Lewis v. Yagel

28 N.Y.S. 833, 77 Hun 337, 60 N.Y. St. Rep. 23
New York Supreme Court·Decided May 18, 1894·Published·Cited by 9 cases

Opinion

MARTIN, J.

In the complaint, as a first cause of action, it was alleged that the plaintiffs were copartners; that on the 2d day of June, 1886, they entered into a written agreement with the defendant to construct two three-story stores, except party walls, plumbing, and' painting, and to furnish the materials therefor, for the sum of $7,700, part of which was to be paid in installments as the work progressed, and at completion, upon the production of the architect’s certificate that the work was completed in accordance with the contract, the remainder was to be paid; that they performed such work on their part, and the stores were completed and accepted by the defendant; that she paid them the sum of $7,388.85, leaving unpaid $311.35. For a second cause of action it was alleged that on the 5th day of June, 1886, the parties entered into another written contract, whereby the plaintiffs agreed to do the area-wall work, plumbing, gas fitting, put down two wells, and furnish the labor and materials for all such work for the sum of $587; that they performed the contract upon their part, but that no part thereof had been paid. For a third cause of action the plaintiffs allege that between the 2d day of June, 1886, and the 10th day of December of the same year, the defendant became indebted to them in the sum of $9,494.26 for work, labor, and services rendered and performed and for materials furnished at her request, and for which she agreed to pay that sum; that she has paid thereon the sum of $8,595.91, leaving: a balance unpaid of $898.35, with interest from December 11, 1886, for which sum judgment was demanded. The defendant set up in her answer that all the work performed or materials furnished by the plaintiffs were furnished under written contracts which were entered into by and between the parties, and copies of which were made a part of the answer; that the contracts were not fulfilled by the plaintiffs, and by reason thereof she suffered damage to an amount greatly in excess of the amount claimed by them, which was set up as an offset or counterclaim. It was also alleged that she had paid the plaintiffs more than was due upon the contracts between them; that she was not indebted to them in any sum whatever; that certain conditions precedent to the plain[835]*835tiffs’ right of recovery were not performed by them; that the second contract, so far as it related to the area wall, was obtained from her by the fraud and misrepresentations of the plaintiffs, and that it was not performed by them. The answer likewise contained a denial of all the allegations of the complaint not admitted by the answer, and contained allegations that the plaintiffs had been fully paid; that the contracts between the parties had not been either actually or substantially performed by the plaintiffs; and that the defendant had sustained material damage by reason thereof, and demanded judgment for the amount of such damage. The plaintiffs replied to the defendant’s 'answer, denying each and every allegation thereof, and alleging that each and all of the changes which were made in the construction of the buildings mentioned in the complaint and answer herein, so far as the same differed from the plans and specifications thereof, were made at the request of the defendant, with her knowledge and consent, and under the direction of her architect. The defendant served an amended answer, wherein it was averred that the plaintiffs did not perform the work under the second contract between the parties according to the contract, plans, and specifications, and omitted to do the same in a good, proper, and workmanlike manner; that they omitted to put in ventilating pipes, and to vent the traps to the water-closets and sinks, according to the plans and specifications, and as-required by the contract for such plumbing; that they omitted to construct the area wall in the same manner as the area wall of the First National Bank building, mentioned in the contract; that the same was constructed in an improper, imperfect, and unsubstantial manner, and that she sustained damage thereby to the amount of $500, which was set up as an offset or counterclaim in the action. The plaintiffs’ reply to such amended answer denied each and every allegation contained therein respecting the alleged counterclaims, and also alleged that each and all of the alterations and changes or omissions which were made in the work and materials mentioned in the amended answer, so far as the same differed from the plans and specifications, were made at the request of the defendant, with her knowledge or consent, and under the supervision and direction of her architect.

That the work was performed and materials furnished, for which this action was brought, were performed and furnished under the two written contracts between the parties, and in pursuance of their provisions, there can be no manner of doubt. Therefore, to a proper understanding of the questions involved on this appeal, it becomes necessary to examine some of the provisions contained in the contracts between the parties. The first contract between them, which was made June 2, 1886, provided that the plaintiffs should erect, finish, and deliver in a true, perfect, and thoroughly workmanlike manner the building mentioned, except plumbing and painting, agreeably to the plans, drawings, and specifications referred to, under the direction of Blend, who was an architect; the plaintiffs to furnish all the labor and materials, and to be paid therefor the sum of $7,700, which the defendant [836]*836agreed to pay in the manner stated in the contract. Among others, the contract contained the provision that, should the owner, or her agent, during the progress of the work, require any alterations of, deviations from, additions to, or omissions in the said- contract, she should have the right to make such changes, and the same should in no way injuriously affect or make the contract void, but the difference should be added to or deducted from the amount of the contract, as the case might be, by a fair and reasonable valuation. It also provided: “No work shall be considered as extra, unless a separate estimate, in writing, for the same shall have been submitted by the contractor to" the architect and the owner, or her agent, and their signatures obtained thereto.” It contained the further provision that in case of dispute as to the value of extra work or work omitted the same should be valued by two competent persons, one employed by the owner, or her agent, and the other by the contractor, and they should have the power to name an umpire, whose decision should be binding on all the parties. By the contract the last payment was to be made when the building was all completed, and the drawings and specifications returned to the architect, provided that in each case of payment a certificate should be obtained from, and signed by, the architect to the effect that the work was done in strict accordance with the drawings and specifications, and that he considered the payment properly due; the certificate, however, in no way lessening the total and final responsibility of the plaintiffs, and providing further that when the work was all completed a certificate should be obtained by the plaintiffs from the clerk of the office where liens are recorded, and signed and sealed by said clerk, that he had fully examined the records, and found no liens or claims recorded against said work, or on account of the plaintiffs. All ceilings were to be seven-eighths of an inch thick, instead of one-half of an inch, as mentioned in the specifications; and the floors in the third story were to be one and one-eighth inches in thickness, instead of the thickness mentioned therein.

Free access — add to your briefcase to read the full text and ask questions with AI

Lewis v. Yagel, 28 N.Y.S. 833, 77 Hun 337, 60 N.Y. St. Rep. 23 (N.Y. Super. Ct. 1894).

28 N.Y.S. 833 (Lewis v. Yagel) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

National Union Fire Ins. Co. v. Duvall
103 S.W.2d 220 (Court of Appeals of Kentucky (pre-1976), 1937)
Town of Sterling v. Hurd
44 Colo. 436 (Supreme Court of Colorado, 1908)
Langley v. . Rouss
77 N.E. 1168 (New York Court of Appeals, 1906)
L'Hommedieu v. Winthrop
59 A.D. 192 (Appellate Division of the Supreme Court of New York, 1901)
Haist v. Bell
24 A.D. 252 (Appellate Division of the Supreme Court of New York, 1897)
Hawver v. Wright
21 Misc. 211 (New York Supreme Court, 1895)
Murphy v. Stickley-Simonds Co.
31 N.Y.S. 295 (New York Supreme Court, 1894)
West v. Buttner
31 N.Y.S. 1135 (New York Supreme Court, 1894)