Clevco, Inc. v. Municipality of Metropolitan Seattle

799 P.2d 1183, 59 Wash. App. 536, 1990 Wash. App. LEXIS 404
CourtCourt of Appeals of Washington
DecidedNovember 5, 1990
Docket25267-4-I
StatusPublished
Cited by9 cases

This text of 799 P.2d 1183 (Clevco, Inc. v. Municipality of Metropolitan Seattle) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clevco, Inc. v. Municipality of Metropolitan Seattle, 799 P.2d 1183, 59 Wash. App. 536, 1990 Wash. App. LEXIS 404 (Wash. Ct. App. 1990).

Opinion

Pearson, J. *

Appellant Clevco, Inc., and its principals, James and Kaycee Clevenger and Kenneth and Brenda Clark (Clevco) appeal the trial court's order granting summary judgment in favor of respondent Municipality of Metropolitan Seattle (Metro) on Metro's motion and dismissing all of Clevco's alleged causes of action arising out of a wastewater sewer construction project in Medina and Bellevue. We hold that the trial court incorrectly interpreted the contract and that summary judgment should not have been granted.

In January of 1985 Metro issued a solicitation of bids for the construction of an underground sewer main in Medina. Accompanying the solicitation were the plans, specifications and drawings for the project. The plans and specifications contained information indicating the location of underground utilities in the vicinity of, and potentially conflicting *538 with, the proposed sewer. Only two major conflicts appear to have been indicated on the plans and specifications. Clevco relied on the plans and specifications in figuring the bid on the project, although the contract documents purported to inform the bidders that the information on the utility locations might not be complete. On the basis of the documents Clevco estimated that the job would take 2,600 labor hours to complete. Clevco submitted a bid of $1,574,900. On May 17, 1985, Clevco received notice that it had been awarded the contract, and on June 17, 1985, Metro instructed Clevco to begin performance.

In the course of performance Clevco discovered that there were numerous major utility conflicts with the planned sewer. As a result of these conflicts Clevco expended a total of more than 8,400 hours of labor on the project. Clevco's complaint alleged eight theories of recovery arising out of the construction project, including breach of contract, negligence and negligent misrepresentation and tortious interference with contractual relationships. The gist of Clevco's arguments is that Metro had breached the contract by failing to pay Clevco for the "extra" work resulting from the utility conflicts that had not been indicated in the construction plans, that Metro's employees owed a duty to Clevco to prepare the construction plans so as to show all of the existing utility conflicts, and that Metro's failure to pay Clevco for the extra expenses incurred as a result of the utility conflicts rendered Clevco unable to complete a separate construction contract causing a loss of the profits associated with that project.

Metro filed motions for summary judgment addressed to all of Clevco's theories of recovery, dividing Clevco's arguments into three inclusive theories: contract claims; non-contract claims; and claims for consequential damages. The trial court granted summary judgment on each of Metro's three motions and dismissed Clevco's complaint in its entirety.

Although the trial court did not set forth its reasoning for the rulings in favor of Metro, the parties agree in their *539 briefs that the basis for the trial court's ruling was the finding that one of the provisions of the contract between Clevco and Metro placed all risks for increased costs arising out of unanticipated utility conflicts on Clevco. The parties also stated that, as an alternative basis for its ruling, the trial court relied on the case of Dravo Corp. v. Metropolitan Seattle, 79 Wn.2d 214, 484 P.2d 399 (1971) as placing the burden of such costs on the contractor as a matter of law. Because we disagree with the trial court's interpretation of the contract and its interpretation of Dravo, we reverse the trial court's ruling and remand for further proceedings.

Discussion

In reviewing a summary judgment the appellate court engages in the same inquiry as the trial court. Sisters of Providence v. Snohomish Cy., 57 Wn. App. 848, 850, 790 P.2d 656 (1990). The present case presents questions of whether there is ambiguity in the contract between Metro and Clevco and of the legal effect of that written instrument. In general, these are questions of law, and will be reviewed as such on appeal. McGary v. Westlake Investors, 99 Wn.2d 280, 661 P.2d 971 (1983); Yeats v. Estate of Yeats, 90 Wn.2d 201, 580 P.2d 617 (1978).

I

The contractual provision relied upon by the trial court is section 1.18. That provision states:

Existing Utilities.
In general, the location of existing major utilities, whether above-ground or underground, are indicated on the drawings. This information has been obtained from utility maps and field surveys provided by the Municipality. The Municipality does not guarantee the accuracy or completeness of this information, and it is to be understood that other aboveground or underground facilities not shown on the drawings may be encountered during the course of the work. In any case, minor lines such as water, gas and sewer services, and sprinkler irrigation lines are not all indicated.
Underground utility service lines, including but not limited to, sanitary sewer services, gas services, water services, house or *540 yard drains, and electric or telephone services, shall be maintained, relocated, rerouted, removed, and restored by the Contractor with the least possible interference with such services and in no case shall the interference of such service lines be considered for extra compensation. For purposes of definition, services are defined as utilities extending from the utility in right-of-way or easement to the abutting private property.
Existing aboveground utilities, including but not limited to power transmission and distribution, telegraph, telephone, and traffic control systems, whether shown on the drawings or not, shall be maintained, relocated, rerouted, removed, and restored without extra cost as may be necessary by the Contractor in a manner satisfactory to owners and operators of the utilities and to the Municipality.
Existing major underground utilities and appurtenant structures, whether shown on the drawings or not, shall be maintained, relocated, rerouted, removed, and restored by the Contractor in a manner satisfactory to owners and operators of the utilities and to the Municipality. The Contractor shall arrange with the owners and operators of the respective utility systems to mark the location and, if necessary or prudent, to expose the existing utilities prior to construction of the facilities contained in this contract.
The right is reserved by owners of public utilities and franchises to enter upon any street, road, right-of-way, or easement for the purpose of maintaining their property and for making necessary repairs or changes caused by the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mike M. Johnson, Inc. v. Spokane County
150 Wash. 2d 375 (Washington Supreme Court, 2003)
Mike M. Johnson, Inc. v. County of Spokane
78 P.3d 161 (Washington Supreme Court, 2003)
Litho Color, Inc. v. Pacific Employers Ins.
991 P.2d 638 (Court of Appeals of Washington, 1999)
Litho Color, Inc. v. Pacific Employers Insurance
991 P.2d 638 (Court of Appeals of Washington, 1999)
State v. Nason
981 P.2d 866 (Court of Appeals of Washington, 1999)
Absher Construction Co. v. Kent School District No. 415
890 P.2d 1071 (Court of Appeals of Washington, 1995)
State v. Parada
877 P.2d 231 (Court of Appeals of Washington, 1994)
Syrovy v. Alpine Resources, Inc.
841 P.2d 1279 (Court of Appeals of Washington, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
799 P.2d 1183, 59 Wash. App. 536, 1990 Wash. App. LEXIS 404, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clevco-inc-v-municipality-of-metropolitan-seattle-washctapp-1990.