Berry v. Huntington Masonic Temple Ass'n

93 S.E. 355, 80 W. Va. 342, 1917 W. Va. LEXIS 43
CourtWest Virginia Supreme Court
DecidedMay 1, 1917
StatusPublished
Cited by11 cases

This text of 93 S.E. 355 (Berry v. Huntington Masonic Temple Ass'n) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berry v. Huntington Masonic Temple Ass'n, 93 S.E. 355, 80 W. Va. 342, 1917 W. Va. LEXIS 43 (W. Va. 1917).

Opinions

JUDGE:

This writ of error challenges a $25,000.00 judgment rendered in an action in assumpsit and founded upon the theory of a breach of a building contract, by the owner. It represents the jury’s estimate of the value of work- done and materials furnished by the contractor and gain or profit lost or prevented by the alleged wrongful conduct of the owner.

Sufficiency 'of the pleadings to develop and define the dominant issue in the case, the character of the breach of the contract for the erection of a seven story reinforced concrete building, known as the Huntington Masonic Temple, seems to be conceded. The overruling of a demurrer to the second amended declaration is assigned as error, but no argument is submitted in suport of the assignment.

The defense on the issue of liability is predicated on the theory of a breach of the contract by the plaintiff 'himself, justifying the action of the defendant in reletting the contract to another, for completion at his expense. The architect employed for supervision of the work Certified, April 10, 1912, that the plaintiff was not prosecuting the work with diligence, had failed to supply sufficient skilled workmen or proper materials at any time since he took charge of the work, did not possess the necessary equipment, experience or knowledge to enable him to complete the building as per contract, and had not provided any employees or assistants who possessed such equipment or knowledge. On receipt of that letter, the owners communicated the purport thereof to the Citizens Trust & Guaranty Company, of Parkersburg, W. [345]*345Va., the surety in the plaintiff’s $35,000.00 bond given to guarantee performance of the contract. Correspondence between them and the surety company ensued and, on May 30, 1912, the manager of that company went to Huntington and made an investigation of the situation. On June 14, following, he returned to Huntington, and, on the next day, June 15, 1913,- a contract was entered into by The Huntington Masonic Temple Association, The Citizens Trust & Guaranty Co., and the Moore Construction Co., by which the work was Telet to said Moore Construction Co. at the original contract price, $121,500.00.

The ground of dismissal of the plaintiff, relied upon in the evidence as well as in one of the special pleas filed, for justification thereof, was not specifically set forth in the architect’s certificate, namely, financial inability of the plaintiff to carry on and complete the work. The notice followed the language of the contract providing therefor. The special plea is based, upon a provision of the surety contract between the plaintiff and the Citizens Trust & Guaranty Co., authorizing the latter to take over and sub-let or complete the work, if, at any time, it should appear that the principal had abandoned the work or would not be able, or should not intend, to perform the contract..

The surety company did not avail itself of this provision of the .contract, until about two months after the date of the architect’s certificate. The owners gave it formal notice of the contractor’s inability to complete the contract, on June 5, 1912, and, as stated, the contract was relet on June 15, 1912. It is shown that, on May 30, 1912, the contractor was laboring under financial embarrassment; some judgments having been recovered against him and one or more executions issued thereon. He seems to have held on to the work and insisted upon his right to continue it, until the Moore Construction Company took it over.

For the most part, the recitals of the certificate of the architect are fully and completely refuted and disproved by the plaintiff’s evidence, and there is practically no contradiction thereof. Though the plaintiff was'a contractor of twelve or fifteen years experience and a man of good character and [346]*346standing, he had never erected a reinforced concrete building ; but he originally took the contract for the work in question, in connection with one George Iback, a man of considerable experience in that line of work, and, after Iback retired 'from the firm, or perhaps before, he employed M. M. Mathews as superintendent or foreman, and he was a competent concrete builder. Mathews and contractors of the city of Huntington, whose competency is not questioned, as well as certain engineers, all say the equipment Berry had on the ground and employed in the prosecution of the work was amply sufficient, and their testimony is not contradicted. One kind of material was lacking, namely, steel for reinforcement of the concrete, but the plaintiff charges his inability to procure that article to the failure and refusal of the architect to approve what are known as the “Shop Plans,” prescribing the kinds and dimensions of the steel to be used for that purpose. Plaintiff’s financial ability to procure the steel, after the date of the contract and commencement of his work and until about the date of the giving of the notice of default, is fully and clearly proved and established, if his shop plans had been approved by the architect. His ease proceeds upon the theory, therefore, that the architect was the agent of the owners, and that they, by his wrongful conduct, prevented him from performing his contract and occasioned his financial embarrassment, the action taken against him by the surety in his bond and loss of the labor and materials he bestowed upon the work and the profits he expected to obtain by completion thereof.

Although a man of limited financial ability, the plaintiff held a contract with the Miller Supply Co., a concern of ample means, by which it obligated itself to furnish him materials, credit' and protection to the extent of $86,500.00, in the prosecution of the work. The terms of the contract between the builder and the owner made it necessary for the former to carry all accounts for materials until sixty days after the completion and acceptance of the building, but the labor was to be paid for in an amount not exceeding $35,000.00, on estimates to be issued by the architect for work done in; (1), completion of excavation and the base[347]*347ment walls; (2), completion of concrete work on the second floor; (3), completion of concrete work on third floor; (4), completion of concrete work on fonrth floor; (5), completion of concrete work on fifth floor; (6), completion of concrete work on sixth floor; (7), completion of concrete work on seventh floor; (8), completion of roof; (9), completion of masonry; and, (10), completion of building ready for occupancy. Of the total contract price, $121,500.00] a portion, $2,500, was allowed the contractor for having “financed” the operation. He did that by procuring his line of credit with the Miller Supply Company.

The enterprise seems to have been started without adequate preparation therefor. As originally planned or designed by the architect, Wilbur T. Mills of Columbus, Ohio, the frame of the building was to have been of steel. Finding this plan more expensive than was anticipated or desired, the owners, under the architect’s advice and supervision, let the contract to J. E. Berry and George Ibaek, doing business as the Iback Construction Co., on June 28, 1911, for a structure with a reinforced concrete frame.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vecellio & Grogan, Inc. v. Division of Highways
19 Ct. Cl. 147 (West Virginia Court of Claims, 1992)
City of Richmond v. A. H. Ewing's Sons, Inc.
114 S.E.2d 608 (Supreme Court of Virginia, 1960)
Franklin v. Pence
36 S.E.2d 505 (West Virginia Supreme Court, 1945)
Morgan v. Town of Burlington
55 N.E.2d 758 (Massachusetts Supreme Judicial Court, 1944)
O'Dell v. Criss & Shaver, Inc.
14 S.E.2d 767 (West Virginia Supreme Court, 1941)
City of Wheeling v. John F. Casey Co.
74 F.2d 794 (Fourth Circuit, 1935)
Ohio Valley Builders Supply Co. v. Wetzel Construction Co.
151 S.E. 1 (West Virginia Supreme Court, 1929)
Weems v. Albert Pick & Co.
127 S.E. 819 (Court of Appeals of Georgia, 1925)
Twentieth Street Bank v. Summers
110 S.E. 478 (West Virginia Supreme Court, 1922)
Raleigh Coal & Coke Co. v. Mankin
97 S.E. 299 (West Virginia Supreme Court, 1918)
Vaughan Construction Co. v. Virginian Railway Co.
97 S.E. 278 (West Virginia Supreme Court, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
93 S.E. 355, 80 W. Va. 342, 1917 W. Va. LEXIS 43, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berry-v-huntington-masonic-temple-assn-wva-1917.