Neagle v. Herbert

73 Ill. App. 17, 1897 Ill. App. LEXIS 285
CourtAppellate Court of Illinois
DecidedJanuary 6, 1898
StatusPublished
Cited by7 cases

This text of 73 Ill. App. 17 (Neagle v. Herbert) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neagle v. Herbert, 73 Ill. App. 17, 1897 Ill. App. LEXIS 285 (Ill. Ct. App. 1898).

Opinion

Mr. Presiding Justice Adams

delivered the opinion of the Court.

This was an action of assumpsit by defendant in error against plaintiff in error for work done and material furnished in pursuance of a contract between the parties, and for extra work. Defendant in error recovered judgment for the sum of $2,745.26, to reverse which the present suit was brought. The declaration contains only the common counts. John F. Neagle, plaintiff in error, pleaded the general issue.

Under date of May 9, 1892, M. E. Herbert, the defendant in error, entered into a written contract with the firm of F. C. Neagle & Company, general contractors, of which firm the plaintiff in error, John F. Neagle,- is the surviving partner. By this contract defendant in error agreed, “on or before the building is ready for lathing, to finish the roughing and construct and finish the steam heating thirty days after plastering done of the new building situated on southwest corner of Thirtieth street and Michigan avenue, Chicago, for the Potomac Apartment Company, according to the drawings and specifications made by Jul. De Horvath, architect, * * * in a good, workmanlike and substantial manner, under the direction of said architect, and to his satisfaction, to be testified to by a certificate under his hand; and to * * * furnish such good, proper and sufficient materials, workmanship and labor * * * as shall be proper and sufficient for the completion and finishing all the hereinbefore designated steam heating work of said building mentioned in said drawings and specifications,” etc.

The consideration to be paid Mr. Herbert is specified to be $9,385, payable in monthly payments, as the work progressed, on presentation of certificates signed by the architect, fifteen per cent of each estimate being retained until completion of the contract.

The first clause, among other things, provides that “should any dispute arise respecting the true construction and meaning of said drawings and' specifications, the same shall be decided by said architect, and his decision shall be final.”

The fourth clause of the contract provides that should defendant in error neglect or be unable to supply a sufficiency of material or workmen to complete the work on time," or to provide necessary materials and labor as required, and with reasonable rapidity, or show gross carelessness or incompetency, Neagle & Company, after notice in writing to defendant in error, should have power to provide materials and workmen, the cost of same to be deducted from the contract price.

The seventh clause provides that if the said work be delayed by frost or inclement weather, or causes not under the control of defendant in error, causing delay to defendant in error, or in case of alterations or additions requiring additional time, or in case he be delayed by other contractors on the building, on written notice a fair allowance, to be determined by the architect, shall be added to the time stipulated for the completion of the work, and on default in such completion, defendant in error to pay Neagle & Company-dollars per day for every day during which such default should exist, provided the architect should, in writing, certify that the work could have been reasonably completed within the time stipulated, and the addition thereto.

The Potomac building, referred to in the contract, is an eight story building, containing about three hundred and twenty rooms, and has a frontage of about one hundred and twenty-five feet.

Attorney for plaintiff in error, in his argument, makes the following objections:

1. That the court erred in admitting the written contract in evidence, the declaration containing only the common counts.

2. That defendant in error was not entitled to recover in the absence of a certificate from the architect.

3. That a former judgment in favor of defendant in error was a bar to this action.

4. That the evidence of an account stated was insufficent.

5. That the first and second instructions, given at request of defendant in error, are .erroneous.

Of these in their order. It is not claimed by the attorney for plaintiff in error that defendant in error did not perform the work and furnish the material which, by his contract, he agreed to perform and furnish, nor that he did not do the extra work for which he claims compensation.

“Where a contract has been fully executed on the part of the plaintiff, and nothing remains to be done under it but the payment of money, which payment it is the duty, under the contract, of the defendant to make, the plaintiff need not declare specially, and may recover in indebitatus assumpsit.” Lane et al. v. Adams, 19 Ill. 167, citing 2 Phillips, Ev., Ch. 9, p. 108.

In Childs v. Fischer, 52 Ib. 205, 209, the court, alluding to the rule announced in Lane v. Adams, supra, say: “This rule has been frequently recognized by this court, and is regarded as settled law.”

It seems strange that a rule so frequently recognized in practice, and with which members of the bar are so familiar, should be questioned. The contract was properly admitted in evidence “for the purpose of showing its terms, and to measure the damages.” Adlard v. Muldoon, 45 Ill. 193.

JuL. De Horvath, who was the supervising architect of the Potomac building, the building in question, testified that, under the contract between Neagle and the Potomac Apartment Company, the work of Herbert, defendant in error, was required to be accepted by the supervising engineer, W. C. Gillespie, who had been appointed by the witness with the consent of the Potomac company; that he, the witness, told Herbert this, and that, May 24, 1893, the witness told Gillespie, the engineer, to examine and report on the condition of the heating plant, pointing out any defects and omissions, with reference to the contract; that Gillespie examined the plant and reported accordingly; that the witness, after receiving the report, made an appointment with all the parties interested to meet at his office, which they did, there being present there Mr. Moore and Mr. Gretzel, the former the president and the latter the secretary of the Potomac company, Mr. Maher, Herbert’s attorney, Mr. Herbert and John F. Neagle; that at the meeting so held, the report of engineer Gillespie was taken up, section by section, and that all present, including plaintiff in error, agreed upon what was to be done; that Herbert then agreed to do what had been agreed on, and that, June 22, 1893, witness received a report from Gillespie, stating that the work had been done as agreed.

The witness further testified that when he, witness, received the report of Gillespie, the supervising engineer, he thought that Mr. Herbert was entitled to a settlement. Gillespie testified that at the first meeting above mentioned, when the parties present, including the parties to this suit, agreed on what remained to be done, it was agreed that when the deviations pointed out were taken care of and complied with according to the specifications, the plant would be accepted and paid for. This witness also recommended in his report of June 22, 1893, that defendant in error should be settled with.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson-Ross Floors, Inc. v. Scherrer Construction Co.
379 N.E.2d 786 (Appellate Court of Illinois, 1978)
Piper v. Murray
115 P. 669 (Montana Supreme Court, 1911)
King v. Kahn
157 Ill. App. 251 (Appellate Court of Illinois, 1910)
Lutcher & Moore Lumber Co. v. Eells
108 Ill. App. 156 (Appellate Court of Illinois, 1903)
Union Elevated R. R. Co. v. Nixon
99 Ill. App. 502 (Appellate Court of Illinois, 1902)
Congress Construction Co. v. Interior Building Co.
86 Ill. App. 199 (Appellate Court of Illinois, 1899)
Foster v. McKeown
85 Ill. App. 449 (Appellate Court of Illinois, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
73 Ill. App. 17, 1897 Ill. App. LEXIS 285, Counsel Stack Legal Research, https://law.counselstack.com/opinion/neagle-v-herbert-illappct-1898.