King County v. Vinci Construction Grands Projets/Parsons RCI/Frontier-Kemper, JV

191 Wash. App. 142
CourtCourt of Appeals of Washington
DecidedNovember 9, 2015
Docket70432-0-I
StatusPublished
Cited by5 cases

This text of 191 Wash. App. 142 (King County v. Vinci Construction Grands Projets/Parsons RCI/Frontier-Kemper, JV) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
King County v. Vinci Construction Grands Projets/Parsons RCI/Frontier-Kemper, JV, 191 Wash. App. 142 (Wash. Ct. App. 2015).

Opinion

Trickey, J.

¶1 — The Brightwater project was King County’s first major expansion of its wastewater treatment system since the 1960s. 1 It was intended to add capacity to county wastewater systems to deal with the increasing sewage from the growing region. 2 The new treatment system was to serve Snohomish County and King County residences and businesses. 3

¶2 In 2006, King County hired a joint venture of three firms—Vinci Construction Grands Projets; Parsons RCI; and Frontier-Kemper, JV (collectively VPFK) 4 —to construct *149 portions of the tunneling work for the project for a fixed price and within a specified time frame. VPFK obtained a bond for the over $200 million project from five surety companies (collectively the Sureties), which are the appellants/cross respondents on appeal.

¶3 VPFK encountered many difficulties during the construction of the tunnels, and the project was significantly delayed as a result. When VPFK failed to meet its contractual deadlines, King County retained another contractor to complete one of the tunnels.

¶4 King County then sued VPFK and the Sureties for default. The trial court ruled in favor of King County on three summary judgment motions, dismissing two of VPFK’s claims concerning differing site conditions and defective specifications.

¶5 Following a three-month trial, the jury found VPFK and the Sureties jointly and severally liable for King County’s single claim of default, awarding King County $155,831,471.00 in damages. The jury also awarded VPFK $26,252,949.00 in damages for some of the many claims VPFK submitted to the jury. The trial court awarded King County attorney fees and costs.

¶6 VPFK and the Sureties appeal. VPFK asserts numerous challenges to the summary judgment rulings, the jury instructions, and the trial court’s ruling excluding evidence. The Sureties appeal the trial court’s award of attorney fees. King County cross appeals, asserting that the trial court erred by denying its motion for judgment as a matter of law.

¶7 We affirm the trial court’s summary judgment, evi-dentiary, and jury instruction rulings challenged by VPFK. We also affirm the trial court’s denial of King County’s motion for judgment as a matter of law. Finally, we affirm the award of attorney fees to King County and award attorney fees to King County on appeal.

*150 FACTS

I. The Brightwater Project’s Conveyance System

¶8 The Brightwater project was comprised of two major components: (1) a new treatment plant and (2) a conveyance system composed of pipelines and pumps that would carry raw sewage to the treatment plant and, in turn, carry clean effluent from the plant to Puget Sound. 5 The conveyance system called for the construction of 13 miles of pipelines in underground tunnels, the excavation of which was divided into three contracts: tunnel segment BT-1 (East Contract), tunnel segments BT-2 and BT-3 (Central Contract), and tunnel segment BT-4 (West Contract). 6

II. The Contract Documents

¶9 King County (County) and its consultants began designing the Brightwater contract and the subcontracting documents in 2002. 7 They conducted site investigations and soil analysis, and drafted the specifications and the bid documents. 8 The County provided the bidders for the Central Contract with numerous bid documents (Contract Documents). These documents included the contract (Contract) itself and its “General Terms and Conditions” and “General Requirements” for performance of the Central Contract work, as well as two geotechnical reports to assist in preparing the bids—the “Geotechnical Data Report” (GDR) and the “Geotechnical Baseline Report” (GBR). 9

*151 a. The Contract

i. Selection of Slurry Tunnel Boring Machine

¶10 According to the County’s February 2004 “Predesign Report,” the new tunnel would be situated below the “groundwater table.” 10 External pressures below the groundwater table meant that the soil surrounding the future tunnel would be saturated with water. 11 These conditions required the use of a boring machine that could apply constant pressure to prevent the face of the tunnel from collapsing. 12 However, a limited number of tunnel boring machines were well suited for such conditions. 13 The Pre-design Report advised the County to use an earth pressure balance machine (EPBM) or a slurry tunnel boring machine (STBM). 14

¶11 The County selected an STBM over an EPBM because the BT-3 tunnel was anticipated to experience high pressures, and at the time, STBMs had the ability to operate in higher pressures than EPBMs. 15 The County incorporated the STBM specification into the Contract. 16

ii. Differing Site Conditions Clause

¶12 The Contract contained a “Differing Site Conditions” clause, which allowed VPFK to request an equitable adjustment in contract time or price if it encountered site conditions different from those indicated in the Contract Docu- *152 merits. 17 The Contract identified two categories of Differing Site Conditions: “Type I” and “Type II.” At issue here is a Type I “Differing Site Condition[ ] ,” defined as “[s]ubsurface or latent physical conditions at the site which differ materially from those indicated in the Contract Documents.” 18

iii. Interventions and Pressurized Conditions

¶13 The Contract also included provisions about interventions. 19 During an intervention, the contractor stops the tunneling and conducts an inspection or repair on the cutterhead (the front of the boring machine that contains the large soil-cutting tools). 20 The contractor needs to have a reasonable understanding of the ground conditions in order to choose the proper slurry and pressure specifications. The correct slurry and pressure levels enable the STBM to support the tunnel face during excavations and interventions.

Related

Cite This Page — Counsel Stack

Bluebook (online)
191 Wash. App. 142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/king-county-v-vinci-construction-grands-projetsparsons-washctapp-2015.