Drhew v. Altoona City

15 A. 636, 121 Pa. 401, 1888 Pa. LEXIS 675
CourtSupreme Court of Pennsylvania
DecidedOctober 1, 1888
DocketNo. 59
StatusPublished
Cited by13 cases

This text of 15 A. 636 (Drhew v. Altoona City) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Drhew v. Altoona City, 15 A. 636, 121 Pa. 401, 1888 Pa. LEXIS 675 (Pa. 1888).

Opinion

Opinion,

Mr. Justice Clark :

This action of covenant is brought to recover the amount claimed to be due to Drhew & Bell, from the city of Altoona, upon a contract for the construction of a reservoir at Kittanning Point, for the supply of the city with water; and also for damages upon an alleged bread) of the contract on the part of the city. The work was done under the terms of an agreement under seal, dated August 3,1881; it was to be performed according to certain specifications set forth in the contract agreeably and subject to the directions of the city engineer, and be completed by the 31st August, 1882, to his satisfaction and acceptance. The location and general method of construction were defined by the contract, but changes and alterations therein were provided for as the engineer might determine, and the allowance or deduction consequent thereon was to be made by him; extra work was not to be compensated unless performed upon his order, and then according to his estimate of the value thereof; the work was to be performed with such force as the engineer should deem adequate to its completion within the time specified, and if the force in his opinion was inadequate, he had the right to employ additional force; pay for the same, and charge to the account of the contractor; for any omission or neglect in the requirements of the contract on the pai't of the contractors, the engineer had authority to forfeit their rights under it, and to stop the work at any time when in his opinion the best interests of the city required it. The city agreed to pay for the different kinds or classes of work at certain rates specified in the contract; the whole amount of the compensation thus depending upon the quantity of each kind of work, which should be actually performed. Although full specifications and plans were agreed upon, and working drawings prepared in advance, it was expressly provided, that the quantities exhibited to the contractors were necessarily only approximate; they furnished in the language of the contract itself “ only general information, and will in no way govern or affect the final estimate, which will be made [418]*418out on the completion of the work, from actual measurements aud established facts, not determinable at the time of letting the work.” Provision was made for estimates of the work done, and for payment therefor, as follows, viz.: “ On or about the last day of each month, during the progress of this work, an estimate shall be made of the relative value of the work done, to be judged of by the engineer, and eighty-five per cent of the amount of said estimate shall be paid to the party of the first part, on or about the first day of each month. And when all the work embraced in this contract is completed, agreeably to the specifications, and in accordance with the directions and to the satisfaction and acceptance of the engineer and city council, there shall be a final estimate made, of the quality, character, and value of said work, according to the terms of this agreement, when the balance appearing due to the said parties of the first part shall be paid to them, within thirty ■days thereafter.” Every part of the work was to be executed ■“ under the direction and subject to the approval of the engineer in charge,” and it was understood, “ that in all questions or matters relating thereto, or to the work, or the contract for the same, the decision of the engineer in charge shall be final and conclusive without appeal.”

From these provisions of the contract it seems plain, that monthly estimates were required as mere approximations; they were, to be made of the “ relative value ” of the work done; that is to say, the value was not absolute; it was the estimated value of a part, as it stood in connection with the whole. Each monthly estimate therefore bore relation to and was subordinate to the final one. The estimates were approximate, for, under the terms of the contract, it was only on the completion of the whole that the absolute amount of the compensation could be computed. The final estimate was to be made “ when all the work embraced in the contract is completed,” and it was agreed that an estimate should then be made of the quality, character, and value of said work, that is to say, of the whole work according to the terms of the agreement, when the balance appearing to be due shall be paid, etc.; this was the final estimate. It was to be made from actual measurements and established facts, which the parties agreed were not determinable at the time of the letting of the work, and in the [419]*419nature of the case were not determinable until its completion. The contractors were, however, entitled to be paid, during the progress of the work, according to these monthly estimates, and it cannot be doubted that when the city refused to pay the estimate No. 15, made November 1, 1882, a right of action accrued to the contractors, as against the city, for recovery of the amount. The value of the work as it progressed was a matter which, by the terms of the contract, was expressly submitted to the engineer; the estimate was his adjudication of it, and that was conclusive until the final estimate was made.

The work was commenced as agreed upon, but it was not completed within the period specified; no complaint is made that the work was unduly delayed; the engineer did not deem it necessary to employ additional force, and it is fair to presume that he deemed the force adequate; the delay, it is conceded, arose from the extent and difficulty of the work, beyond what had been anticipated. The reasons assigned for the refusal to pay were, first, that the work was not performed in a substantial and proper manner; this, however, was disposed of by the jury. And second, that the city had no money to pay it; that the 160,000 appropriated to this purpose was exhausted, and the city had no power under the constitution and laws of the state to provide further funds. Under these circumstances the contractors had an undoubted right to stop the work and they did stop it. They demanded the final estimate, which the engineer, at first, refused to make ; it was not an absolute refusal, however; he refused until he would see what the city would decide to do. It may be, perhaps, that the contractors were not bound to await the engineer’s convenience, or until he could see what the councils might determine in the matter, before bringing suit, for in some cases this might occasion the loss of the claim. That question is not raised on this record and we do not decide it.

The demand for a final estimate was properly addressed to the city; the engineer was the servant of the city, and it was the city’s duty to have the final estimate made by the engineer. If upon demand this was not done with reasonable dispatch, the plaintiffs were entitled to their action and to prove the value of their work otherwise: McMahon v. N. Y. & Erie R. [420]*420Co., 20 N. Y. 463; Herrick v. Belknap, 27 Vt. 673. But we are clearly of opinion that there was not a refusal, in such, terms and for such length of time, under the circumstances, as would oust the jurisdiction of the engineer, in the adjustment of the matters involved in the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth v. Eastern Paving Co.
136 A. 853 (Supreme Court of Pennsylvania, 1927)
Commonwealth v. Eastern Paving Co.
8 Pa. D. & C. 357 (Dauphin County Court of Common Pleas, 1926)
Ahrens v. Reading
104 A. 511 (Supreme Court of Pennsylvania, 1918)
Berry v. Huntington Masonic Temple Ass'n
93 S.E. 355 (West Virginia Supreme Court, 1917)
Texas Fidelity & Bonding Co. v. Rosenberg Independent School Dist.
195 S.W. 298 (Court of Appeals of Texas, 1917)
Williams v. Mount Hood Ry. & Power Co.
110 P. 490 (Oregon Supreme Court, 1910)
Martindale v. Town of Rochester
86 N.E. 321 (Indiana Supreme Court, 1908)
City of Atchison v. Rackliffe
96 P. 477 (Supreme Court of Kansas, 1908)
Elizardi v. Kelly
2 Teiss. 279 (Louisiana Court of Appeal, 1905)
Koch v. Kuhns
6 Pa. Super. 186 (Superior Court of Pennsylvania, 1897)
Fisher v. Borough of South Williamsport
1 Pa. Super. 386 (Superior Court of Pennsylvania, 1896)
Walmsley v. Levy
36 La. Ann. 226 (Supreme Court of Louisiana, 1884)
Morris v. Cain's Executors
34 La. 657 (Supreme Court of Louisiana, 1882)

Cite This Page — Counsel Stack

Bluebook (online)
15 A. 636, 121 Pa. 401, 1888 Pa. LEXIS 675, Counsel Stack Legal Research, https://law.counselstack.com/opinion/drhew-v-altoona-city-pa-1888.