King County v. Vinci Constr. Grands Projets/Parsons RCI/Frontier-Kemper, JV

CourtWashington Supreme Court
DecidedJuly 6, 2017
Docket92744-8
StatusPublished

This text of King County v. Vinci Constr. Grands Projets/Parsons RCI/Frontier-Kemper, JV (King County v. Vinci Constr. Grands Projets/Parsons RCI/Frontier-Kemper, JV) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
King County v. Vinci Constr. Grands Projets/Parsons RCI/Frontier-Kemper, JV, (Wash. 2017).

Opinion

• .,. •.• : •• ~ 7• ',, ....... ~ ~ • t 1 • ~.-~~ i .. r' ,.;_ :·,.:..·.~.;,

This opinion was filed for 'fecor'd

at 6'i~M 0-W\ on\!vJ~ ~/Jill o~~ SUSAN L. CARLSON SUPREME COURT CLERK

IN THE SUPREME COURT OF THE STATE OF WASHINGTON

KING COUNTY, ) ) Respondent, ) ) v. ) No. 92744-8 ) VINCI CONSTRUCTION GRANDS ) ENBANC PROJETS/P ARSONS RCI/ ) FRONTIER-KEMPER, JV, a Washington ) Filed: __JUL OG 2017 joint venture, ) ) Defendant, ) ) LIBERTY MUTUAL INSURANCE ) COMP ANY, a Massachusetts corporation; ) FEDERAL INSURANCE COMPANY, an ) Indiana corporation; FIDELITY AND ) DEPOSIT COMPANY OF MARYLAND, a) Maryland corporation; ZURICH ) AMERICAN INSURANCE COMP ANY, a ) New York corporation; and TRAVELERS ) CASUAL TY SURETY COMP ANY OF ) AMERICA, a Connecticut corporation, ) ) Petitioners. ) ___________) King County v. Vinci Constr. Grands Projets, et al., No. 92744-8 - - - ------- -------------------- ----------------------- - - - - - - - ---! YU, J. --This case requires us to examine an award of attorney fees against

five surety companies following a three-month jury trial for breach of contract in a

public works project. The parties litigated the issue of whether three construction

firms had defaulted on a contract, thus triggering coverage under a performance

bond issued by the surety companies. At issue is whether the existence of a

statutory fee provision bars equitable remedies available at common law for

coverage disputes and whether the trial court correctly determined that segregation

between covered and uncovered fees was impossible. The Court of Appeals

affirmed the award of Olympic Steamship fees and held that the trial court did not

abuse its discretion in determining that the fees could not be segregated. Olympic

S.S. Co. v. Centennial Ins. Co., 117 Wn.2d 37, 811 P.2d 673 (1991). For the

reasons discussed below, we now affirm.

FACTUAL AND PROCEDURAL HISTORY

The underlying facts are not at issue here, having been resolved by a jury

trial and being unchallenged by petitioners on appeal. In 2006, King County

contracted with three construction firms-Vinci Construction Grands Projets,

Parsons RCI, and Frontier-Kemper JV (collectively VPFK)-to expand its

wastewater treatment system. This expansion entailed the construction of a new

treatment plant along with three new conveyance tunnels that would increase the

treatment system's capacity to manage additional sewage from both Snohomish

2 King County v. Vinci Constr. Grands Pro.Jets, et al., No. 92744-8

County and King County residents and businesses. Because the project would

impact public health, the environment, and local economic growth, King County

required substantial completion of the project by November 14, 2010.

VPFK won the bid to construct the second and third sections of the central

tunnel, which together would measure 18 feet in diameter and 31,700 feet in

length. Further, both sections of the tunnel were to be excavated concurrently.

Under the terms of the contract, VPFK secured a performance bond from five

surety companies: Liberty Mutual Insurance Company, Travelers Casualty and

Surety Company of America, Federal Insurance Company, Fidelity and Deposit

Company of Maryland, and Zurich American Insurance Company (collectively

Sureties). IfVPFK failed to perform under the terms of the contract, the

performance bond obligated the Sureties to step in and "promptly remedy the

default in a manner acceptable to [King County]." Clerk's Papers (CP) at 5542.

Throughout the project, VPFK encountered a number of difficulties with its

equipment and management. At the time of its bid, VPFK estimated it could dig

57 feet per day on the longest tunnel, yet during the course of construction it

averaged only 28 feet per day. VPFK's tunnel-boring machines broke down

numerous times, including one nine-month delay during which VPKF attempted

(and failed) to ease the tunnel's atmospheric pressure by removing groundwater

before repairing the stalled machine. VPFK submitted numerous change orders

3 King County v. Vinci Constr. Grands Projets, et al., No. 92744-8

and at one point agreed to establish a workshop of experts from various disciplines

to "'mutually review all aspects of the tunneling operation to develop strategies for

the remaining construction.'" Id. at 7046.

