Skanska Usa Building Inc., V. 1200 Howell Street, Llc

CourtCourt of Appeals of Washington
DecidedJanuary 22, 2025
Docket58950-8
StatusUnpublished

This text of Skanska Usa Building Inc., V. 1200 Howell Street, Llc (Skanska Usa Building Inc., V. 1200 Howell Street, Llc) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skanska Usa Building Inc., V. 1200 Howell Street, Llc, (Wash. Ct. App. 2025).

Opinion

Filed Washington State Court of Appeals Division Two

January 22, 2025

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II SKANSKA USA BUILDING INC., No. 58950-8-II a Delaware corporation,

Respondent,

v.

1200 HOWELL STREET, LLC, a Washington UNPUBLISHED OPINION limited liability company,

Appellant,

FIDELITY & DEPOSIT COMPANY OF MARYLAND, an Illinois Insurance Company; SOUND GLASS SALES, INC., a Washington corporation,

Third-Party Defendants,

SOUND GLASS SALES, INC., a Washington corporation,

Fourth-Party Plaintiff,

KAWNEER COMPANY, INC., dba ARCONIC, INC., a Delaware corporation; METTEMEYER ENGINEERING, LLC, a Missouri limited liability company; ECKERSLEY O’CALLAGHAN & PARTNERS, LLC, a New York limited liability company,

Fourth-Party Defendants.

GLASGOW, J.—In 2016, 1200 Howell Street LLC, hired Skanska USA Building Inc. to

construct the 41-story Nexus condominium tower in downtown Seattle. Howell then withheld part No. 58950-8-II

of Skanska’s contract balance and refused to pay Skanska for additional work that arose from

significant changes in design documents and other developments during construction.

In 2020, as it was finishing construction, Skanska recorded a lien on the Nexus tower

property. Skanska then sued Howell for breach of contract, breach of the duty of good faith and

fair dealing, and quantum meruit. Skanska also sought money to pay two subcontractor claims.

Skanska sought to foreclose on the lien.

Howell counterclaimed for negligent misrepresentation, breach of contract, and breach of

the duty of good faith and fair dealing. Howell sought liquidated damages under the contract for

Skanska’s delay in finishing the building and tort damages for negligent misrepresentation.

Pretrial, the trial court dismissed Howell’s negligent misrepresentation claim on partial

summary judgment. Howell did not move for summary judgment dismissal based on the plain

language of the parties’ contract regarding the format or time limits for requests for authorization

of additional work, additional costs, or additional time for substantial completion.

Near the end of a seven-week trial, Howell instead moved for a judgment as a matter of

law under CR 50, which the trial court denied without prejudice, allowing Howell to revive its

motion post verdict. The jury awarded Skanska the overwhelming majority of its claims and

awarded Howell limited liquidated damages on its breach of contract counterclaim. The net jury

award to Skanska was roughly $19.2 million.

The trial court denied Howell’s posttrial CR 50 motions for judgment as a matter of law or

a new trial. In addition to the base jury award, the trial court awarded Skanska approximately $5.1

million in prejudgment interest and $6.6 million in attorney fees, including fees for expert

2 No. 58950-8-II

witnesses and subcontractors’ attorney fees, for a total principal judgment of about $30.8 million.

The trial court also foreclosed Skanska’s lien on the Nexus tower.

Howell appeals. It argues that the trial court erred by dismissing its claim for negligent

misrepresentation on partial summary judgment. Next, Howell contends that the trial court abused

its discretion by excluding evidence alleging that Skanska generally mismanaged the project, and

by declining to give a jury instruction about that evidence. And Howell asserts that the trial court

erred by denying its CR 50 motions for judgment as a matter of law or a new trial. It further argues

that the trial court erred by foreclosing Skanska’s lien, awarding prejudgment interest, and

awarding Skanska attorney fees. Both parties seek attorney fees on appeal.

We reverse the amount of prejudgment interest awarded to Skanska and remand solely for

the trial court to recalculate the prejudgment interest for the limited number of authorization

request (AR) claims Skanska submitted to Howell after Skanska recorded the lien. Prejudgment

interest for those claims should begin to accrue on the day that Skanska submitted the AR claims

to Howell, rather than the earlier lien date. We otherwise affirm. We deny Howell’s request for

attorney fees on appeal and grant Skanska’s request for attorney fees on appeal.

FACTS

A. Background

1. Key contract provisions

Burrard Development LLC owned and managed Howell.1 In 2016, Howell hired Skanska

to build the Nexus tower. The parties initially negotiated a guaranteed maximum price contract for

1 The parties referred to Howell and Burrard interchangeably. We will refer to the defendants collectively as “Howell” throughout to avoid confusion.

