Town of Sterling v. Hurd

44 Colo. 436
CourtSupreme Court of Colorado
DecidedSeptember 15, 1908
DocketNo. 5767
StatusPublished
Cited by4 cases

This text of 44 Colo. 436 (Town of Sterling v. Hurd) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Sterling v. Hurd, 44 Colo. 436 (Colo. 1908).

Opinion

Mr. Justice Gabbert

delivered the opinion of the court.

Appellee Hurd and the appellant, the town of Sterling, entered into a contract whereby the former agreed to construct a system of water works for the [437]*437purpose of supplying the inhabitants of the town with water for • domestic, fire and other purposes. Hurd was to furnish all the materials and perform all the work necessary to complete the system. The contract contemplated the building of a reservoir, the construction of a wooden pipeline about six miles in length, a distributing system within the corporate limits of the town, and the installation of an auxiliary fire pump for the purpose of increasing the pressure when the occasion demanded. When the system was completed, the town refused to accept it, because it had not been constructed in accordance with' the terms and conditions of the contract. Hurd brought suit to recover the balance claimed to be due him, alleging in his complaint that he had completed the construction of the system according to his contract. The town answered,' that the wooden pipeline was laid and constructed in such a negligent and unskillful manner as to permit the water to escape and leak in large quantities, .and that the system had been constructed in such a negligent, careless and unworkmanlike manner that the pipeline was frequently broken, and the leakage was so great as to render it almost useless, and that because of these defects the pumping system could not be used for fire protection, and that in order to overcome the defective conditions of the system resulting from the negligence of the plaintiff in constructing it, it would have to be relaid and reconstructed, to the damage of the town in the sum of twenty-five thousand dollars. To this answer the plaintiff filed a replication denying its averments.

At the conclusion of the testimony the court withdrew the counterclaim of the defendant for damages from the consideration of the jury, evidently upon the ground that according to the contract entered into between the parties, and the testimony, [438]*438the town had waived its right to litigate the questions of alleged imperfections in the system. There was a verdict and judgment for the plaintiff,, from which the defendant appeals.

The contract between the parties provided that the plaintiff was to furnish all the materials and perform all the labor necessary to construct a waterworks system for the town in accordance with specifications which were attached to and declared and accepted as a part of the agreement. Among other provisions, it contained the following, as paragraph 9:

“The said engineer herein mentioned and referred to is understood to be an engineer to be appointed by the said town of Sterling, whose particular business shall be to see that the said contractor performs the work of constructing and erecting said water works according to the terms of said contract and the plans and specifications hereto attached, with reference to the labor as well as to the material furnished and used in the construction and erection of said water-works system.”

The specifications above referred to contained the following clauses:

“1. In the following specifications, wherever the words ‘town’ and ‘engineer’ are used, they refer respectively to the town of Sterling, Colorado, and to the engineer appointed by said town as its representative.
“5. All materials are to be the best of their respective kinds, and new and unused when installed, and all workmanship shall be thorough and first-class, and both material and workmanship shall be subject to the inspection and approval of the engineer. The engineer shall have full power to reject all materials not conforming to the plans and specifications, and all unsound or defective work so re[439]*439jected shall be replaced by the contractor at his own expense immediately upon receiving written notice to do so. * ' * *
“12. The work shall be completed within the timé specified hereafter. If in entire accordance with these specifications, it will then be accepted. If not in accordance with these specifications, the contractor must take immediate steps to rectify any defect at his own expense, and at such time as is most convenient to the town.
“14. The contractor shall be responsible for the entire work as a. whole until it is accepted by the town, and he will under no consideration be released from responsibility for any part of the work until such time as the plant is accepted.
“20. When the contract is completed the system will be tested by the engineer. If this test shows the system to be in entire accordance with these specifications, the balance of the amount of the contract price will be paid to the contractor by the town. ’ ’

The specifications provided in detail with respect to the staves of which the wooden pipeline was to be constructed; the size and material of the pipe bands, and the spacing of the latter, which should be sufficiently close to render the pipe perfectly watertight. The specifications also provided that the contractor should build the foundation for, and install the auxiliary fire pump, and connect it with the system.

On behalf of the plaintiff the testimony was to the effect that the materials employed in the construction of the system and the work performed in constructing it conformed to the standard required by the 'contract and specifications, and, generally, that the system was properly constructed and in good condition. There was also testimony on the part of [440]*440the plaintiff to the effect that during the progress of the work an engineer for the town was present when the wooden pipeline was being constructed, with the exception of about 1,500 feet; that the engineer found no fault with the pipeline, and seemed to be perfectly satisfied; that he inspected the material before and after the pipeline was constructed and accepted the pipe after it was constructed.

On behalf of the town the testimony was to the effect that an engineer representing it overlooked the construction of the pipeline and the distributing system through the town; that he called the attention of the contractor to the fact that building the pipe on the top of the trench which was dug to receive it, and then lowering it when assembled, caused the joints and sections of which it was composed to open, because it did not have sufficient tensile strength to hold together when being lower'ed; that the contractor agreed to close the joints which had been separated, and to see that the rest were butted squarely together. It also appears from the testimony that on a certain date the contractor notified the engineer that he would quit work for something like six weeks, but that he resumed work within a week, and that about 1,500 feet of the pipeline was laid and covered when the engineer' for the town was not present.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Napper v. Schmeh
773 P.2d 531 (Supreme Court of Colorado, 1989)
Hines v. Oliver
291 P.2d 693 (Supreme Court of Colorado, 1955)
Berry v. Huntington Masonic Temple Ass'n
93 S.E. 355 (West Virginia Supreme Court, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
44 Colo. 436, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-sterling-v-hurd-colo-1908.