Hopkins v. Ulvestad

282 P.2d 806, 46 Wash. 2d 514, 1955 Wash. LEXIS 515
CourtWashington Supreme Court
DecidedApril 26, 1955
Docket33007
StatusPublished
Cited by15 cases

This text of 282 P.2d 806 (Hopkins v. Ulvestad) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hopkins v. Ulvestad, 282 P.2d 806, 46 Wash. 2d 514, 1955 Wash. LEXIS 515 (Wash. 1955).

Opinion

Donworth, J.

This action was brought to foreclose a lien for labor and material furnished in the construction of the foundation of a house in the amount of $837.48. The trial court held that certain items claimed were not chargeable to the defendant because plaintiff was simultaneously engaged in the performance of two contracts; that as to the balance of the items the lien should be foreclosed; that the defendant should be allowed to set off against the recovery on the lien certain damages suffered by reason of poor workmanship; that the plaintiff should be allowed an attorney’s fee of one hundred fifty dollars; and that neither party should recover costs. Findings of fact and conclusions of law were made, and judgment was entered in favor of the plaintiff for $173.70 plus the attorney’s fees.

Plaintiff has appealed from the judgment and has assigned error to all material portions of the findings of fact, conclusions of law, and judgment.

The situation presented is quite different from the usual *516 lien foreclosure proceeding and requires a somewhat detailed statement of facts.

Thor P. Ulvestad and wife desired to construct a family-dwelling upon a lot they owned in the city of Seattle. Mr. Ulvestad, a practicing attorney, shall be referred to as though he were the sole respondent. He planned to do much of the work on the proposed dwelling himself and thereby greatly reduce the usual cost of construction.

In his endeavor to hold down costs, respondent contemplated the making of several separate contracts: (1) he retained an architect to draw plans for the house but not to supervise the construction; (2) he contracted with a bulldozer operator to excavate the lot; (3) he arranged with another party to supply and dump fill dirt; (4) he entered into a contract with two carpenters (hereinafter referred to as the partnership) to set foundation forms and frame the house; (5) he contracted with an acquaintance to pour the foundation and basement cement work; and, in addition, he made several other separate contracts for the furnishing of different materials as required throughout the progress of the work. There was no general contractor or other representative of the owner to supervise the work done on the premises.

The lot upon which the dwelling was to be erected was not level. The street forms the west boundary. Along a portion of the south boundary it was near street grade, but it sloped downward until it was about twenty feet below the level of the adjoining lot on the south. At about the center of the lot was a level area which was some twenty feet below street grade. From this level, portion the lot sloped downward to the north and east boundaries.

The architect drew plans for a three-level dwelling which would utilize the natural terrain of the lot. Respondent, working alone, cleared the lot of trees, brush, and undergrowth. Fill dirt was dumped and leveled on the north side of the lot. The bank on the south side of the lot was then excavated to the property line by a bulldozer. The architect’s plans called for the location of the house eleven feet and four inches from this boundary.

*517 The evening that this excavation was completed (January 7, 1953), Mr. Jory, the owner of the property adjoining respondent’s lot on the south, telephoned respondent and advised him that as the result of this excavation a slide had occurred, and that he feared that his house would become undermined because of the removal of lateral support. At the time of the trial of this case, a suit was pending which had been instituted by Mr. Jory against the respondent here to recover for damages to his property resulting from this removal of lateral support. .

Respondent inspected the reported slide and found that a tree, about a truck load of dirt, and some eight feet of rockery had slipped into the excavation from Jory’s lot. The surface of Mr. Jory’s lot was then about twenty feet higher than the adjacent part of respondent’s property. Upon the advice of an engineer respondent attempted to restore the lateral support the next day by causing some eighty yards of sand to be dumped into the excavation and graded up against the bank. The slide ceased.

The foregoing events took place two months before appellant ever was on the respondent’s property. Appellant started to work on March 12,1953, as a subcontractor for the partnership under the circumstances described below.

The partners, called as witnesses by respondent, testified that in making their contract with the owner they had allowed five hundred dollars to cover the cost of placing the forms for the cement work. The only excavating they were to do under that contract was such hand-shovel work as would be incidental to the leveling of the forms. The partners desired to sublet the work of placing the forms to a subcontractor because they did not have form panels and were not familiar with the work of placing such panels. They contacted appellant at the site of a job where he was then working and asked him if he could rent panel forms and set them in place for five hundred dollars.

The partners testified that they had advised appellant that in making their contract with the owner they had allowed five hundred dollars for putting the forms in place, and that if there were any additional cost, appellant would have *518 to look to the owner. Appellant drove by respondent’s lot on a Sunday, observed its condition and terrain, and later telephoned the partners that he estimated that the cost of placing the forms would not exceed five hundred dollars. The partners then requested him to start work immediately.

Appellant was furnished the architect’s sketch showing the location and general character of the proposed house. This plan called for the setting of the basement walls on solid footing. On March 12, 1953, he proceeded to stake out the basement. It was then that he discovered that an excavation two or three feet wide and forty feet long would have to be made in the sand bank on the south side of the lot in order to place the forms according to the plan. Appellant procured a bulldozer operator, who was working in the vicinity, to make- the necessary excavation of the south bank. (Respondent later paid the bulldozer operator for this work.) Appellant and his crew then started to use hand shovels to dig for a firm level footing for the south wall forms. The bank started sliding down faster than the crew could shovel. In an attempt to hold the bank, appellant drove a large number of two-by-fours into the ground and nailed shiplap to them, forming a temporary retaining wall. Shortly after this wall was in place, a further slide occurred which completely buried it.

When this emergency arose, appellant and respondent had their first contact in regard to the work which appellant was doing and was to do on the property.

Appellant telephoned respondent and advised him that because of the sliding tendency of the bank, it was impossible to put in the forms according to plan and suggested two alternatives. One was to place the house farther to the north and away from the south bank. Respondent would not consent to this suggestion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Highway Commission v. Brasel & Sims Construction Co.
688 P.2d 871 (Wyoming Supreme Court, 1984)
Rissler & McMurry Co. v. Atlantic Richfield Co.
559 P.2d 25 (Wyoming Supreme Court, 1977)
Dravo Corp. v. L. W. Moses Co.
492 P.2d 1058 (Court of Appeals of Washington, 1971)
Swenson v. Lowe
486 P.2d 1120 (Court of Appeals of Washington, 1971)
Hellbaum v. Burwell & Morford
463 P.2d 225 (Court of Appeals of Washington, 1969)
Brandt v. Impero
463 P.2d 197 (Court of Appeals of Washington, 1969)
Gannon v. Emtman
405 P.2d 254 (Washington Supreme Court, 1965)
Paduano v. J. C. Boespflug Construction Co.
403 P.2d 841 (Washington Supreme Court, 1965)
Elmore v. Graystone of Centralia, Inc.
387 P.2d 75 (Washington Supreme Court, 1963)
Central Steel Erection Co. v. Will
304 F.2d 548 (Ninth Circuit, 1962)
Boespflug v. Wilson
362 P.2d 747 (Washington Supreme Court, 1961)
Forrester v. Craddock
317 P.2d 1077 (Washington Supreme Court, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
282 P.2d 806, 46 Wash. 2d 514, 1955 Wash. LEXIS 515, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hopkins-v-ulvestad-wash-1955.