Vecellio & Grogan, Inc. v. Division of Highways

19 Ct. Cl. 147
CourtWest Virginia Court of Claims
DecidedNovember 18, 1992
DocketCC-91-243
StatusPublished

This text of 19 Ct. Cl. 147 (Vecellio & Grogan, Inc. v. Division of Highways) is published on Counsel Stack Legal Research, covering West Virginia Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vecellio & Grogan, Inc. v. Division of Highways, 19 Ct. Cl. 147 (W. Va. Super. Ct. 1992).

Opinion

PER CURIAM:

Vecellio & Grogan, Inc., a West Virginia corporation (hereinafter “V&G”, brings this action against the West Virginia Division of Highways (hereinafter “D/H”) for damages resulting for an alleged breach of a highway construction contract between them, which called for excavation and construction on Project ID-77-2(50)77 at the Sharon Interchange of the former West Virginia Turnpike but now Interstate 77, in Kanawha County, West Virginia.

The contract, dated 31 May 1993 is divisible, one part relating to excavation and removal of unclassified material, and one part relating to new road construction. Performance by V&G was to be complete by 13 July 1986, without intermediate completion dates as to either part. The construction part of the whole contract is otherwise irrelevant to this proceeding.

By the terms of the excavation contract, V&G was to remove an estimated 1,469,926 cubic yards of unclassified material, consisting of rock, shale, and dirt, from its place in nature along the easterly side of the Turnpike, a two-lane road, to the end that the planned Interstate highway would be wide enough to accommodate two lanes of traffic in each direction.

In preparing its bid of $4.25 per cubic yard of material excavated and removed, V & G took into consideration the fact that the cost of excavating rock and shale, the greater part of the mass to be removed, was appreciably higher than the cost of removing dirt, but the bid price, accepted by D/H represented a blend of costs for all materials.

It was necessary for D/H to maintain the flow of traffic over the Turnpike during the period of construction, and it was provided in the contract that V&G should not have the right, in removing excavated material, to go upon or cross the Turnpike with its hauling trucks. Accordingly, V&G devised and put into operation a system for material, under which it started excavation operations at the southerly end of its excavation sector, removed the excavated material by trucks in a southerly direction, and, as the face of the excavation operations advanced in a northerly direction, the newly excavated material was removed by trucks over the already excavated area, southward.

The northerly end of the sector awarded to V & G for excavation abutted upon a [148]*148sector designated as Project ID-77-2(51)80, upon which the Nello L. Teer Company (hereinafter “Teer”) was to perform excavation and construction under a contract dated 17 June 1983. Apparently, by mistake, the northerly end of V & G’s area of responsibility was also included in the Teer contract, although it had already been awarded to V & G. Teer was informed by D/H, by letter dated 5 August 1983, that excavation of the “overlap” area would be performed by V & G, and Teer’s contract was amended to reflect the deletion.

V & G conducted excavation operations in 1983 until weather conditions forced it to suspend operations until the following spring. By 18 September 1984 it had completed more than two-thirds of its excavation work and was then moving northward through rock, which it had to excavate and remove in order to gain access to the northern area of its excavation responsibility, the “overlap” area. Supervisory personnel of V & G testified that they then estimated that, at the rate work was proceeding, V & G would reach the “overlap” area in November 1984, and that thereafter the unclassified material, which was stipulated to be mainly dirt, and containing 62,745 cubic yards, could have been removed at the rate of 3,00 cubic yards per working day, or about 21 working days.

On 18 September 1984, at a meeting convened by D/H and attended by representatives of V & G then present, was asked by a representative of V & G then present, was asked by a representative of D/H weather V & G could then move the material in the “overlap” area, and Smith’s reply was that V & G could not do so at the time, as it was obvious that V & G had not yet reached the area by excavating in that direction. Thereupon, on the same day D/H took the “overlap” area from V & G and awarded it to Teer excavation, over the protest of V & G. Teer thereafter proceeded to excavate and remove the dirt from the “overlap” area, completing the work well before the end of 1984.

D/H attempted to justify its decision to take the work from V & G and award it to Teer, by asserting a right to do so under the provisions of Sec. 104.2 of the Standard Specifications for Roads and Bridges, made part of the contract and providing in pertinent part as follows:

“104.2 - Altercation of Plans or Character of Work.
The Department reserves the right to make alterations in the Plans or in the quantities of work as may be necessary or desirable at any time either before or during the work under the Contract. Such altercations shall not be considered as a waiver of any conditions of the Contract nor shall they invalidate any of the provisions thereof, except as provided herein.”
The Department may omit any item or items in the Contract, provided that notice of intent to omit such item or items is given to the Contractor before any material has been purchased or labor [149]*149involved has been performed, and such omission shall not constitute grounds for any claim for damages or loss of anticipated profits. The Department may omit any item or items shown in the Proposal, at any time, by agreeing to compensate the Contractor for the reasonable expense already incurred and to take over at actual cost any unused material purchase in good faith for use for the item or items omitted. ...”

We do not agree with the construction sought by D/H for the word “omit”, for the following reasons:

(a) the language of the specifications is plain and unambiguous, the word “omit” being commonly understood to refer to something deleted and not to something taken from one’s contract and handed to another for performance; see Burke v. Board of Improvement Paving District No. Five, 179 S. W. 654, (Ark. 1915); and Gallagher v. Hirsh, 61 N.Y. S. 609 (App. Div. 1899);
(b) from the record it is quite clear that V & G was well advanced in its performance and that it received no notice from the D/H of the latter’s intent to take the work from V & G;
(c) were the interpretation sought by D/H to be accepted generally, building contracts would be so uncertain and risky, not to mention litigious, as to create unsettled contracts and an unmanageable condition in the industry.

We conclude that the excavation contract of 31 May 1983, between D/H and V & G was unjustifiable breached, in part, by D/H, by its making further performance by V & G impossible, and that V & G is entitled to such damages as were caused by the breach of contract. We proceed to a consideration of the proper measure of damages.

In Restatement, Contracts 2d, it is provided in pertinent part:

Sec. 344. Purposes of Remedies
Judicial remedies under the rules of this Reinstatement serve to protect one or more of the following interests of the promisee:
(a) his “expectation interest,” which is his interest in having the profit of his bargain by being put in as good a position as he would have been had the contract been performed;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Franklin v. Pence
36 S.E.2d 505 (West Virginia Supreme Court, 1945)
Burke v. Board of Improvement Paving District No. 5
179 S.W. 654 (Supreme Court of Arkansas, 1915)
Berry v. Huntington Masonic Temple Ass'n
93 S.E. 355 (West Virginia Supreme Court, 1917)
Polino v. Keck
92 S.E. 665 (West Virginia Supreme Court, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
19 Ct. Cl. 147, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vecellio-grogan-inc-v-division-of-highways-wvctcl-1992.