City of St. Charles v. Stookey

154 F. 772, 85 C.C.A. 494, 1907 U.S. App. LEXIS 4583
Court of Appeals for the Eighth Circuit·Decided June 11, 1907·No. No. 2,508·Published·Cited by 27 cases

Opinion

SANBORN, Circuit Judge.

In this case the plaintiff below, Charles A. Stookey, recovered a judgment of $10,695.82, the unpaid balance of the agreed price of the construction of a system of waterworks, which consisted of three settling basins, boilers, pumps, power house, pipes, distribution mains and hydrants, for the city of St. Charles The contract price of the works was.about $84,000, and the city had paid the contractor about $75,000, and had taken possession of and was using the works. They had been built under written contracts and specifications, which provided that the contractor should make excavations as directed by the engineer; that the engineer should stake out all work; that the engineer might make alterations in line, grade, form, or dimensions of the work; that the engineer should in all cases, decide all questions which might arise relative to the installation of the plant by the contractor; that his estimates and decisions should be final and conclusive; that the contractor should be responsible for the entire work as a whole until its acceptance by the city; that the settling basins should be filled with water, and should stand until proved to be water tight to the .satisfaction of the engineer; that “all leaks, breaks, or defects caused by improper material or workmanship that develop within six months after the plant is accepted by city must be repaired or replaced by contractor; that the contractor shall do such extra work, in addition to his contract, as the engineer may direct in writing, subject to the'approval of the council”; that estimates should be made, and 80 per cent, thereof should be paid monthly as the work progressed; that “when contract is completed, and tested to the satisfaction of the engineer and all repairs made, 15 per cent, of the contract price will be paid the contractor”; and that the remaining 5 per cent, should be paid, one-half in three months and one-half in six months after the acceptance of the plant by the city, less the amount, if any, due the city for repairs to the plant.

Early in January, 1903, the plant had been constructed and tested to the satisfaction of the engineer, and on January 5, 1903, he made a final'estimate, subject to such exceptions as might be taken into account by the committee in charge, in which he certified the full amount of the bid for the three settling basins, to be earned and the 15 per cent, payable when the work was completed to his satisfaction and when all repairs were made, to be due. The committee made certain specifications of defects, which the contractor subsequently proceeded to remedy. They inspected and tested the works, and on January 15, 1903, pursuant to a recommendation of the committee, the city paid the contractor $12,000 on this estimate. On February 9, 1903, the city took and thereafter retained possession of the waterworks system. From time to time, as requested, the engineer stopped leaks in the [775] basins and made repairs, which he completed before May 20, 1903. About May 25, 1903, a portion of the east wall of two of the settling-basins tipped toward the east, and cracked the floor and the ends of two of the basins so that they would not hold water. The city subsequently repaired this break at a cost of $5,667.03, and the meritorious issue in this cáse is whether the contractor or the city should bear the expense of these repairs. There was evidence, on the one handi that this break was caused by improper material and workmanship furnished by the contractor, that the floors of the basins were not covered with the specified thickness of cement, so that the leakages through them undermined the east wall and produced the break. On the other hand, there was testimony that this break was caused by the direction of the engineer to locate the east wall so that a portion of it rested upon earth, sand, and silt, and by his direction not to remove this soft material and place the foundation of the wall upon the solid rock below so that the portion of the wall upon this silt and sand settled more than the remainder of the wall and of the basins which rested on solid rock, and that the crack in the basins was caused by this settling. The issue which this evidence presented was submitted to the jury under proper instructions, and they found that the misdirection of the engineer was the real cause of the break, and that it was not produced by the plaintiff’s improper workmanship or material. There was sufficient evidence to sustain this conclusion, and in the consideration of the case in this court that must be deemed to be the fact.

Free access — add to your briefcase to read the full text and ask questions with AI

City of St. Charles v. Stookey, 154 F. 772, 85 C.C.A. 494, 1907 U.S. App. LEXIS 4583 (8th Cir. 1907).

154 F. 772 (City of St. Charles v. Stookey) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Britt v. City of Sioux Falls
291 N.W.2d 784 (South Dakota Supreme Court, 1980)
Schimmelpfennig v. Gaedke
27 N.W.2d 416 (Supreme Court of Minnesota, 1947)
Cable v. United States
104 F.2d 541 (Seventh Circuit, 1939)
A. & R. Realty Co. v. Northwestern Mut. Life Ins.
95 F.2d 703 (Eighth Circuit, 1938)
United States v. French
95 F.2d 922 (Eighth Circuit, 1938)
Burke Grain Co. v. St. Paul-Mercury Indemnity Co.
94 F.2d 458 (Eighth Circuit, 1938)
School District No. 1 v. Howard
52 P.2d 421 (Wyoming Supreme Court, 1935)
Koch Sand & Gravel Co. v. Koss Construction Co.
266 N.W. 507 (Supreme Court of Iowa, 1935)
Inhabitants of Plainfield v. Palmer
72 F.2d 312 (Third Circuit, 1934)
City of Jackson Ex Rel. Cape County Savings Bank v. Houck
43 S.W.2d 908 (Missouri Court of Appeals, 1931)
Browne v. Franklin Fire Insurance
37 S.W.2d 977 (Missouri Court of Appeals, 1931)
Granette Products Co. v. Arthur H. Neumann & Co.
221 N.W. 197 (Supreme Court of Iowa, 1928)
Boyden v. United Mercury Mines Co.
267 P. 830 (Idaho Supreme Court, 1928)
Vanadium Corp. v. Willis
255 P. 985 (Supreme Court of Colorado, 1926)
In re A. W. Cowen & Bros.
11 F.2d 692 (Second Circuit, 1926)
Finley v. Pew
205 P. 310 (Wyoming Supreme Court, 1922)