Burke v. Board of Improvement Paving District No. 5

179 S.W. 654, 120 Ark. 435, 1915 Ark. LEXIS 71
CourtSupreme Court of Arkansas
DecidedOctober 25, 1915
StatusPublished
Cited by1 cases

This text of 179 S.W. 654 (Burke v. Board of Improvement Paving District No. 5) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burke v. Board of Improvement Paving District No. 5, 179 S.W. 654, 120 Ark. 435, 1915 Ark. LEXIS 71 (Ark. 1915).

Opinion

Kirby, J.

This suit was brought by Burke Bros, for an ¡accounting and to recover the balance claimed to be due under a contract with Improvement District No-. 5 of the City of Fort .Smith, for paving the streets of said city. The contract provided for paving the roadways of all the streets of said city and the work was carried on hy them during a period of 5 or 6 years, after they had erected a brick manufacturing plant at an expense of near $150,000, in the City of Port Smith to comply with the terms of the contract in furnishing brick manufactured in Port Smith for "the work.

A great mass of testimony was introduced and the record is voluminous. A master was appointed by the chancellor and reported his findings on the different claims made, and upon exceptions to the master’s report, the chancellor found in favor of appellants on their claim for retained percentage $38,297.86, of the 'amount due for paving, and for pine headers $197.88, and for iron gutter plates, $377.00 and rendered a decree for the whole sum, $42,260.88 found to be due, from which Burke Bros, appealed, contending that the chancellor erred in finding 'against them on their other claims and in reducing their claims on the items for pine headers and iron gutters.

The court held against appellees on all claims made byway of counter-claim .and set-off and they also appealed.

In the notice and proposal for bids sent out by the district it was stated ‘ ‘ The approximate quantities upon which 'bids will be received and compared are as follows:

“Square yards of completed brick pavement laid on sand foundation, 20,000 sq. yd.
“Square yards of completed brick pavement laid on concrete foundation, 20,000 sq. yd.
“Cubic yards of concrete in place for gutterways, 4.000 cu. yd.
“Pounds of cast iron cover plates for gutterways, . 300.000 pounds.”

The bidders were .also advised “to make such examinations as may be necessary to inform themselves in respect to present conditions of the streets and local surroundings before submitting proposals.”

Appellants’ bid of 81 3-4 cents per square yard for the pavement on sand foundation, $1.46 per square yard for pavement on concrete foundation, $12.00 for each yard of concrete in place for guttering, and 3 cents per-pound for iron covers for gutter wlays, all materials to be furnished and work done by the bidder, was the lowest bid and accepted by the board and a contract tríade with them.

The contract as entered into for the construction of the paving, contains no provision relative to the particular kind and amount of paving to be done and makes no reference to the proposals for bids, nor bids received, except it recites that Burke Bros., party of the first part, “in competition submitted the lowest and best tender for constructing the paving improvement in Paving District No. 5, of the City of Fort Smith, Arkansas, said improvement being as follows, viz.: “The construction and completion of the paving of the roadways of the streets and avenues in said Paving District No. 5, as indicated by said board of improvement, and furnishing the necessary labor, materials, tools and plant therefor.” The other provisions necessary to be set out are Sections. 9, 14 and 15 of the contract and the specifications relating to concrete iand gutterways as follows:

“9. If, in the judgment of the engineer, the work is not being pushed with the degree of activity necessary to its completion within the specified time, then it shall be at his option upon written notice ¡and approval of the board, to employ isuch additional force of men as may be required, and to purchase material in opea market and deduct the cost thereof from money due the contractor.
“14. The engineer, in concurrence with the board, shall have the right to make alterations in the line, grade, plain, form ¡and quantity of the work herein contemplated, either bef ore or after the commencement of the work.

If such alterations diminish the quantity of the work to be done, they shall not constitute a claim for damages on 'anticipated profits on the work 'dispensed with; if they increase the .amount of work, .such increase shall be paid for according to the quantity actually done, and the price or prices stipulated for such work in this contract.”.

“15. In consideration of the completion by the said first party of all work embraced in this contract in conformity with the specification and stipulations herein contained, the Board of Improvement of Paving District No. 5 of the City of Fort Smith, Arkansas, party of the second part, hereby agrees to pay said first party the following prices:

For each square yard of completed brick pavement laid on sand foundation the sum of eighty-one and three-quarter cents (81 3-4 cents) dollars;

For each square of completed brick pavement laid on concrete foundation the sum of one and forty-six one hundredths ($1.46) dollars.

For each cubic yard of concrete in gutterways, the sum of twelve ($12.00) dollars;

For each pound of cast-iron cover for gutterways, the sum of three (3) cents.

“ Concrete. If upon any street to be paved the Board of Improvement should decide to use a concrete base due to .the presence of street or steam railway tracks, or for any other cause, the engineer may order that the surface of the sulbgrade be brought eleven (11) inches below and parallel with the finished cross-section of the street, and that upon this subgrade., -when properly prepared, there shall be laid a layer of Portland cement concrete, not less than five (5) inches in thickness when tamped. * * *”

£ ‘ Gfutter-ways. At such street and alley intersections as may be designated by the engineer there shall be constructed by the contractor, as a part of the street pavement, covered gutters or waterways, the same to conform to the details therefor on file. * * * ”

Appellants after constructing a plant for the manufacture of .paving brick out of shale, at Fort .Smith, which required almost two years, proceeded with the work of paving the streets as they were designated for that purpose by the engineer of the .district. They were delayed greatly in the prosecution of ithe work of paving by the failure of the property owners to construct the sidewalks and curbs on the abutting property and were compelled often to move their working companies and appliances to different streets or to different sections of the same street in order to continue the work without too great •break or delay. Neither the paving district nor the contractors were at fault for the failure of the property-owners to sooner construct their sidewalks and curbs. The city attempted to compel the construction by an ordinance which w>as declared void by this court and finally by another ordinance passed after a grant of power by the Legislature succeeded in having it done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vecellio & Grogan, Inc. v. Division of Highways
19 Ct. Cl. 147 (West Virginia Court of Claims, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
179 S.W. 654, 120 Ark. 435, 1915 Ark. LEXIS 71, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burke-v-board-of-improvement-paving-district-no-5-ark-1915.