MR. JUSTICE SMITH

delivered the opinion of the court.

This action was begun in Park county to recover the sum of $1,694.37, balance alleged to be due for material furnished and [236]*236labor performed upon the Hunters Hot Springs hotel and natatorium, under a written contract with the defendant Murray, acting ,as agent for the defendant, The Monida Trust, a corporation. The cause was tried to the district court, sitting with a jury. A verdict for $1,200 was rendered in favor of the plaintiffs. From a judgment in the amount of the verdict and an order denying a new trial, the defendants have appealed.

The complaint, after setting forth the contract showing that “payments shall be made only upon certificate of the architects,” alleges that “plaintiffs have furnished all the materials and performed all the labor mentioned in said contract to be-by them furnished and performed in accordance with the terms thereof, and have in every respect faithfully performed all the conditions of said contract on their part, and all of said work was completed on the 3d day of August, 1909.” It is then further alleged that the sum of $1,694.37 remains due and unpaid, and “that plaintiffs have not secured the certificate of the architects authorizing the final payment upon said contract as required by the terms thereof, but have made repeated demands upon them for such certificate, and said architects have refused the same, not because of any fault of plaintiffs, but for the reason that defendant Murray has started suit against them, has made payments to plaintiffs without their certificates and without their knowledge, and has practically taken the matter out of their hands. ’ ’

1. It is contended that the complaint does not state facts sufficient to constitute a cause of action, for the reason “that it was necessary for plaintiffs to allege and prove the issuance of the certificate, or show that it was waived by defendants, or withheld by collusion between the architects and the defendants, or [1] fraud of the architects.” We think, however, that the complaint sufficiently shows that the certificate was withheld arbitrarily, or at least for some cause over which the contractors had no control, and such showing is all that is necessary. (Wortman v. Kleinschmidt, 12 Mont. 316, 30 Pac. 280; McGlauflin v. Wormser, 28 Mont. 177, 72 Pac. 428; 6 Cyc. 88; Windham v. Independent Tel. Co., 35 Wash. 166, 76 Pac. 936; Halsey v. [237]*237Waukesha Springs Sanitarium, 125 Wis. 311, 110 Am. St. Rep. 838, 104 N. W. 94; Dyer v. Irr. Dist., 25 Wash. 80, 64 Pac. 1009; McConologue v. Larkins, 32 Misc. Rep. 166, 66 N. Y. Supp. 188; Neagle v. Herbert, 73 Ill. App. 17; Bannon v. Jackson, 121 Tenn. 381, 130 Am. St. Rep. 778, 117 S. W. 504; Michaelis v. Wolf, 136 Ill. 68, 26 N. E. 384; Schmidt v. City of North Yakima, 12 Wash. 121, 40 Pac. 790; Bentley v. Davidson, 74 Wis. 420, 43 N. W. 139; Byrne v. Sisters of Charity, 45 N. J. L. 213.)

2. Contention is made that the evidence is insufficient to sustain the verdict: First, as we understand it, because plaintiffs failed to show a substantial compliance with the terms of the contract on their part; and, second, because the competent evidence in the record, as distinguished from that which is incompetent and irrelevant, discloses the fact that they have been fully paid. First. We think the court properly submitted to the jury the question whether plaintiffs’ part of the- contract was substantially performed. Second. We agree with appellants on this point. It is alleged in the complaint that the contract price was $70,000, upon which the sum of $68,305.63 has been paid, leaving a balance due of $1,694.37. There is no word of extras in the pleading. The record shows that appellants have paid the sum of $77,402.18 on the contract. To offset this apparent overpayment of $7,402.18, plaintiffs undertook to show that they furnished extra work and material to the amount of $9,096.55, and had applied to the payment of this sum certain of the moneys paid by appellants under the contract. Under the head of “extra work,” the specifications attached to the contract provided : ‘1 The owner reserves the right to make any changes whatever, either in the quality or quantity of the work or materials that he may think fit, and the value of the said change or changes, either more or less, must be added to or deducted from the face of the contract. Nothing shall be considered an extra, unless it is agreed upon in writing before said extra work is done, and signed by the owner and contractor and certified to by the architects ; and nothing shall be considered as extra work unless consequent upon some specific change in the plans or specifications. No change in the plans or these specifications can be made with[238]*238out the written order of the architects with the approval of the owner. ’ ’

In the case of Wortman v. Kleinschmidt, 12 Mont. 316, 30 Pac. 280, this court quoted with approval excerpts from the following cases: Russell v. Da Bandeira, 13 Com. B., N. S., 149, and Abbott v. Gatch, 13 Md. 314, 71 Am. Dec. 635. The doctrine laid down in those cases is that, where the contract provides that [2] no extra charges shall be made unless there shall be an order in writing fixing the price, there can be no charge for extra work, no matter what it may be, whether alterations in the plan or mode of doing the work, or additions or improvements in and about the completion of the building, ship, or other structure, unless the order or certificate has first been made. Mr. Chief Justice Blake, in writing the opinion of this court, said: “The contrary rule is a dangerous standard, and impairs the value, and renders uncertain every written contract for the construction of an edifice. ’ ’

At the trial of this case the following proceedings took place while Mr. W. E. Piper, one of the plaintiffs, was a witness: Direct examination: “Q. In building this hotel building were there a number of extras, or not? (Objected to as immaterial and irrelevant under the pleadings. Objection overruled, and exception noted.) Q. Was there considerable extra work done on the work on this building? A. There was. Q. Can you state the amounts the extra work came to? Defendants’ Counsel: The contract already in evidence provides as to the extra work and what shall be considered extra work. Nothing considered extra work unless it is agreed upon in writing. Q. Mr. Piper, were certain extras' ordered by the architects in the progress of the work? (Objected to as incompetent; the contract calls for orders to be in writing. Objection overruled. Exception noted.) A. There were. Q. Were such agreements for extras made in writing? A. They were. Q. And were the prices for such extras agreed upon? (The defendants ask that the writing be produced as the best evidence.) Q. The extras were agreed upon in writing, were they? A. Yes, sir. (Objected to as incompetent.) Court: It is proper to state if they were; as to [239]*239what they were, the writing is the best evidence. Q. Mr. Piper, can you state the total amount that was agreed upon between you and the architects and Mr. Murray that would be paid for the extra work? (Objected to as immaterial and incompetent under the pleadings; the contract required such matter to be determined in writing. Overruled. Exception.) A. The extras amounted to $9,096.55.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blecick v. School District No. 18 of Cochise County
406 P.2d 750 (Court of Appeals of Arizona, 1965)
Gillespie Land & Irrigation Co. v. Hamilton
29 P.2d 158 (Arizona Supreme Court, 1934)
State v. Arnold
275 P. 757 (Montana Supreme Court, 1929)
Roberts v. Sinnott
177 P. 252 (Montana Supreme Court, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
115 P. 669, 43 Mont. 230, 1911 Mont. LEXIS 24, Counsel Stack Legal Research, https://law.counselstack.com/opinion/piper-v-murray-mont-1911.