City of Richmond v. A. H. Ewing's Sons, Inc.

114 S.E.2d 608, 201 Va. 862, 1960 Va. LEXIS 171
CourtSupreme Court of Virginia
DecidedJune 13, 1960
DocketRecord 5103
StatusPublished
Cited by13 cases

This text of 114 S.E.2d 608 (City of Richmond v. A. H. Ewing's Sons, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Richmond v. A. H. Ewing's Sons, Inc., 114 S.E.2d 608, 201 Va. 862, 1960 Va. LEXIS 171 (Va. 1960).

Opinion

Eggleston, C. J.,

delivered the opinion of the court.

A. H. Ewing’s Sons, Incorporated, filed a motion for judgment against the City of Richmond in the court below claiming damages for the alleged breach by the city of a contract which the parties had entered into for the construction of a juvenile detention home on a site owned by the city. After the city had filed its grounds of defense the case was heard by the court without a jury and resulted in a judgment in favor of the plaintiff against the city for the sum of $47,393, with interest. Appealing from this judgment, the city assigns a number of errors which question both its liability and the quantum of damages allowed.

The underlying facts are not in dispute. A. H. Ewing’s Sons, Incorporated, a general contractor, and the City of Richmond entered *864 into a contract dated May 31, 1956, for the construction of a juvenile detention home, at the agreed price of $262,869, on property owned by the city at the northeast corner of Forest Lawn Road and Old Brook Road in the city of Richmond. The site for the proposed facility had been approved by the City Manager and the city council. On June 5 the contractor applied to the Commissioner of Buildings for a building permit, which was denied on the ground that the erection of the proposed structure on the site was not permitted by the city zoning ordinance. The city appealed this decision to the Board of Zoning Appeals. The Board at first denied the appeal, but upon a rehearing on July 2, granted the permit provided the detention home building and playground area be set back at least 440 feet from Old Brook Road, instead of 130 feet as had been originally contemplated.

On July 6 the Wicker Apartments, Incorporated, the owner of near-by property, appealed from the Board’s decision to the Law and Equity Court of the City of Richmond, and obtained an injunction from that court restraining the city and the contractor from constructing the detention home on the approved site. This injunction expired by its terms on October 1. On October 3 the Law and Equity Court entered an order affiming the order of the Board of Zoning Appeals and from that order Wicker Apartments appealed to the Supreme Court of Appeals. On September 6, 1957, the appellate court affirmed the order of the lower court. Wicker Apartments, Inc. v. City of Richmond, 199 Va. 263, 99 S. E. 2d 656.

Pending the Wicker Apartments appeal, several conferences were held and correspondence passed between the city officials, the contractor and the architect with respect to the status of the construction contract. On July 13, 1956, the Assistant Director of Public Works advised the architect and the contractor as follows:

“All work on this project is to come to a complete standstill except the engineering required to complete the design in the new site location. Also any design changes that may be necessary should be undertaken and completed.
“As soon as legal action regarding this project is resolved, this office will advise you further on the future course of action to be pursued.”

In reply to this letter the architect wrote the contractor, stating: “You are accordingly requested to stop all purchasing of any ma *865 terials for this project and all work is to come to a complete standstill pending outcome of legal action being undertaken by the Owners.”

On July 18 the contractor wrote the Director of Public Works confirming the understanding that the contractor was ready, willing and able to proceed with the contract but was “prevented from doing so at this time by the injunction,” and that “any additional costs occasioned by the delay would be borne by the City.” In reply to this letter the director wrote the contractor that this statement “is proper for it is certainly our intention that you as the contractor should suffer no loss due to the situation that has developed over which you had no control.”

During the pendency of the Wicker Apartments appeal, in reply to a letter from the contractor, the contractor was told that after a decision in that case, which was expected in September, 1957, the city would be “in a better position” to answer the inquiries which the subcontractors were making of the contractor as to the status of the project.

After the decision of the appellate court on September 6, affirming the legality of the issuance of the permit by the Board of Zoning Appeals, there was some uncertainty as to whether the city would proceed with the contract. In a letter dated September 19, 1957, to counsel for the contractor, the City Attorney, after referring to the provisions in the contract under which the city and the contractor had the right to terminate it, requested that he be advised “whether Ewing expects to proceed with the work;” whether it would “exercise its rights, if any, under the contract” because the work had been stopped “through no act or fault of Ewing;” “should the city insist upon proceeding with the work, what claims, if any,” the contractor would assert against the city on account of the delay in the performance of the contract; and “should the city exercise its rights to cancel the contract,” what claims the contractor would make against the city.

Counsel promptly replied that the contractor was still ready, willing and able to proceed with the contract, as it had been all along; that the contractor had entered into firm contracts with subcontractors for work to be done on the project; and that without information from them the contractor was unable to say what claims it would assert against the city in the event the city decided to cancel the contract.

Shortly after the receipt of this letter a conference of the parties was held, at which it was decided that all pending matters should *866 be postponed until the city had determined whether it would proceed with the project. On December 4, 1957, the City Attorney wrote counsel for the contractor as follows:

“After public hearings and informal discussions, it appears that the Council will abandon the project for the construction of the juvenile detention home on the Pine Camp property, although it has not taken final action with respect thereto.
“It is recognized that the City has a binding contract with A. H. Ewing's Sons, Incorporated, for this construction. Will you please advise this office in detail of the damages or compensation the contractor expects to assert against the City on account of being unable to perform its contract. The items of claim or damage should be in such detail as will enable the City to check them for accuracy and reasonableness.
“We would like, if possible, to have the claim segregated so as to cover the damages during the period the contractor and the City were prevented from proceeding with the contract under the restraining order of the Law and Equity Court entered on July 6, 1956, and which expired on October 1, 1956.” (Emphasis added.)

The contractor furnished the requested information.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wood v. Adamson
59 Va. Cir. 25 (Virginia Circuit Court, 2002)
Lewis v. Kim
46 Va. Cir. 227 (Alexandria County Circuit Court, 1998)
Novick v. Dillon
44 Va. Cir. 111 (Richmond County Circuit Court, 1997)
Lyle, Siegel, Croshaw & Beale, P.C. v. Tidewater Capital Corp.
457 S.E.2d 28 (Supreme Court of Virginia, 1995)
Kang v. Roof
24 Va. Cir. 193 (Fairfax County Circuit Court, 1991)
Wayne Insulation Co., Inc. v. Hex Corp.
534 A.2d 1279 (District of Columbia Court of Appeals, 1987)
Sweeney Co. v. Engineers-Constructors, Inc.
823 F.2d 805 (Fourth Circuit, 1987)
Agelasto v. Frank Atkinson Real Estate
327 S.E.2d 84 (Supreme Court of Virginia, 1985)
Pennsylvania State Shopping Plazas, Inc. v. Olive
120 S.E.2d 372 (Supreme Court of Virginia, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
114 S.E.2d 608, 201 Va. 862, 1960 Va. LEXIS 171, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-richmond-v-a-h-ewings-sons-inc-va-1960.