School District No. 1 v. Howard

52 P.2d 421, 49 Wyo. 41, 1935 Wyo. LEXIS 8
CourtWyoming Supreme Court
DecidedDecember 10, 1935
Docket1879
StatusPublished
Cited by3 cases

This text of 52 P.2d 421 (School District No. 1 v. Howard) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
School District No. 1 v. Howard, 52 P.2d 421, 49 Wyo. 41, 1935 Wyo. LEXIS 8 (Wyo. 1935).

Opinion

Kimball, Chief Justice.

This is an appeal from a judgment on a general finding in favor of the defendants after trial to the court in an action by a School District against a building contractor and his sureties to recover the amount certified by the architect as damages for defects and omissions in the construction of a school building at Laramie, Wyoming.

The building was constructed under a contract evidenced by writings, called the contract documents, consisting of an agreement, general conditions, drawings and specifications. The agreement and general conditions are the standard form put out by the American Institute of Architects.

The agreement provides that payment of the contract price, 3201,000, shall be made on certificates of the architect who, when he “finds the work acceptable under the contract and the contract fully performed,” *46 is required to issue a final certificate. The architect named in the agreement was W. A. Hitchcock.

The general conditions are set forth in 44 articles covering 9 printed pages. We quote the parts that seem pertinent.

Article 20, headed “Correction of Work after Final Payment/' provides.

“Neither the final certificate nor payment nor any provision in the contract documents shall relieve the contractor of responsibility for faulty materials or workmanship and, unless otherwise specified, he shall remedy any defects due thereto and pay for any damage to other work resulting therefrom, which shall appear within a period of one year from the date of substantial completion. The owner shall give notice of observed defects with reasonable promptness. All questions arising under this article shall be decided by the architect subject to arbitration.”

Article 25 provides for issuance by the architect of certificates for amounts due the contractor, and that

“No certificate issued nor payment made to the contractor, nor partial or entire use or occupancy of the work by the owner, shall be an acceptance of any work or materials not in accordance with this contract. The making and acceptance of the final payment shall constitute a waiver of all claims by the owner, other than those arising from unsettled liens, from faulty work appearing after final payment or from requirement of the specifications, and of all claims of the contractor, except those previously made and still unsettled.”

Article 31, headed “Damages,” provides:

“If either party to this Contract should suffer damage in any manner because of any wrongful act or neglect of the other party or of anyone employed by him, then he shall be reimbursed by the other party for such damage.
“Claims under this clause shall be made in writing to the party liable within a reasonable time of the first observance of such damage and not later than the time *47 of final payment, except as expressly stipulated otherwise in the case of faulty work or materials, and shall be adjusted by agreement or arbitration.”

Article 88, headed “Architect’s Status,” provides:

“The architect shall have general supervision and direction of the work. He is the agent of the owner only to the extent provided in the contract documents and when in special instances he is authorized by the owner so to act, and in such instances he shall, upon request, show the contractor written authority. * * * As the architect is, in the first instance, the interpreter of the conditions of the contract and the judge of its performance, he shall side neither with the owner nor with the contractor, but shall use his powers under the contract to enforce its faithful performance by both. In case of termination of the employment of the architect, the owner shall appoint a capable and reputable architect, whose status under the contract shall be that of the former architect.”

Article 39, headed “Architect’s Decisions,” provides:

“The architect shall, within a reasonable time, make decisions on all claims of the owner or contractor and on all other matters relating to the execution and progress of the work or the interpretation of the contract documents. The architect’s decisions, in matters relating to artistic effect, shall be final, if within the terms of the contract documents. Except as otherwise expressly provided in the contract documents, all the architect’s decisions are subject to arbitration.”

Article 40, headed “Arbitration,” contains the following provisions:

“All questions subject to arbitration under this Contract shall be submitted to arbitration at the choice of either party to the dispute. * * *
“The demand for arbitration shall be filed in writing with the Architect, in the case of an appeal from his decision, within ten days of its receipt and in any other case within a reasonable time after cause thereof and in no case later than the time of final payment, except *48 as otherwise expressly stipulated in the Contract. If the Architect fails to make a decision within a reasonable time, an appeal to arbitration may be taken as if his decision had been rendered against the party appealing. * * *
“Unless otherwise provided by controlling statutes, the parties may agree upon one arbitrator; otherwise there shall be three, one named in writing, by each party to this Contract, (sic) to the other party and to the Architect and the third chosen by these two arbitrators, or if they fail to select a third within fifteen days, then he shall be chosen by the presiding officer of the Bar Association nearest to the location of the work. Should the party demanding arbitartion fail to name an arbitrator within ten days of his demand, his right to arbitration shall lapse. Should the other party fail to choose an arbitrator within said ten days, then such presiding officer shall appoint such arbitrator.* * *
“If there be one arbitrator his decision shall be binding; if three the decision of any two shall be binding. Such decision shall be a condition precedent to any right of legal action, and wherever permitted by law it may be filed in Court to carry it into effect.”

The building was turned over to the district as completed in January, 1930; the architect’s final certificate was issued, and the final payment, except for a small amount deducted on account of a minor omission, was made in April, 1930.

The architect, Mr. Hitchcock, left Laramie about November 1, 1930, and while away was killed in an accident. After his death, and on December 4, 1930, the school district board, as shown by its minutes, instructed its clerk “to write to Mr. W. E. Ware, architect, Salt Lake City, accepting his offer to make an examination of the building, the Board to pay his expenses in coming here and return; and to write John W. Howard, contractor, to meet with the Board as soon as Mr. Ware had made a report.”

Mr. Ware thereafter came to Laramie “in response *49

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lucksinger v. Salisbury
262 P.2d 396 (Wyoming Supreme Court, 1953)
Hagie v. Lincoln Land Co.
18 F. Supp. 637 (D. Wyoming, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
52 P.2d 421, 49 Wyo. 41, 1935 Wyo. LEXIS 8, Counsel Stack Legal Research, https://law.counselstack.com/opinion/school-district-no-1-v-howard-wyo-1935.