3 No. 58950-8-II

approximately $152 million. The contract allowed Skanska to charge Howell for the actual costs

of building the Nexus tower, plus Skanska’s fee, a contingency fee, and a lump sum for certain

general overhead costs to run the project (known as general conditions and general requirements),

up to the guaranteed maximum price. The contract required Skanska to achieve substantial

completion by a particular date.

The guaranteed maximum price contract was based on architecture drawings that were only

60 percent complete. The contract allowed for a price amendment once the architect finished more

detailed final drawings. The contract referred to the anticipated final drawings as “‘100%

Construction Documents,’” but when the drawings were produced, the parties referred to them as

“Issued For Construction” documents. Ex. 46, at 4; Clerk’s Papers (CP) at 653. The contract

provided that when Howell authorized a change in the work that increased the actual cost of

construction, the guaranteed maximum price would increase by the same amount.

Several contract provisions set procedures and processes. Provision GC-24(A) of the

contract defined when the building would be substantially complete, requiring a temporary

certificate of occupancy from the city and completion of other benchmarks. If Skanska did not

substantially complete the building by a contractual date, it agreed to pay Howell $39,750 per day

in liquidated damages, up to 2.5 percent of the project’s price (about $4 million). And GC-25(C)

let Skanska seek extensions of the substantial completion date for excused delays, such as extreme

weather, as long as it notified Howell of the delay in writing within seven days.

Section GC-26 of the contract covered several key procedures regarding changes in the

work. GC-26(A) allowed Skanska to change its scope of work if Howell approved the change in

writing in a change order or change directive. GC-26(B) then stated that Skanska could not rely

4 No. 58950-8-II

on any course of conduct or dealing between the parties or claim of unjust enrichment to seek an

increase in the contract price or time for work. Skanska could rely on only Howell’s express

approval of price increases or time extensions. GC-26(C) listed methods the parties could use to

value changed work. If the parties could not agree on the price of the additional or changed work,

this provision let Skanska seek the actual cost of its work, with corresponding increases to

Skanska’s fee and the general conditions and general requirements sum. And GC-26(D) required

Skanska to submit written notice to Howell within seven days if any of Howell’s instructions

required extra cost or time to execute.

2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Dahl
705 P.2d 781 (Court of Appeals of Washington, 1985)
Prier v. Refrigeration Engineering Co.
442 P.2d 621 (Washington Supreme Court, 1968)
Coastal Building Corp. v. City of Seattle
828 P.2d 7 (Court of Appeals of Washington, 1992)
Bignold v. King County
399 P.2d 611 (Washington Supreme Court, 1965)
Sprague v. Sumitomo Forestry Co., Ltd.
709 P.2d 1200 (Washington Supreme Court, 1985)
Swenson v. Lowe
486 P.2d 1120 (Court of Appeals of Washington, 1971)
Washburn v. Beatt Equipment Co.
840 P.2d 860 (Washington Supreme Court, 1992)
Tanner Electric Cooperative v. Puget Sound Power & Light
911 P.2d 1301 (Washington Supreme Court, 1996)
Casa Clara Condo. Ass'n v. Charley Toppino and Sons, Inc.
620 So. 2d 1244 (Supreme Court of Florida, 1993)
SPRADLIN ROCK v. Public Utility Dist. No. 1
266 P.3d 229 (Court of Appeals of Washington, 2011)
Eastwood v. Horse Harbor Foundation, Inc.
241 P.3d 1256 (Washington Supreme Court, 2010)
Mike M. Johnson, Inc. v. County of Spokane
78 P.3d 161 (Washington Supreme Court, 2003)
Wm. Dickson Co. v. Pierce County
116 P.3d 409 (Court of Appeals of Washington, 2005)
In Re Marriage of Zigler and Sidwell
226 P.3d 202 (Court of Appeals of Washington, 2010)
Guijosa v. Wal-Mart Stores, Inc.
32 P.3d 250 (Washington Supreme Court, 2001)
Lehrer v. Dept. of Social & Health Servs.
5 P.3d 722 (Court of Appeals of Washington, 2000)
LAKEVIEW v. Apartment Sales Corp.
6 P.3d 74 (Court of Appeals of Washington, 2000)
Noble v. SAFE HARBOR PRESERVATION TRUST
216 P.3d 1007 (Washington Supreme Court, 2009)
DBM Consulting Engineers, Inc. v. US Fidelity & Guar. Co.
170 P.3d 592 (Court of Appeals of Washington, 2007)
Browne v. Cassidy
728 P.2d 1388 (Court of Appeals of Washington, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
Skanska Usa Building Inc., V. 1200 Howell Street, Llc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skanska-usa-building-inc-v-1200-howell-street-llc-washctapp-2025.