Nelson Construction Co. of Ferndale, Inc. v. Port of Bremerton

582 P.2d 511, 20 Wash. App. 321, 1978 Wash. App. LEXIS 2425
CourtCourt of Appeals of Washington
DecidedJune 5, 1978
Docket2658-2
StatusPublished
Cited by17 cases

This text of 582 P.2d 511 (Nelson Construction Co. of Ferndale, Inc. v. Port of Bremerton) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nelson Construction Co. of Ferndale, Inc. v. Port of Bremerton, 582 P.2d 511, 20 Wash. App. 321, 1978 Wash. App. LEXIS 2425 (Wash. Ct. App. 1978).

Opinion

*323 Soule, J.

Nelson Construction Company of Ferndale, Inc. (Nelson Construction) appeals from the trial court's dismissal of its action against the Port of Bremerton for increased costs of dredging in Puget Sound at the site of a planned Port Orchard Marina. We affirm the dismissal.

In September of 1971 the Port hired Reid, Middleton & Associates, Inc. (RMA), an engineering firm, to prepare detailed plans and specifications for construction of the proposed marina and to perform related engineering services. The project was designed to include a parking lot created from fill dredged up from a designated underwater area nearby.

RMA's application for a permit from the State Department of Fisheries contained the following language:

Description and Procedure of Work and Equipment To Be Used: Hydraulic dredging of harbor area and placement of dredged material behind berm for parking area fill.

This language was unknown to the contractors bidding for the dredging job, and the Fisheries permit did not limit the method of dredging to be allowed.

The Port also employed a soils engineering firm, Dames & Moore, to conduct a study of the soils in the project area. Their report was prepared in part from underwater borings in and near the area to be dredged. The report, submitted to RMA on August 24, 1973, contained the results of two test borings in the dredging area which failed to reveal any rocks larger than 2 inches in diameter. The report, however, cautioned that:

The recent marine sediments which occur just below the mudline in the dredge area may be satisfactorily excavated with a suction dredge. However, excavation of the glacially consolidated soils underlying the marine sediments will require a cutterhead-type dredge.

Excavation of the glacial soils is expected to be slow and difficult to accomplish and rocks of varying size may be encountered.

RMA subsequently prepared the plans and specifications for the project which were submitted to prospective bidders *324 for the dredging task. Included were the test boring data and a drawing indicating the presence of two boulders larger than 6 feet in diameter. The existence of the Dames & Moore soils report was not mentioned to prospective bidders, but section 2.05 of the specifications provides in part:

Soil borings indicate the presence of glacial consolidated soils within the area to be dredged. It is anticipated that special equipment will be required to remove this material.

A hydraulic dredging company, Marine Construction & Dredging, Inc. (Marine), was interested in bidding the dredging subcontract for the project. Marine's general manager, Kenneth Youngsman, conducted a prebid investigation of the dredging work, including the plans and specifications and test boring data. Mr. Youngsman, who had been involved with previous dredging in Puget Sound, called Lloyd Nelson, RMA's project manager for the job. Mr. Youngsman wanted clarification of the size of gravel likely to be encountered and the "special equipment" that might be needed to remove the "glacial consolidated soils." Mr. Nelson knew Marine was a hydraulic dredging company. He informed Youngsman the term "special equipment" meant a cutter head attachment on a hydraulic dredge, a device Marine had for use. 1 Nelson referred Youngsman to Mr. Larry Morrison of Dames & Moore for further information about the subsurface. Morrison told him the gravel did not exceed 2 inches. Youngsman did not ask if a soils report had been prepared, and there was conflicting testimony as to whether Nelson or Morrison told him about the Dames & Moore report.

The specifications in the hands of Mr. Youngsman cautioned in section 2.02 as follows:

*325 Exploration to determine the character of material to be removed by dredging has been performed by the Owner, and the results of the borings are shown on the drawings. The results of the exploration are submitted for information only, and the Owner assumes no responsibility for the accuracy of the exploration or the resulting data, nor does the Owner guarantee that no other materials will be encountered, or that the proportions of materials will not vary. It will be the responsibility of the Contractor to make such investigations as he feels necessary before the time of bidding on this work.

