Williams Tilt-Up Contractors, Inc. v. Schmid

326 P.2d 41, 52 Wash. 2d 429, 1958 Wash. LEXIS 388
CourtWashington Supreme Court
DecidedMay 29, 1958
Docket33866
StatusPublished
Cited by9 cases

This text of 326 P.2d 41 (Williams Tilt-Up Contractors, Inc. v. Schmid) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Williams Tilt-Up Contractors, Inc. v. Schmid, 326 P.2d 41, 52 Wash. 2d 429, 1958 Wash. LEXIS 388 (Wash. 1958).

Opinion

Hill, C. J.

This is a controversy between a subcontractor and a general contractor arising out of work done, or not done, in connection with two subcontracts involved in the construction of a depot warehouse in Alaska for the United States government.

The- general contractor terminated the subcontracts and completed the work. The subcontractor, contending that the subcontracts were wrongfully terminated, sues in one action for the amount due on each contract at the time of the termination thereof and an additional five thousand dollars, which was to be paid if the direct costs on the two subcontracts exceeded the amount of the subcontracts, together with certain extras alleged to have been furnished at the special instance and request of the general contractor. The subcontractor also sues, in a separate but consolidated action, for the conversion by the general contractor — to his own use — of certain equipment which the subcontractor had left on the job in the possession of the general contractor at the time the subcontracts were terminated.

The issues are for the most part factual and call for the application of the familiar principle that we will not *431 disturb the findings of the trial court, unless there is no credible evidence to sustain them, or unless the evidence clearly preponderates against them. Nelson Equipment Co. v. Estep (1957), 50 Wn. (2d) 612, 313 P. (2d) 679.

The first issue of fact, in point of importance, was whether the general contractor was within his rights in terminating the subcontracts. The trial court found, on sharply conflicting evidence, that the action of the general contractor in terminating the subcontracts and taking over their completion “was without cause or justification.” This finding disposed of the general contractor’s cross-complaint for the cost of completing the subcontracts, over and above the amount fixed in the subcontracts.

The second issue of fact, in point of importance, was the percentage of completion of the subcontracts at the time of their termination by the general contractor. Again, on sharply conflicting evidence, the trial court found that the subcontractor had completed 96.6 per cent of the work required under one subcontract and 93.1 per cent of the work required under the other. This finding determined the amount due under the subcontracts to the subcontractor. The finding that the subcontractor’s direct costs, exclusive of extras, amounted to $143,940.95 was decisive of the subcontractor’s right to the additional five thousand dollars. This leaves for our consideration (exclusive of the conversion action) only the amount of some forty items of claimed extras (twenty-five items were referred to in the bill of particulars, but the twenty-fifth item was itself made up of sixteen separate items which we will refer to as subitems).

Of the first twenty-four items of extras, the trial court found with the general contractor and against the subcontractor on only two items; on the other twenty-two items, the trial court found for the subcontractor in the amount claimed; but in many of these the amount claimed was conceded and, actually, only eleven items are in controversy. The general contractor conceded that some amount was due on all but two of these eleven controverted items.

Of the sixteen separate subitems, which made up the twenty-fifth item, the trial court found with the general *432 contractor.and against the subcontractor on five subitems, which left eleven subitems in controversy. Because of the general. contractor’s insistence that the evidence preponderated against the findings of the trial court, we have assayed the evidence in support of these twenty-two claimed extras, and have found support for the trial court’s findings on all except three items and three subitems.

The largest amount involved is a claim for twenty thousand dollars for equipment rental, which is subitem 16 of item 25. We are satisfied that the evidence clearly preponderates against the finding that twenty thousand dollars, paid by the subcontractor to S & S Enterprises (for equipment rental), was an extra for which the general contractor had agreed to pay or was obligated to pay.

In December, 1953, the subcontractor had submitted a bid covering the construction and placing of the concrete walls by its “Tilt-Up” process, which had been accepted.

On February 24, 1954, the subcontractor had submitted a bid covering the balance of the concrete work (principally the floor). This bid contained an item for concrete placement in the amount of $33,083, which did not include the furnishing of any equipment by the subcontractor. This bid was not accepted, but, after discussion with the general contractor, a new bid was submitted on March 3, 1954, and the amount of the bid for concrete placement was increased almost $21,000 — to $54,019.24 — with the subcontractor agreeing to furnish the necessary equipment.

That bid was accepted, and the subcontract, which obligated the subcontractor “to furnish all equipment . . . for the work specified . . . was signed March 4, 1954. The same day, the subcontractor entered into a written agreement under which it agreed to pay S & S Enterprises twenty thousand dollars for the use and rental of certain listed equipment and material. That amount was paid and is the amount the subcontractor seeks to recover as an extra.

We find no basis in the record for the allowance of the item of twenty thousand dollars for equipment rental as an extra, except the unsupported statement of the presi *433 dent of the subcontractor that the representative who signed the subcontracts on behalf of the general contractor told him, “I will reimburse you for this $20,000 equipment rental as an extra.”

Aside from any consideration of the parol evidence rule, which was invoked to keep out the proferred testimony of the representative of the general contractor as to this item and relaxed to admit the testimony of the representative of the subcontractor, the written documents, to which we have here referred, constituted evidence which overwhelmingly preponderates against that offered in support of the subcontractor’s claim for a twenty-thousand-dollar extra for equipment rental. The allowance by the trial court for extras must be reduced by this item of twenty thousand dollars.

The other items and subitems, on which the trial court erred, are not of sufficient importance to warrant extended discussion. Our conclusions are of interest only to the litigants, and we shall identify the items by the same numbers used in the briefs.

Item 1: The subcontractor claimed an extra in the amount of $522.92. The general contractor admitted this extra in the amount of $505.53. The trial court found for the subcontractor for the full amount claimed, but on this appeal the subcontractor concedes that it is not claiming any amount greater than $505.53. The amount allowed for extras must be reduced by $17.39.

Item 19: The repair of a cement finishing machine, in the amount of $15.45, was never approved by any representative of the general contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hulse v. Driver
524 P.2d 255 (Court of Appeals of Washington, 1974)
Paduano v. J. C. Boespflug Construction Co.
403 P.2d 841 (Washington Supreme Court, 1965)
Town of Lovell v. Menhall
386 P.2d 109 (Wyoming Supreme Court, 1963)
In Re the Adoption of Reinius
346 P.2d 672 (Washington Supreme Court, 1959)
Choate v. Swanson
344 P.2d 502 (Washington Supreme Court, 1959)
Lewis v. Scott
341 P.2d 488 (Washington Supreme Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
326 P.2d 41, 52 Wash. 2d 429, 1958 Wash. LEXIS 388, Counsel Stack Legal Research, https://law.counselstack.com/opinion/williams-tilt-up-contractors-inc-v-schmid-wash-1958.