Paduano v. J. C. Boespflug Construction Co.

403 P.2d 841, 66 Wash. 2d 527, 1965 Wash. LEXIS 892
CourtWashington Supreme Court
DecidedJune 24, 1965
Docket37892
StatusPublished
Cited by6 cases

This text of 403 P.2d 841 (Paduano v. J. C. Boespflug Construction Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paduano v. J. C. Boespflug Construction Co., 403 P.2d 841, 66 Wash. 2d 527, 1965 Wash. LEXIS 892 (Wash. 1965).

Opinion

Ott, J.

J. C. Boespflug Construction Company, a corporation (hereinafter referred to as the construction company), was awarded a $3,000,000 prime contract for the construction of a building project known as Providence Heights College, in King County. The construction company had previously requested Ned Paduano to submit a bid, as a prospective subcontractor, for “clearing and grubbing and site excavation and building excavation, putting footings and excavation, backfilling, stripping and respreading topsoil.” After the prime contract was obtained, the construction company awarded Paduano the subcontract for specified excavation work in the sum of $67,509.

Paduano commenced work on December 3, 1958, and continued until October 31, 1959. During this time, Paduano had also performed extra work resulting from change orders which increased the amount of the subcontract to $81,036.05. The project architect, by October 31, 1959, had approved payment to Paduano of $68,636.10, his subcontract then being nearly 88 per cent performed. From the approved payment, the sum of $6,500 was withheld as the retained percentage authorized by § 17 of the subcontract.

October 31, 1959, Paduano left the project, with the knowledge and consent of the construction company, conditioned upon his returning and finishing the work when the construction company requested further performance.

In July, 1960, Paduano was requested to return to complete the subcontract. When he arrived at the job site, construction had not proceeded far enough for Paduano to finish his subcontract. August 8, 1960, Paduano again returned with his men and equipment and, on September 19, I960;- while he was attempting to complete the. work, the construction company declared Paduano in default and removed him from the job site. The construction company thereafter completed the subcontract.

*529 Ned Paduano commenced this action to recover the balance due him on the subcontract, contending that the construction company had been arbitrary and capricious in terminating it. The construction company denied the material allegations of the complaint and that any sum was due, and, by counterclaim, affirmatively alleged that Paduano was indebted to the construction company in the sum of $31,055.79.

The cause was tried to the court. The trial court found that the construction company’s action in declaring Paduano in default under the subcontract was arbitrary and capricious. It awarded Paduano judgment for $15,471.73, composed of the following items: Retained funds of $6,500; admitted or proved extras of $1,280.75; equipment and operator rental during 1960 of $6,288.49; employees’ wages during 1960 of $1,402.49. No loss of profit was awarded to Paduano by the trial court.

. The court awarded the construction company a setoff of $8,225.38 against Paduano for labor and equipment rental incurred by the construction company in connection with earth moving on the job site prior to September 19, 1960. The court did not allow a setoff for charges incurred in completion of the project after the construction company had declared Paduano in default, and made no finding as to the cost of completing the subcontract.

From the judgment entered, the construction company appeals and Paduano cross-appeals.

The appellant construction company contends that the court erred in finding that it was arbitrary and capricious in declaring respondent Paduano in default. The default was declared under § 15 of the subcontract which provided:

If the Subcontractor shall fail to . . . prosecute said work continuously with sufficient workmen and equipment to insure its completion within the time herein specified for completion, . . . or if . . . Subcontractor shall fail to carry on the said work in an acceptable manner, the Contractor may elect to give notice in writing of such default ....

*530 The reason appellant gave for declaring the respondent in default was respondent’s alleged failure to have sufficient manpower and equipment on the job to insure timely completion of the work in an acceptable manner. The appellant contends that its action was not arbitrary or capricious since there was room for two opinions relative to the cause of the delay, and its action was exercised honestly even though an erroneous decision may have been reached. Lillions v. Gibbs, 47 Wn.2d 629, 633, 289 P.2d 203 (1955), and case cited.

In its oral decision, the court stated:

In reviewing the testimony of the defendant [construction company], we find no denial that there was improper staking, improper engineering, necessitating the change in engineers, removal of superintendents, uncontradicted testimony that everybody was behind on the project.
He [Paduano] was the contractor on the job, yet in October, 1959, he had gotten off the job and done everything that reasonably could be done at that period of time in the progress of the work. He was to await a call from Mr. Boespflug, Jr., as to the time of return to the job. When the call came, and he proceeded out to the job site, the evidence is quite clear that they were not ready to have him perform. Of course, I recognize that some of this evidence is conflicting, however, the Court accepts Mr. Paduano’s version of this, and in large measure it is not contradicted.

There was further testimony by appellant’s witness, John F. Boespflug, that a series of strikes during the period of construction caused delays and necessitated an extension of time for completion of the project.

From this evidence, the court entered its finding of fact No. 5 as follows:

On September 19, 1960, defendant [construction company] declared plaintiff [Paduano] in default and removed plaintiff from the Providence Heights College job site. Such action on the part of the defendant was arbitrary, capricious and unreasonable.

*531 The evidence at the trial was conflicting as to the cause of the delay in the completion of the project. The trial court did not accept appellant’s version that respondent caused the delay.

There is substantial evidence to support the trial court’s finding that the appellant was arbitrary and capricious in declaring the default; therefore, the finding must be affirmed. Choate v. Swanson, 54 Wn.2d 710, 715, 344 P.2d 502 (1959), and cases cited; Williams Tilt-up Contractors, Inc., v. Schmid, 52 Wn.2d 429, 430, 326 P.2d 41 (1958), and case cited.

Appellant next assigns error to the following conclusions of law:

Plaintiff [Paduano] has performed work for the defendant [construction company] pursuant to express contract therefor and for which he has not been compensated in the sum of $14,190.98.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rissler & McMurry Co. v. Atlantic Richfield Co.
559 P.2d 25 (Wyoming Supreme Court, 1977)
Segall v. Ben's Truck Parts, Inc.
488 P.2d 790 (Court of Appeals of Washington, 1971)
Tucker v. Bankers Life & Casualty Co.
406 P.2d 628 (Washington Supreme Court, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
403 P.2d 841, 66 Wash. 2d 527, 1965 Wash. LEXIS 892, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paduano-v-j-c-boespflug-construction-co-wash-1965.