Robert Akhtar And Gulnoor Akhtar, V. TTG, LLC

Court of Appeals of Washington·Decided August 28, 2023·No. 83849-1·Unpublished

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

TTG, LLC, a Washington limited liability company, No. 83849-1-I

Respondent, DIVISION ONE v. UNPUBLISHED OPINION

ROBERT AKHTAR; and GULNOOR JAHAN-AKHTAR, husband and wife,

Appellants,

TED THOMAS and JANE DOE THOMAS, husband and wife; and DUANE SCHOOLEY, husband and wife, d/b/a FIVE STAR FLOORING,

Third Party Defendants.

BIRK, J. — Robert Akhtar and Gulnoor Jahan-Akhtar’s home suffered from severe fire and smoke damage. The Akhtars contracted with TTG LLC to commence repair efforts and substantially expand the house. After protracted disputes over payments, progress on the house, and the Akhtars’ refusal to sign change orders, TTG terminated its services, recorded a lien against the property, and filed this action. The superior court awarded TTG damages for work the court found TTG had performed for which the Akhtars had not paid, together with prejudgment interest and attorney fees. We remand for recalculation of prejudgment interest, but otherwise affirm and award attorney fees and costs on appeal to TTG.

I1

In March 2017, a fire caused extensive damage to the Akhtars’ rental property (House) in Bellevue. The Akhtars had insurance coverage with Safeco Insurance Company of America. On April 18, 2017, Safeco preliminarily estimated the total cost of repairs to be $116,006.14. At times during the project, Safeco issued increased estimates based on items of work not contemplated in its earlier estimates. The Akhtars had a mortgage through Chase Bank. Safeco paid the insurance proceeds for repair and restoration to Chase. Chase released funds based on the percentage of work completed. A Chase inspector reviewed the percentage of completion of the work done and determined the amount Chase would disburse.

The Akhtars contacted Ted Thomas, owner of TTG, about performing repairs. The parties discussed the Akhtars’ desire to construct additions to the House that would significantly increase its size. In late June 2017, the parties agreed to have TTG begin demolition to explore the extent of the fire damage. TTG obtained a permit from the City of Bellevue and removed obviously destroyed parts of the House. TTG submitted a demolition invoice to the Akhtars for $13,514.00, which the Akhtars paid in full. TTG discovered additional required repairs not included in Safeco’s initial estimates.

On July 1, 2017, TTG provided Akhtar with a written proposal, which included all work itemized on Safeco’s estimate. On July 5, 2017, Akhtar executed

1 We incorporate unchallenged findings of fact which are accepted as true on appeal. In re Det. of L.S., 23 Wn. App. 2d 672, 686, 517 P.3d 490 (2022).

a contract with Thomas’s company IOAP, LLC, to prepare the design for the House expansion.

Thomas testified his initial repair estimate was $156,104.00. On July 19, 2017, TTG sent a revised estimate, signed and dated by Thomas, to Akhtar for $137,016.00. Thomas testified he revised the estimate to match Safeco’s then current estimate being held by Chase. Thomas did not believe the repairs could be accomplished for that amount, but anticipated further discussion of open line items with Safeco. In August, TTG sent a letter with the same revised estimate, again signed by Thomas on behalf of TTG. On or about August 14, 2017, TTG prepared a proposed written construction agreement (Contract), which listed TTG as the contractor and a total price of $137,016.00, and e-mailed it to Akhtar. The contract price equaled Safeco’s then current estimate. Article 5 of the Contract provided, “All change orders shall be in writing and signed both by Owner and Contractor, and shall be incorporated in, and become part of the contract.” Article 5 further provided, “Contractor may suspend work on the job until such time as all payments due have been made. A failure to make payments for a period in excess of 20 days from the due date of the payment shall be deemed a material breach of this contract.” While Akhtar never signed the Contract despite telling Thomas he would, Akhtar’s subsequent actions manifested his assent to the Contract.

After TTG commenced work under the Contract, it again discovered additional required repairs and code upgrades not included in Safeco’s initial estimates. In March 2018, Safeco increased its estimate to $185,611.37.

