Northwood Estates, Llc v. Lennar Northwest, Inc.

CourtCourt of Appeals of Washington
DecidedMarch 3, 2020
Docket52000-1
StatusUnpublished

This text of Northwood Estates, Llc v. Lennar Northwest, Inc. (Northwood Estates, Llc v. Lennar Northwest, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwood Estates, Llc v. Lennar Northwest, Inc., (Wash. Ct. App. 2020).

Opinion

Filed Washington State Court of Appeals Division Two

March 3, 2020 IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II NORTHWOOD ESTATE, LLC, a Washington No. 52000-1-II State limited liability company,

Respondent,

v.

LENNAR NORTHWEST, INC., a Delaware UNPUBLISHED OPINION corporation,

Appellant.

GLASGOW, J.—Northwood Estate LLC contracted to sell 33 residential lots to Lennar

Northwest, Inc. In relevant part, an amendment to their agreement provided that if Northwood

successfully recorded an approved plat modification by a specified deadline, the number of lots

would increase by five and Lennar would pay Northwood an additional $765,000. When the

deadline passed without successful approval and recording, Lennar assumed control of the

modification application and refused to pay Northwood the additional $765,000. Northwood sued

Lennar for breach of contract and included alternative claims of quantum meruit and unjust

enrichment.

Lennar argued the relevant provision was an unsatisfied condition precedent excusing

Lennar from payment. The trial court ultimately agreed with Northwood that the plat modification

provision was instead a contractual obligation, and so Lennar was not excused from payment, but

it could seek damages for Northwood’s delay. The court granted summary judgment to Northwood No. 52000-1-II

on its breach of contract claim and granted summary judgment to Lennar rejecting the quantum

meruit and unjust enrichment claims.

Lennar obtained discretionary review of the breach of contract decision. Northwood

counters that the trial court was correct to rule in its favor because treating the provision as a

condition precedent would result in forfeiture, and forfeitures are disfavored. In the alternative,

Northwood argues that if the provision was a condition precedent, we should employ equitable

remedies to prevent the forfeiture of $765,000 that would result from enforcement of the condition.

In that event, Northwood asks that we reinstate its equitable claims.

We reverse the trial court’s conclusion that the plat modification provision was a

contractual promise and its grant of summary judgment to Northwood on this basis. We hold that

the relevant provision created a condition precedent and recognize that conditions precedent

should not be strictly enforced if they effectuate a harsh forfeiture. We remand to the trial court

to determine whether any equitable relief is appropriate to prevent forfeiture in this case and, if so,

what form that relief should take.

FACTS

In December 2015, Northwood entered into a purchase and sale agreement to sell 33

residential lots in the city of Edgewood, Washington to Lennar for $153,000 per lot. Paragraph 2.3

of the agreement provided that Northwood would obtain, at its expense, a plat modification to

convert 8 of the lots into 13 separate lots, increasing the total number of lots by 5. If the plat

modification was recorded within a year after closing, Lennar would pay Northwood an additional

$765,000. If Northwood could not meet that deadline, it could extend the plat modification

deadline once for up to three months.

2 No. 52000-1-II

Paragraph 2.3 also provided that if Northwood could not obtain finished lots prior to

closing, then it would be in default. Paragraph 7.1 defined “default” as the “failure of either party

to perform any act to be performed by such party” if the failure continued for 10 days after written

notice by the nondefaulting party. Clerk’s Papers (CP) at 29. Paragraph 10.14 also provided,

“Time is of the essence with respect to the performance by Buyer and Seller of each and every

obligation under each and every provision of this Agreement.” CP at 33.

On December 6, 2016, the parties amended the agreement’s plat modification provision,

changing the modification deadline to December 1, 2017, and removing Northwood’s right to

extend the deadline any further. The second amendment reaffirmed, “If the Plat Modification has

recorded not later than the Plat Modification Deadline, the number of Lots will increase by five

(5) and Buyer shall pay Seller an additional Seven Hundred Sixty Five Thousand and No/100

Dollars ($765,000).” CP at 38. It then continued, “If Seller does not obtain the Plat Modification

by the Plat Modification Deadline, Seller shall assign and turn over to Buyer Seller’s applicant

status to the Plat Modification and all other entitlements, development rights, and permits related

thereto.” CP at 38.

Closing occurred on December 8, 2016, and Northwood had almost a year to fulfill its

remaining obligation to obtain approval for and record the plat modification by the new deadline

of December 1, 2017.

