Northwood Estate, LLC v. Lennar Northwest, Inc.

CourtCourt of Appeals of Washington
DecidedJune 28, 2022
Docket38546-9
StatusUnpublished

This text of Northwood Estate, LLC v. Lennar Northwest, Inc. (Northwood Estate, LLC v. Lennar Northwest, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwood Estate, LLC v. Lennar Northwest, Inc., (Wash. Ct. App. 2022).

Opinion

FILED JUNE 28, 2022 In the Office of the Clerk of Court WA State Court of Appeals, Division III

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION THREE

NORTHWOOD ESTATE, LLC, a ) Washington State Limited Liability ) No. 38546-9-III Company, ) ) Respondent, ) ) v. ) UNPUBLISHED OPINION ) LENNAR NORTHWEST, INC., a ) Delaware corporation, ) ) Appellant. )

STAAB, J. — Lennar Northwest, Inc. (Lennar), and Northwood Estate, LLC,

(Northwood) entered into a purchase and sale agreement (PSA) for several residential

lots. According to the original PSA, Lennar would pay Northwood an additional

$765,000 if Northwood completed a plat modification that changed 8 lots into 13 lots by

the closing date. When Northwood failed to meet this deadline, the sale closed and the

parties signed an amendment giving Northwood one additional year to finalize the plat

modification with no further extensions. When Northwood failed to meet this second No. 38546-9-III Northwood Estate, LLC v. Lennar Northwest, Inc.

deadline, Lennar assumed the plat revision and refused to pay the additional $765,000.

Shortly thereafter, the City of Edgewood (City) granted Lennar the revised plat.

Northwood sued Lennar, alleging breach of contract. Division Two of this court

granted discretionary review and held that Northwood’s obligation to finalize the plat

modification was a condition precedent to Lennar’s obligation to pay the additional sales

price. Northwood Estate, LLC v. Lennar NW., Inc., No. 52000-1-II, slip op. at 1 (Wash.

Ct. App. Mar. 3, 2020) (unpublished), https://www.courts.wa.gov/opinions/pdf

/D2%52000-1-II%20Unpublished%20Opinion.pdf. Nevertheless, the court held that

equitable relief would be available to avoid extreme forfeiture if the condition precedent

did not form an essential part of the bargain. Id. at 8. The court remanded for the trial

court to determine if equitable relief was available and, if so, in what form it should take.

Id. at 15, 17.

On remand, Lennar moved for summary judgment, arguing that the deadline for

completing the plat modification was an essential part of the bargain because the contract

includes a time-is-of-the-essence clause and Lennar relied on the deadline to schedule the

development of the property. The trial court denied Lennar’s motion, indicating that

Lennar had waived strict application of the deadline by providing two prior extensions.

Northwood then filed for summary judgment, arguing that it was entitled to

equitable relief. The court granted Northwood’s motion, imposed an equitable grace

2 No. 38546-9-III Northwood Estate, LLC v. Lennar Northwest, Inc.

period, found that Northwood had complied with the condition and was entitled to the

increased purchase price, prejudgment interest, and attorney fees.

Lennar appeals raising five issues: whether the trial court erred in (1) denying its

motion for summary judgment, (2) concluding that the parties had waived the “time-is-

of-the essence” provision, (3) finding waiver when that issue was not raised by either

party, (4) failing to grant Lennar’s motion for a continuance to conduct discovery, and

(5) granting Northwood’s motion for summary judgment.

While Lennar is generally precluded from appealing a denial of summary

judgment under RAP 2.2, to the extent that the trial court found waiver of an essential

term on summary judgment, such a finding was premature and based on contested

evidence. Otherwise, we conclude that the trial court abused its discretion by denying

Lennar’s motion to continue Northwood’s motion for summary judgment so that Lennar

could conduct discovery. We reverse the judgment in favor of Northwood and remand

for further proceedings.

BACKGROUND

The basic facts of this case were set out in a previous appeal to Division Two.

Northwood Estate, LLC, No. 52000-1-II. Lennar is engaged in the business of the

construction and sale of single-family residences. In December 2015, Lennar agreed to

purchase from Northwood finished lots in a residential subdivision. The PSA provided

that Lennar would pay an additional $765,000 if Northwood obtained a plat modification

3 No. 38546-9-III Northwood Estate, LLC v. Lennar Northwest, Inc.

that turned 8 lots into 13 lots by the closing date in the PSA—about a year out from

mutual acceptance of the PSA. When the sale closed on December 8, 2016, Northwood

had not started the plat modification. The parties agreed to a second amendment to the

PSA, giving Northwood until December 1, 2017, to complete the plat modifications. The

amendment provided that no additional extensions would be granted.