When it became clear that VPFK was not "prosecuting the Work with

sufficient diligence to achieve Substantial Completion within the Contract Time,"

King County declared VPFK to be in default and requested a corrective action plan

that would ensure completion within the contract's deadline. Id. at 576. VPFK

submitted its revised schedule to King County, estimating a completion date

several years past the contract's deadline and at a significantly greater cost. As a

result, King County entered into an interim agreement with VPFK to hire a

different contractor to complete a portion of the work.

King County notified the Sureties of its plan and requested that the Sureties

either cure VPFK's default themselves or agree to fund the new contractor.

Instead, the Sureties argued that performance was not required under the bond

because no breach had occurred. On April 19, 2010, King County filed suit against

VPFK and one of the sureties, Travelers Casualty and Surety Company of

America, claiming breach of contract and seeking declaratory relief that VPFK was

in default and that the Sureties were joint and severally liable. The remaining four

surety companies intervened, and together the Sureties, while denying coverage,

also adopted all of VPFK's defenses against breach of contract.

4 King County v. Vinci Cons tr. Grands Projets, et al., No. 92744-8

At trial, the jury was asked to consider whether "VPFK was in default of its

obligations under the Contract by failing to perform its work so as to ensure

substantial completion by the Contract deadline" and whether "the Sureties

breached their obligations under the Bond because the Sureties failed to pay King

County's costs and expenses incurred because ofVPFK's default." Id. at 9091.

The jury found in favor of King County and awarded nearly $130 million in

damages. Pursuant to Olympic Steamship, 117 Wn.2d 37, the trial court awarded

King County its attorney fees and costs totaling nearly $15 million. The trial court

further held that the fees could not be segregated because King County's claim

against the Sureties was intertwined and indistinguishable from its claim against

VPFK.

On appeal, the Sureties argued that Olympic Steamship did not apply

because the fee provisions of RCW 39.04.240 are the exclusive fee remedy in

public works contracts. Further, the Sureties disagreed with the trial court's

determination that the fees could not be segregated. The Court of Appeals

affirmed the award of fees, holding both that RCW 39.04.240 was not the

exclusive fee remedy and that the fees could not be segregated. King County v.

Vinci Constr. Grands Projets/Parsons RCI/Frontier-Kemper, JV, 191 Wn. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Magniac v. Thomson
56 U.S. 281 (Supreme Court, 1854)
Gregg v. Georgia
428 U.S. 153 (Supreme Court, 1976)
Marks v. United States
430 U.S. 188 (Supreme Court, 1977)
Ruckelshaus v. Sierra Club
463 U.S. 680 (Supreme Court, 1983)
Marx v. General Revenue Corp.
133 S. Ct. 1166 (Supreme Court, 2013)
Olympic Steamship Co., Inc. v. Centennial Ins. Co.
811 P.2d 673 (Washington Supreme Court, 1991)
Stephanus v. Anderson
613 P.2d 533 (Court of Appeals of Washington, 1980)
State Ex Rel. Lemon v. Langlie
273 P.2d 464 (Washington Supreme Court, 1954)
Transamerica Premier Insurance Co. v. Brighton School District 27J
940 P.2d 348 (Supreme Court of Colorado, 1997)
Allard v. First Interstate Bank of Washington, N.A.
773 P.2d 420 (Washington Supreme Court, 1989)
Washington Water Power Co. v. Graybar Electric Co.
774 P.2d 1199 (Washington Supreme Court, 1989)
State v. Smith
610 P.2d 869 (Washington Supreme Court, 1980)
Estate of Jordan v. Hartford Accident & Indemnity Co.
844 P.2d 403 (Washington Supreme Court, 1993)
Dayton v. Farmers Insurance Group
876 P.2d 896 (Washington Supreme Court, 1994)
Solnicka v. Safeco Ins. Co. of Illinois
969 P.2d 124 (Court of Appeals of Washington, 1999)
National Bank v. Equity Investors
546 P.2d 440 (Washington Supreme Court, 1976)
Masterclean, Inc. v. Star Insurance
556 S.E.2d 371 (Supreme Court of South Carolina, 2001)
Longview Fibre Co. v. Cowlitz County
790 P.2d 149 (Washington Supreme Court, 1990)
Cates Construction, Inc. v. Talbot Partners
980 P.2d 407 (California Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
King County v. Vinci Constr. Grands Projets/Parsons RCI/Frontier-Kemper, JV, Counsel Stack Legal Research, https://law.counselstack.com/opinion/king-county-v-vinci-constr-grands-projetsparsons-rcifrontier-kemper-jv-wash-2017.