On or about April 2, 2018, the parties signed a written amendment (Amendment) to the Contract. The Amendment increased the Contract price to $185,000.00. It established a payment schedule pursuant to which the Akhtars paid TTG $22,500.00. Paragraph 18 of the Amendment permitted the Akhtars to order additions, deletions or modifications to the work, and the Akhtars agreed to make corresponding, applicable adjustments to the Contract price and time of completion. All changes “will be authorized in a written ‘Change Order’ signed by Owner and Contractor.” TTG would be permitted to recover, among other things, payment for all work completed.

Per the Amendment’s terms, the parties agreed the Akhtars’ next payment would become due when the project was at 70 percent completion. On September 6, 2018, the Akhtars paid $45,195.01 for the 70 percent project completion payment. The Akhtars’ payments to TTG totaled $130,044.46. The final payment was due on completion.

The Akhtars requested TTG perform additional work outside the scope of the Contract and Amendment. The scope of the work and TTG’s pricing for the Akhtars’ requests were generally described in six change orders. TTG asked Akhtar to sign the change orders, but he never did and instead stated that he wanted to sort them out after TTG completed all of its work on the project.

TTG attributed project delays to the time it took the City of Bellevue to provide permitting, the Akhtars’ changing intentions for the scope of work, and a setback issue that arose when Akhtar mistook the location of his lot line, among other things. TTG viewed certain change orders as impacting the ability to proceed

with the project. TTG declined to do additional work and work out payment terms only later.

TTG ceased its project work in April 2019. That month, Chase’s inspector valued the total loss amount at $205,798.08. Chase’s inspector estimated the work was 45 percent complete. TTG estimated the work was at least approximately 70 percent complete. On April 9, 2019, TTG recorded a claim of lien pursuant to chapter 60.04 RCW against the property.

On May 23, 2019, TTG filed a lawsuit against the Akhtars alleging breach of contract and requesting foreclosure of its lien. The Akhtars pleaded affirmative defenses, added Thomas and another party as third party defendants, and counterclaimed for breach of contract and violations of the Washington Consumer Protection Act, chapter 19.86 RCW. The Akhtars later added several affirmative defenses and a counterclaim for fraud.

Following a bench trial, the superior court found in favor of TTG and against the Akhtars. TTG’s further performance was deemed excused by the Akhtars’ refusal to sign the change orders. The court calculated the Akhtars owed TTG $14,014.20, which was determined by taking 70 percent of $205,798.08 and subtracting the Akhtars’ payments. The court awarded TTG prejudgment interest, reasonable attorney fees, and a decree of foreclosure. The court rejected the Akhtars’ counterclaims, but ordered TTG to return appliances that the Akhtars had purchased and TTG had stored and later withheld. The court entered final judgment in the amount of $52,466.14. The Akhtars appeal.

II

A

Free access — add to your briefcase to read the full text and ask questions with AI

Robert Akhtar And Gulnoor Akhtar, V. TTG, LLC, (Wash. Ct. App. 2023).

Robert Akhtar And Gulnoor Akhtar, V. TTG, LLC (Robert Akhtar And Gulnoor Akhtar, V. TTG, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lovric v. Dunatov
567 P.2d 678 (Court of Appeals of Washington, 1977)
Austin v. U.S. Bank
869 P.2d 404 (Court of Appeals of Washington, 1994)
CKP, Inc. v. GRS Construction Co.
821 P.2d 63 (Court of Appeals of Washington, 1991)
Modern Builders, Inc. v. Manke
615 P.2d 1332 (Court of Appeals of Washington, 1980)
Holland v. Boeing Company
583 P.2d 621 (Washington Supreme Court, 1978)
Hemisphere Loggers & Contractors, Inc. v. Everett Plywood Corp.
499 P.2d 85 (Court of Appeals of Washington, 1972)
Eastlake Construction Co. v. Hess
686 P.2d 465 (Washington Supreme Court, 1984)
Columbia State Bank, Res. v. Mark v. Jordan And Cynthia Jordan, Apps.
199 Wash. App. 306 (Court of Appeals of Washington, 2017)
Shelcon Construction Group, LLC v. Haymond
351 P.3d 895 (Court of Appeals of Washington, 2015)