Ryker v. Stidham

561 P.2d 1103, 17 Wash. App. 83, 1977 Wash. App. LEXIS 1537
CourtCourt of Appeals of Washington
DecidedMarch 9, 1977
Docket1887-2
StatusPublished
Cited by13 cases

This text of 561 P.2d 1103 (Ryker v. Stidham) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ryker v. Stidham, 561 P.2d 1103, 17 Wash. App. 83, 1977 Wash. App. LEXIS 1537 (Wash. Ct. App. 1977).

Opinion

Ringold, J. *

On November 25, 1971, plaintiffs sold vacant land to defendants Robert E. and Clarcy Stidham *84 pursuant to a standard form of real estate contract common in this state. The purchase price was $28,285, with a down payment of $3,500, and the balance payable in monthly installments of $200 including interest on the diminishing balance. The contract contained the usual "time is of the essence" clause:

Time is of the essence of this contract, and it is agreed that in case the purchaser shall fail to comply with or perform any condition or agreement . . . the seller may elect to declare all the purchaser's rights hereunder terminated, and ... all payments . . . and all improvements . . . shall be forfeited to the seller as liquidated damages . . .

The purchasers' interest was assigned to their son Terry Stidham and his wife Norma. Panacom Building Systems, Inc., a family-owned corporation, acquired an interest in the property as mortgagee of the purchasers' interest. Panacom was to function as the financing and construction agency to develop and build a complex of houses on adjoining land and the subject property. The corporation made all the payments on the contract. There is no dispute as found by the trial court:

8.

That the Defendants have been delinquent in payment of the installments under the terms of said contract from its inception and during the period from February 1, 1972, to November 19, 1973, the Plaintiffs caused four (4) Notices of Intention to Forfeit said contract and eight (8) letters demanding payment of installments and taxes to be forwarded to the Plaintiffs.

In August 1972, the sellers sent a notice of forfeiture to the purchasers. Subsequently the contract was reinstated, but delinquencies continued until November 19,1973, when again the sellers declared the contract forfeited. Negotiations between the parties, represented by counsel, resulted on December 8, 1973, in an agreement modifying and reinstating the contract. The agreement, inter alia, required the purchasers to pay the delinquencies, and an additional *85 $50 per month to be held as a reserve fund for taxes. The timeliness of subsequent payments was the subject of negotiation between respective counsel, and the following provision was agreed to by the parties:

Notwithstanding any other provision . . . failure to make any payment of principal, interest or reserve or any portion thereof on or before the due date, shall constitute breach of this agreement and shall render this contract subject to forfeiture at the option of the Seller without further notice to the purchaser.

In 1974 the purchasers made the following payments on the modified contract:

Amount

Date Paid Date Due Paid

January 25 January 24 $650

February 25 February 25 250

March 25 March 26 250

April 25 May 10 250

May 25 May 31 230

June 25 July 2 230

The principal balance then due was $23,316.77. The property had remained unimproved, other than some grading and surface work done in conjunction with the development of the adjoining site upon which a model home had been constructed. The trial court found: "that said improvement was inconsequential." (Finding of fact No. 13.)

On August 15, 1974, sellers' attorney advised the collecting bank not to accept any further payments. Three days later he advised the purchasers that the contract was terminated and their rights were forfeited. This action was then commenced October 17, 1974, for a decree adjudging the contract terminated, forfeiting the payments and quieting title in the sellers.

After trial, the court found for the sellers, decreeing the contract terminated and forfeited. Exercising his equitable powers, the trial judge granted to the purchasers a

*86 "grace period" of six (6) months from March 26, 1975, during which period said Defendants may redeem the . . . property by paying to the Plaintiffs, . . . ($23,316.77) . . . plus interest thereon . . . and real property taxes . . . [costs and attorneys' fees].

This appeal follows. Numerous assignments of error are alleged which resolve into three issues:

1. Did the sellers breach the contract, as modified, by not setting up a separate account for the tax "reserve fund?"

2. Did the declaration of forfeiture require as a condition precedent prior notice of an intention to forfeit sufficient to give the purchasers an opportunity to cure any delinquencies in payments?

3. Did the trial court abuse its discretion in the exercise of equitable powers to require payment of the entire amount due within 6 months after trial?

Our answer to each of the questions raised by these issues is "No."

Reserve Fund

The payments received after the modification were all applied to principal and interest. When the taxes were paid by the seller the amount was added back to the principal sum. The provision for a "reserve fund" does not require a separate bank account. The trial court found:

11.
That as to all sums paid by the Defendants to the Plaintiffs as reserve for taxes, said funds have been properly held and applied by the Plaintiffs.

We agree.

Forfeiture

The purchasers argue that payments for March, April, May, and June 1974, were late by 1, 15, 6, and 7 days respectively—and were accepted without protest. Therefore, they argue, there can be no termination of rights and forfeiture without prior notice of an intention to declare a forfeiture.

*87 When time has been made the essence of an executory contract for the sale of land, the seller may require strict performance and has the right to terminate the contract and declare a forfeiture for the late tender or nonpayment of the purchase price or any installment due. 91 C.J.S. Vendor and Purchaser § 133, at 1069 (1955). This general rule has long been followed in this state. Dill v. Zielke, 26 Wn.2d 246, 252, 173 P.2d 977 (1946):

We are cognizant of the well-established rule in this state that, where time is made of the essence of a contract of sale, the vendor may declare a forfeiture of the contract for the nonpayment of the purchase price or any installment thereof.

The strict performance requirement with respect to time of payment required by contract may be waived by the promisee. The law is well stated by the court in Bulmon v. Bailey, 22 Wn.2d 372, 156 P.2d 231 (1945), at 376-77:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northwood Estate, LLC v. Lennar Northwest, Inc.
Court of Appeals of Washington, 2022
Northwood Estates, Llc v. Lennar Northwest, Inc.
Court of Appeals of Washington, 2020
Barnett v. Oliver
858 P.2d 1228 (Court of Appeals of Kansas, 1993)
Vacova Company v. Farrell
814 P.2d 255 (Court of Appeals of Washington, 1991)
Sunland Investments, Inc. v. Graham
773 P.2d 873 (Court of Appeals of Washington, 1989)
United States v. Winterburn
749 F.2d 1283 (Ninth Circuit, 1984)
Reed v. Eller
664 P.2d 515 (Court of Appeals of Washington, 1983)
Sofie v. Kane
650 P.2d 1124 (Court of Appeals of Washington, 1982)
Markland v. Wheeldon
629 P.2d 921 (Court of Appeals of Washington, 1981)
Benson v. McGovern
627 P.2d 148 (Court of Appeals of Washington, 1981)
Terry v. Born
604 P.2d 504 (Court of Appeals of Washington, 1979)
Falaschi v. Yowell
601 P.2d 989 (Court of Appeals of Washington, 1979)
Rains v. Lewis
579 P.2d 980 (Court of Appeals of Washington, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
561 P.2d 1103, 17 Wash. App. 83, 1977 Wash. App. LEXIS 1537, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ryker-v-stidham-washctapp-1977.