Mr. Youngsman again called Mr. Nelson to inquire about rocks in the dredging area that could not be dredged hydraulically, specifically including the two large rocks drawn on the dredging plans. As a result, Mr. Nelson issued the following addendum No. 2 to the contract specifications:

"Existing rocks in the dredged area, as noted on the plans, shall be removed. Payment for said removal shall be incidental to the unit price bid per cubic yard for "Dredging to Specified Limits in Harbor." If other rock is encountered during the dredging operation which cannot be handled by normal suction dredging procedures, payment for the removal shall be negotiated on a force account basis."

The phrase "force account" in the addendum means on a time and materials basis.

Mr. Youngsman described this addendum as a "rock clause" of the sort sometimes inserted in a hydraulic dredging contract to provide for extra compensation if rocks appear which must be dredged by another method.

Apparently satisfied with the situation, Mr. Youngsman then submitted Marine's bid of $2.08 per yard for the dredging subcontract to Nelson Construction. Those parties agreed on a subcontract, with this exclusion: "Large rocks to be removed by Nelson Construction Company."

Nelson Construction thereupon incorporated Marine's bid for dredging into its bid for the overall marina project. Nelson Construction was awarded the contract, and on February 17,1974, Marine began dredging.

*326 During the second pass of the dredge, difficulties arose. Rocks were encountered with unexpected frequency, and many would not pass through the suction pipe and cutter-head. The cutter teeth were replaced, but still the required depth of dredging could not be achieved. Marine alleged to Nelson Construction and RMA that these conditions made it unfeasible to proceed with hydraulic dredging, and suggested that clamshell dredging be used. Marine ceased work after attempting a third pass. At that point, the general contractor sent a diver to inspect the dredging area, and he found some six boulders ánd numerous "cobbles" up to 24 inches in diameter. The diver reported, however, that hydraulic dredging could be used with a clamshell doing the "final touches."

On February 25, Nelson Construction wrote a letter to RMA claiming impossibility of performance and erroneous specifications. The letter demanded that further dredging be handled on a force account basis, as contemplated by addendum No. 2.

The Port and Nelson Construction did not negotiate at that point about additional costs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charles & Janice Wolfe, V State Dept Of Transportation
Court of Appeals of Washington, 2018
General Construction Company v. Public Utility District No. 2
380 P.3d 636 (Court of Appeals of Washington, 2016)
In Re The Custody Of N.j.r.s.
Court of Appeals of Washington, 2014
Arthur West v. Port Of Tacoma
Court of Appeals of Washington, 2014
Schermer v. Department of Social & Health Services
161 Wash. 2d 927 (Washington Supreme Court, 2007)
In Re Dependency of Schermer
169 P.3d 452 (Washington Supreme Court, 2007)
Basin Paving Co. v. Mike M. Johnson, Inc.
107 Wash. App. 61 (Court of Appeals of Washington, 2001)
Postema v. Pollution Control Hearings Bd.
11 P.3d 726 (Washington Supreme Court, 2000)
Postema v. Pollution Control Hearings Board
142 Wash. 2d 68 (Washington Supreme Court, 2000)
McLanahan v. FARMERS INSURANCE
831 P.2d 160 (Court of Appeals of Washington, 1992)
Clevco, Inc. v. Municipality of Metropolitan Seattle
799 P.2d 1183 (Court of Appeals of Washington, 1990)
PT & L. CONST. v. Dept. of Transp.
531 A.2d 1330 (Supreme Court of New Jersey, 1987)
P.T. & L. Construction Co. v. State, Department of Transportation
531 A.2d 1330 (Supreme Court of New Jersey, 1987)
Roy v. Goerz
614 P.2d 1308 (Court of Appeals of Washington, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
582 P.2d 511, 20 Wash. App. 321, 1978 Wash. App. LEXIS 2425, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nelson-construction-co-of-ferndale-inc-v-port-of-bremerton-washctapp-1978.