Wm. Dickson Co. v. Pierce County

128 Wash. App. 488
CourtCourt of Appeals of Washington
DecidedJuly 19, 2005
DocketNo. 31798-2-II
StatusPublished
Cited by21 cases

This text of 128 Wash. App. 488 (Wm. Dickson Co. v. Pierce County) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wm. Dickson Co. v. Pierce County, 128 Wash. App. 488 (Wash. Ct. App. 2005).

Opinion

¶1 The Wm. Dickson Company (Dickson) appeals an order dismissing its breach of contract lawsuit, arguing that material facts precluded summary judgment. We agree and reverse and remand for further proceedings.

Houghton, J.

FACTS

¶2 Pierce County (County) owns a gravel pit adjacent to Waller Road. Dickson is a construction company that owns a neighboring gravel pit.

¶3 In 1973, the County entered into a lease and real estate contract with Asphalt Paving & Engineering Company, one of Dickson’s predecessors in interest. In 1988, the [490]*490County filed suit, alleging that Dickson had not complied with the 1973 lease agreement. The parties attempted to settle the litigation.

¶4 On March 23, 1990, Dickson’s counsel, Thomas Dickson,1 sent a letter to Lloyd Nickel, counsel for the County. Mr. Dickson stated that this letter memorialized the parties’ settlement terms. In part, the letter provided that Dickson would convey seven acres to the County.2 It also described the County’s rights to dump fill on that land:

The county shall also have the right to fill the seven acres, provided however, that only the county and its equipment may perform the filling — not its agents (unless a branch or governmental subdivision of the county), non-county subcontractors, ! or non-county permittees.

Clerk’s Papers (CP) at 23.

¶5 In a letter dated December 12, 1990, William Hess informed Mr. Dickson that he now represented the County in this matter. He indicated that Dickson’s proposed settlement terms may not be acceptable:

In reviewing the County’s file I became familiar with your letter! ] to Mr. Nickel dated March 23, 1990 ... wherein you discussed your understanding of a proposed settlement. I would like to meet with you to make certain we are in complete agreement as to what has been proposed as a settlement agreement. The County may not be able to enter into the proposed settlement agreement [if] my understanding of it is correct.

CP at 28.

¶6 Nearly a year later, the parties entered a stipulated judgment. Drafted by the County, the stipulation provided that Dickson would convey seven acres to the County. Both parties could place fill on those seven acres:

[491]*4913. [Dickson] shall. . . have the right to place fill, and the right to allow third parties to place fill, on the [seven acres] for a period of time ending at the earlier date of either of the following two events:
a. The tenth anniversary of the date this judgment is approved and signed by the above court.
b. The date the placement of fill reaches a maximum elevation of 262 feet....
[The County] shall have the right to place fill at whatever location and to whatever elevation it deems appropriate, on the [seven acres] during the period of time that defendant may place fill on said lands, but shall not give third parties permission to place fill on said lands during that period of time.

CP at 32 (emphasis added). A judge signed and entered the judgment on December 2,1991. After entry of the judgment, the County owned 40 acres at the Waller Road site, a 7-acre parcel and a 33-acre parcel.

¶7 In 1995, Pierce County Surface Water Management constructed a major storm water management facility on Squally Creek. The County requested project bids, which included dumping into the Waller Road landfill. Dickson submitted an unsuccessful bid. Instead, the County accepted the bid of Tucci and Sons (Tucci).

¶8 As part of the Squally Creek project, Tucci dumped material into the Waller Road landfill. The parties agree that Tucci dumped about 135,000 cubic yards of fill. They dispute, however, when Dickson had notice of the dumping. They also disagree about whether Tucci dumped fill onto the 7 acres addressed in the stipulation or onto the remaining 33 acres of the landfill.

¶9 Between 1991 and 1997, Dickson dumped approximately 25,000 cubic yards onto the seven acres. In 1997, it stopped dumping because the pit reached an elevation of 262 feet, the height specified in the stipulation.

¶10 On March 22, 2002, Dickson filed a complaint, alleging breach of contract. Dickson claimed that the County allowed a third party to fill dump onto the seven acres, thereby preventing it from dumping. The Countys [492]*492answer asserted several affirmative defenses, including an allegation that the statute of limitations barred Dickson’s claim.

¶11 Both parties moved for summary judgment. The trial court entered summary judgment in the County’s favor.

¶[12 Dickson appeals.

ANALYSIS

Standard of Review

¶13 We review orders granting summary judgment de novo, engaging in the same inquiry as the trial court. Atherton Condo. Apartment-Owners Ass’n Bd. of Dirs. v. Blume Dev. Co., 115 Wn.2d 506, 515-16, 799 P.2d 250 (1990). We view the facts and all reasonable inferences therefrom in the light most favorable to the nonmoving party. Vallandigham v. Clover Park Sch. Dist. No. 400, 154 Wn.2d 16, 25-27, 109 P.3d 805 (2005). On review of any pleadings, depositions, answers to interrogatories, admissions, and affidavits on file, summary judgment is available if there is no genuine issue as to any material fact, thus entitling the moving party to judgment as a matter of law. Vallandigham, 154 Wn.2d at 25-27; CR 56(c).3 Summary judgment is appropriate if reasonable persons could reach but one conclusion. Wilson v. Steinbach, 98 Wn.2d 434, 437, 656 P.2d 1030 (1982).

Contract Claim

¶14 Dickson contends that the trial court erred when it (1) granted the County’s motion for summary judgment and (2) denied its motion for summary judgment.

[493]*493 ,¶15 Contract principles govern final judgments entered by stipulation or consent. Martinez v. Miller Indus., 94 Wn. App. 935, 942, 974 P.2d 1261 (1999). When interpreting a contract, our primary objective is to discern the parties’ intent. Tanner Elec. Coop. v. Puget Sound Power & Light Co., 128 Wn.2d 656, 674, 911 P.2d 1301 (1996). “Unilateral or subjective purposes and intentions about the meanings of what is written do not constitute evidence of the parties’ intentions.” Lynott v. Nat’l Union Fire Ins. Co., 123 Wn.2d 678, 684, 871 P.2d 146 (1994). “[Ejxtrinsic evidence is admissible as to the entire circumstances under which the contract was made, as an aid in ascertaining the parties’ intent.”4 Berg v. Hudesman, 115 Wn.2d 657, 667, 801 P.2d 222 (1990).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Steven F. Wiker v. United Services Automobile Ass'n
Court of Appeals of Washington, 2026
Skanska Usa Building Inc., V. 1200 Howell Street, Llc
Court of Appeals of Washington, 2025
Todd Skoglund, V. Sahalee Maintenance Association
Court of Appeals of Washington, 2024
Barbara Silvey v. Numerica Credit Union
Court of Appeals of Washington, 2022
Ihif Commercial, Llc, V. City Of Issaquah
Court of Appeals of Washington, 2022
Northwood Estates, Llc v. Lennar Northwest, Inc.
Court of Appeals of Washington, 2020
In re the Custody of: Z.C.
366 P.3d 439 (Court of Appeals of Washington, 2015)
Reed-Jennings v. Baseball Club of Seattle, LP
351 P.3d 887 (Court of Appeals of Washington, 2015)
Exterra Llc v. Cle Elum Gateway Property Llc
Court of Appeals of Washington, 2014
Microsoft Corp. v. Motorola, Inc.
854 F. Supp. 2d 993 (W.D. Washington, 2012)
Marshall v. Thurston County
267 P.3d 491 (Court of Appeals of Washington, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
128 Wash. App. 488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wm-dickson-co-v-pierce-county-washctapp-2005.