower than it would have been had the proper proportions of rock and earth been shown; that they should be permitted to recover for the amount of rock removed, at a fair price.

It will be seen that the answer to this contention depends on whether plaintiffs were entitled to rely on the statements made by defendant as to the amount of earth and rock to be moved.

Plaintiffs point out G. S. 1935, 68-409. That section provides as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Codell Construction Co. v. Commonwealth
566 S.W.2d 161 (Court of Appeals of Kentucky, 1977)
Construction Aggregates Corp. v. State
170 A.2d 274 (Supreme Court of Connecticut, 1961)
State v. Hartford Accident & Indemnity Co.
70 A.2d 109 (Supreme Court of Connecticut, 1949)
Caribbean Engineering Co. v. Municipality of Ponce
60 P.R. 26 (Supreme Court of Puerto Rico, 1942)
Caribbean Engineering Co. v. Municipio de Ponce
60 P.R. Dec. 26 (Supreme Court of Puerto Rico, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
80 P.2d 1105, 148 Kan. 357, 1938 Kan. LEXIS 193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scherrer-v-state-highway-commission-kan-1938.