From December 2016 to December 2017, Northwood began the process of

obtaining a plat modification. Northwood maintains that it spent approximately $260,000

to prepare the plat modification, including engineering costs, surveying, and curb

modifications. On November 13, 2017, 18 days before the contract deadline, Northwood

submitted the plat modification. The City advised developers that plat modifications may

take up to 120 days to finalize. The City responded to Northwood’s submission by

stating it would start review on January 9, 2018, due to the holiday season. Lennar then

advised Northwood that it would not be paying the additional sales price and notified the

City that it was assuming the plat modification.

Lennar completed the plat modification on January 10, 2018. Northwood sued for

payment for the additional lots contending that the PSA “time-is-of-the-essence”

provision was a covenant, not a condition precedent. Lennar argued that the provision

was a condition precedent and Northwood’s failure to perform the condition extinguished

Lennar’s payment obligation. Division Two granted discretionary review, and held that

the provision was a condition precedent. Id. at 17.

4 No. 38546-9-III Northwood Estate, LLC v. Lennar Northwest, Inc.

Despite finding a condition precedent, the court recognized that Northwood might

be entitled to equitable relief. The court suggested that a “[c]ondition[ ] precedent ‘will

be excused if enforcement would involve extreme forfeiture or penalty and if the

condition does not form an essential part of the bargain.’” Id. at12 (quoting Ashburn v.

Safeco Ins. Co. of Am., 42 Wn. App. 692, 698, 713 P.2d 742 (1986)). Without deciding

that the plat modification and deadline were essential to the contract, the court noted:

Here, the plat modification deadline arguably may have been essential to the contract because the plat modification was the only remaining task under the contract and the parties’ time-is-of-the-essence provision suggests that a condition involving the modification deadline was important.

Id. at 14. The court provided further guidance by recognizing several factors a court

should consider in determining whether equitable relief is appropriate: “the amount that

would be forfeited without the equitable relief sought, whether the failure to meet the

deadline was inadvertent, and whether the other party was prejudiced by the delay.”

Id. at 13. In the end, the court remanded the case to address two issues: “whether

equitable relief is appropriate to prevent forfeiture and, if so, what form that relief should

take.” Id. at 17.

On remand, Lennar moved for summary judgment arguing that because the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ferree v. Doric Co.
383 P.2d 900 (Washington Supreme Court, 1963)
Ashburn v. Safeco Insurance Co. of America
713 P.2d 742 (Court of Appeals of Washington, 1986)
Wharf Restaurant, Inc. v. Port of Seattle
605 P.2d 334 (Court of Appeals of Washington, 1979)
Ryker v. Stidham
561 P.2d 1103 (Court of Appeals of Washington, 1977)
Park Avenue Condominium Owners Ass'n v. Buchan Developments, LLC
71 P.3d 692 (Court of Appeals of Washington, 2003)
VEHICLE/VESSEL LLC, DRA v. Whitman County
95 P.3d 394 (Court of Appeals of Washington, 2004)
State v. Hurd
902 P.2d 651 (Washington Supreme Court, 1995)
Durand v. HIMC CORP.
214 P.3d 189 (Court of Appeals of Washington, 2009)
Cornish College v. 1000 Virginia Ltd.
242 P.3d 1 (Court of Appeals of Washington, 2010)
State v. Hurd
127 Wash. 2d 592 (Washington Supreme Court, 1995)
Green v. A.P.C.
960 P.2d 912 (Washington Supreme Court, 1998)
Keck v. Collins
357 P.3d 1080 (Washington Supreme Court, 2015)
Kaplan v. Northwestern Mutual Life Insurance
65 P.3d 16 (Court of Appeals of Washington, 2003)
Park Avenue Condominium Owners Ass'n v. Buchan Developments, L.L.C.
117 Wash. App. 369 (Court of Appeals of Washington, 2003)
Vehicle/Vessel, L.L.C. v. Whitman County
122 Wash. App. 770 (Court of Appeals of Washington, 2004)
Durand v. HIMC Corp.
151 Wash. App. 818 (Court of Appeals of Washington, 2009)
Cornish College of the Arts v. 1000 Virginia Ltd. Partnership
158 Wash. App. 203 (Court of Appeals of Washington, 2010)
224 Westlake, LLC v. Engstrom Properties, LLC
281 P.3d 693 (Court of Appeals of Washington, 2012)
In re the Estates of Jones
287 P.3d 610 (Court of Appeals of Washington, 2012)
Mid-Town Ltd. Partnership v. Preston
848 P.2d 1268 (Court of Appeals of Washington, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Northwood Estate, LLC v. Lennar Northwest, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwood-estate-llc-v-lennar-northwest-inc-washctapp-2022.