Polino v. Keck

92 S.E. 665, 80 W. Va. 426, 1917 W. Va. LEXIS 50
CourtWest Virginia Supreme Court
DecidedMay 8, 1917
StatusPublished
Cited by4 cases

This text of 92 S.E. 665 (Polino v. Keck) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Polino v. Keck, 92 S.E. 665, 80 W. Va. 426, 1917 W. Va. LEXIS 50 (W. Va. 1917).

Opinion

MilleR, Judge:

The declaration in assumpsit, by setting the same out in full therein, averred a contract between plaintiff and defend'ant, with mutual promises and undertakings, and whereby-for the consideration of thirty cents per cubic yard to be paid plaintiff by defendant, as provided therein, plaintiff agreed to supply sufficient teams and to haul from the barges or flats of the defendant to the site of the construction work all the sand and gravel that would be required each day by [428]*428the Crossan Construction Company, contractor, in the work of constructing the Buckhannon and Northern Railroad, between certain stations thereof, and as called for in the contract between defendant and said construction company, and referred to in the contract declared on, said' hauling to commence on the 8th day of May, 1914. And in addition to the price to be paid by defendant therefor, that defendant thereby stipulated and agreed on his part, to keep sufficient sand and gravel at said barges or flats for the purposes aforesaid, and also to furnish an electric motor for the use of plaintiff in hauling said sand and gravel, plaintiff to furnish a competent man to operate the same and to pay him for his 'services, and for the price of the electricity consumed, not to exceed, however, ten dollars per month, and that defendant thereby also agreed to provide a convenient and suitable place for the teams to move said sand and gravel along said construction work for ingress and egress of the teams, as provided in the contract between him and said construction company.

And by way of averring performance of said contract by plaintiff and breaches thereof by defendant, it is further alleged that plaintiff had always from the time of making said contract performed and fulfilled the same in all things required to be done on his part, that on the day appointed by said contract and at great expense he- provided all teams, wagons, and other materials necessary and entered upon and commenced said work, and did perform .the same in part by hauling and delivering about three hundred and fifty cubic yards of said sand and gravel to the satisfaction of defendant, and had always thereafter been ready and -willing to perform and complete the hauling of said sand and gravel, as required by said agreement, and of which defendant had notice. Nevertheless, as it is further averred, defendant, .contriving and wrongfully intending to injure plaintiff did not and would not perform the said agreement, promises and undertakings on his part, but craftily and subtly deceived plaintiff in that he did not and would not keep sufficient sand and gravel at said barges or flats to keep said teams busily engaged or to meet the demands of the said [429]*429Crossan Construction Company, but on the contrary wholly negleeted and refused to do so. And it is also averred that in further disregard of his said promises and undertakings defendant afterwards, to-wit, on May 14, 1914, did not and would not permit or suffer plaintiff to proceed with and to complete said work, and then and there wholly hindered and prevented him from so doing, and then and there wrongfully discharged plaintiff from any further performance or completion of said agreement, whereby plaintiff had lost and been deprived of the pro-fits and advantages which he otherwise might and would have derived and acquired from the completion of said work in accordance with said contract. He further averred that there remained to be hauled approximately forty thousand cubic yards of said sand and gravel, his profits from hauling which would have been approximately nine thousand five hundred dollars, and of all which plaintiff by the action of defendant had been deprived, wherefore, he sued, &c.

The judgment below overruling defendant’s demurrer to the declaration is relied on here as error calling for reversal. Several points are urged. (1) That it is not disclosed how plaintiff proposed to treat the contract, (a) whether as rescinded, and to recover on the quantum meruit for the work done, (b) or as kept alive for the benefit of both parties, and himself ready and able to perform, and at the end of the time for completion of the contract to recover under the contract, or, (e) to treat the breach or breaches, of the contract by defendant as putting an end to it for all purposes of performance and to sue for the profits he would have realized if he had not been prevented from performing it; (2) that it charges a violation of the contract between the Crossan Construction Company and defendant to which plaintiff was not a party, wherefore multifarious; (3) that it avers a discharge of plaintiff by defendant from performance or completion of the contract when the fact is plaintiff was not employed by defendant, that the breaches are not positively averred but by way of” recital only, that it is alleged that ‘ ‘ defendant did not keep sufficient sand and gravel at said barges or fiats to keep the said teams busily engaged”, [430]*430and furthermore that defendant “discharged the said plaintiff from any further performance or completion of said agreement”, both of which breaches could not concur, wherefore they are inconsistent and the declaration subject to demurrer; (4) that the declaration is indefinite in that it does not aver wherein defendant prevented or rendered plaintiff unable to carry on the contract, nor wherein the damages sued for as profits would have amounted to the sum alleged, but only alleges the amount which would have been due had a certain amount of gravel and sand been used by said construction company. We see no substantial merit in either of these points. True the declaration is very inartistically drawn; such papers ought to be prepared with greater care and accuracy, and with some reference to approved forms.

On the first point it is quite clear from the averments that plaintiff did elect to treat the contract as repudiated and at an end for all purposes of performance and to sue for profits, in accordance with the rule laid down in Bare v. Victoria Coal & Coke Co., 73 W. Va. 632. True, as stated in point 4, there is an averment of failure on defendant’s part to keep sufficient sand and gravel at the barges or flats, but this was in anticipation perhaps of the defense that plaintiff did not as provided by the contract haul all the sand and gravel required each day in the work of constructing said railroad, and as averring one of the means employed by defendant to prevent him from carrying out his contract. The main averment on which plaintiff relies is that defendant discharged him and would not permit or suffer him to proceed with the work of completing the contract. We think these general averments sufficient within the rule of Bare v. Victoria Coal & Coke Co., point 1 of the syllabus, supra, to save the declaration from attack by demurrer and to put the demurrant on his defense of pleading to the issue.

The other points of demurrer are sufficiently covered by what has been said upon the first point more or less involved therein. Besides, they are extremely technical and have no substantial merit therein.

The giving and refusing of instructions to the jury is especially relied on for reversal. At the instance of plain[431]*431tiff the court gave six instructions, which were all objected, to and the points saved, by a bill of exceptions. The most general objection to these instructions is that, if propounding good law, they are abstract and with no evidence upon which to predicate the facts assumed therein.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vecellio & Grogan, Inc. v. Division of Highways
19 Ct. Cl. 147 (West Virginia Court of Claims, 1992)
Holcombe v. Laurel Creek Coal Co.
123 S.E. 248 (West Virginia Supreme Court, 1924)
Bulick v. Milkint
111 S.E. 310 (West Virginia Supreme Court, 1922)
McGrew v. Ide Estate Investment Co.
187 P. 887 (Supreme Court of Kansas, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
92 S.E. 665, 80 W. Va. 426, 1917 W. Va. LEXIS 50, Counsel Stack Legal Research, https://law.counselstack.com/opinion/polino-v-keck-wva-1917.