On November 13, 2017, Northwood submitted the plat modification application to the city

of Edgewood. The city then informed Northwood that the city council would not review the

application until January 9, 2018 due to holiday schedules. On December 4, 2017 Lennar informed

Northwood that it would not pay the $765,000 and that it would take over as the applicant with all

3 No. 52000-1-II

related entitlements, development rights, and permits, as outlined in the second amendment.

Northwood did not receive a 10-day notice of default and opportunity to cure, as is provided for

in the agreement where one party is in default. On December 13, 2017, Lennar received a notice

of incomplete application. The notice requested that Lennar correct and resubmit the final plat

drawing by removing buffer setback lines. The notice also requested that Lennar submit a corrected

application with the signatures of parties authorized to act on its behalf. On January 9, 2018,

Lennar submitted a revised application. The city deemed the application complete on January 10,

2018, granted the application, and recorded it on January 25, 2018.

Lennar refused to pay Northwood for the additional five lots because Northwood had not

complied with the deadline established in the second amendment. Northwood sued Lennar for

breach of contract. It alternatively sought recovery under quantum meruit and unjust enrichment.

In a declaration, Northwood’s managing member stated that Northwood had spent approximately

$260,000 and 750 hours on modifying the plat and preparing the application. This included, for

example, engineering, surveying, excavation, and the reworking of driveway approaches, curbing,

and gutters. He further stated that he had not intended to assume the risk of the modification not

being recorded in time, and that he was no longer in control of the application once it was submitted

to city officials, who informed him after submission that recording may be delayed by its holiday

schedule.

Both parties moved for summary judgment. Lennar argued that the amended plat

modification provision established a condition precedent—that Northwood would obtain the

modification by the deadline—and so once Northwood failed to meet that condition, Lennar was

excused from payment. Northwood countered that the provision should instead be read as a

4 No. 52000-1-II

contractual promise in order to avoid a forfeiture, such that Northwood’s failure to meet the

deadline constituted a minor breach but did not excuse Lennar from paying the $765,000. In the

alternative, Northwood argued that if the provision was a condition precedent, Northwood was

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Port of Walla Walla v. Sun-Glo Producers, Inc.
504 P.2d 324 (Court of Appeals of Washington, 1972)
Douglas Northwest, Inc. v. Bill O'Brien & Sons Construction, Inc.
828 P.2d 565 (Court of Appeals of Washington, 1992)
Jones Associates, Inc. v. Eastside Properties, Inc.
704 P.2d 681 (Court of Appeals of Washington, 1985)
Heckman Motors, Inc. v. Gunn
867 P.2d 683 (Court of Appeals of Washington, 1994)
Ashburn v. Safeco Insurance Co. of America
713 P.2d 742 (Court of Appeals of Washington, 1986)
Arnold v. Melani
437 P.2d 908 (Washington Supreme Court, 1968)
Wharf Restaurant, Inc. v. Port of Seattle
605 P.2d 334 (Court of Appeals of Washington, 1979)
Falaschi v. Yowell
601 P.2d 989 (Court of Appeals of Washington, 1979)
Vacova Company v. Farrell
814 P.2d 255 (Court of Appeals of Washington, 1991)
Rains v. Lewis
579 P.2d 980 (Court of Appeals of Washington, 1978)
Ryker v. Stidham
561 P.2d 1103 (Court of Appeals of Washington, 1977)
Hensel Phelps Construction Co. v. King County
787 P.2d 58 (Court of Appeals of Washington, 1990)
Proctor v. Huntington
238 P.3d 1117 (Washington Supreme Court, 2010)
Wm. Dickson Co. v. Pierce County
116 P.3d 409 (Court of Appeals of Washington, 2005)
Salvo v. Thatcher
116 P.3d 1019 (Court of Appeals of Washington, 2005)
Pardee v. Jolly
182 P.3d 967 (Washington Supreme Court, 2008)
Deveny v. Hadaller
161 P.3d 1059 (Court of Appeals of Washington, 2007)
Terry v. Born
604 P.2d 504 (Court of Appeals of Washington, 1979)
Tacoma Northpark, LLC v. NW, LLC
96 P.3d 454 (Court of Appeals of Washington, 2004)
Young v. Young
191 P.3d 1258 (Washington Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Northwood Estates, Llc v. Lennar Northwest, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwood-estates-llc-v-lennar-northwest-inc-washctapp-2020.