Strom-Johnson Construction Co. v. Riverview Furniture Store

198 N.W. 714, 227 Mich. 55, 1924 Mich. LEXIS 603
CourtMichigan Supreme Court
DecidedMay 8, 1924
DocketDocket No. 43.
StatusPublished
Cited by19 cases

This text of 198 N.W. 714 (Strom-Johnson Construction Co. v. Riverview Furniture Store) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Strom-Johnson Construction Co. v. Riverview Furniture Store, 198 N.W. 714, 227 Mich. 55, 1924 Mich. LEXIS 603 (Mich. 1924).

Opinion

Steere, J.

Both parties to this litigation are corporations organized and doing business under the laws of this State. Plaintiff’s business is chiefly construction of large buildings such as stores, school houses, factories, etc. Defendant owned and operated a furniture store in the city of Grand Rapids. On April 27, 1921, plaintiff entered into a contract with defendant to remodel and add a story to> its store building, located on west Bridge street, in said city. Defendant employed an architect and an elaborate building contract with plans and specifications, made a part thereof, was prepared and signed by the parties.' The time specified for performance of the contract was until August 1, 1921. The consideration named in the contract was $27,933. Various extras were added during the progress of the work amounting to $5,006.75, which made a total indebtedness for full performance with extras added $32,939.75. Payments were made by defendant on architect’s certificates before completion of the work to the amount *57 of $28,560.31, leaving a balance of $4,379.44. Defendant was authorized to withhold 15 per cent, until completion of the contract for its protection and declined to make this final payment, claiming damages on various grounds, and particularly for delay in completing the contract. Plaintiff then filed a builder’s lien followed by this bill to foreclose the lien and enforce payment. The contract contained' a clause providing as liquidated damages $25 for each day the contractor extended the work beyond the time prescribed for completing the contract. Defendant claims credit for that amount per day from August 1st to November 17, 1921, less one week’s extension of time for completion granted by the architect, or for 101 days at $25 per day, amounting to $2,525.

Plaintiff’s claim is in effect estoppel by waiver; that the delay was caused through the fault of defendant in requiring a large amount of extra work, in not clearing the rear of the premises as agreed in time for plaintiff to commence performance on May 1, 1921, delay in providing promised water service until May 24th, failure to have the work of auxiliary contractors, hired and controlled by defendant to install wiring, plumbing, elevator, etc., performed in time and manner as agreed and required for the work to proceed without delay.

During the entire time this contract was being performed defendant occupied and daily ran its store, in which it regularly conducted its retail furniture business, as soon as available using the additions and conveniences plaintiff had constructed. The contract was substantially completed on September 17, 1921, with the defendant in occupation and use of its additions when it held an advertised grand opening. But some work was done by plaintiff in completion of its undertaking according to certificate of the architect in charge as late as November 17th. Thirty *58 days thereafter he gave defendant the following certificate, and sent plaintiff a copy:

“Dec. 17, 1921.
“Riverview Furniture Store,
“City.
“Gentlemen: This is to certify that the StrornJohnson Construction Co. having satisfactorily completed the work under their contracts for the erection of the addition to your building on West Bridge street, thirty days ago, are, by the terms of the agreement, entitled to the final payment of four thousand three hundred and seventy-nine and 44/100 dollars ($4,379.44) which was retained as permitted by the agreement for thirty days- subsequent to such completion. See statement of November 17th for this amount.
“Yours very truly,
“Robinson & Campau, Architects,
“By Fred S. Robinson.”

It was the opinion of the trial court that plaintiff’s failure to complete the contract within the specified time was the fault of defendant and a decree was granted plaintiff for the balance of $4,379.44, with lien declared and foreclosure ordered as in such cases provided.

For the contract signed by the parties the standard form of the American Institute of Architects appears to have been used, with its numerous headings and “articles.” Under the heading “General Conditions of the Contract” are some 45 articles deáling with a variety of contingencies and elements of the contract such as “Principle and Definitions,” the “Architect’s Status,” “Architect’s Decisions,” “Materials, Appliances and Employees,” “Deductions for Uncorrected Work,” “Changes in the Work,” “Claims for Extras,” “Certificates and Payments,” “Delays,” “Separate Contracts,” etc. Sub-paragraph “f” of article 1 provides: “All time limits stated in the contract documents are of the essence of the contract.” Under article 9, dealing with the “Architect’s Status,” he is said to *59 have general supervision and direction of the work as agent of the owner to the extent provided in the contract documents, with “authority to stop the work whenever it may be necessary to insure the proper execution of the contract,” and by article 10 he is authorized to make decisions within reasonable time “on all claims of the owner or contractor and on all other matters relating to the execution and progress of the work or the interpretation of the contract documents,” all his decisions being made, however, subject to arbitration.

The Riverview Furniture Store was organized by Valentine J. Banaszak, who for a time personally owned and ran a furniture store where the building in question is located and then incorporated the business, becoming its president and manager. He was defendant’s principal witness, and was at the building representing it while the contract was being performed under supervision of defendant’s architect, with whom he states he mostly talked about matters relating to the improvements in progress and “let the architect handle it,” and “generally transacted the deal” through him, communicating with plaintiff mostly through that channel. At the time this work was done a clothing department had been added to defendant’s merchandising business. He testified that the entire building had a frontage of 82 feet, the portion occupied by the clothing department being 65 feet deep and the other part 118 feet deep.

The contract itself required plaintiff to furnish the material and perform the work shown on the drawings and described in the specifications, which were entitled:

“Specifications for general contract for additions and alterations to the plant of Riverview Furniture Co., 279-281 Bridge St., N. W., Grand Rapids, Mich., modified by addenda issued under dates of April 24 and 25, 1921, copies of which are attached hereto,” etc.

*60 Counsel evidently agreed that it was unnecessary to embody the voluminous specifications and drawings in the record in full, and it only contains certain “excerpts from the specifications for general contract for additions and alterations” said to relate to the issues involved. From them it appears that the contract did not include “the.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Best Team Ever Inc v. Conlan Abu
Michigan Court of Appeals, 2025
Posen Construction Inc v. City of Dearborn
Michigan Court of Appeals, 2015
Innovative Case, Inc. v. Tweddle Litho Co.
147 F. App'x 467 (Sixth Circuit, 2005)
Devalk Lincoln Mercury, Inc. v. Ford Motor Company
811 F.2d 326 (Seventh Circuit, 1987)
DeValk Lincoln Mercury, Inc. v. Ford Motor Co.
811 F.2d 326 (Seventh Circuit, 1987)
Grand Rapids Asphalt Paving Co. v. City of Wyoming
185 N.W.2d 591 (Michigan Court of Appeals, 1971)
Motor State Insurance v. Leonard
183 N.W.2d 309 (Michigan Court of Appeals, 1970)
Fitzgerald v. Hubert Herman, Inc.
179 N.W.2d 252 (Michigan Court of Appeals, 1970)
Bissell v. L. W. Edison Co.
156 N.W.2d 623 (Michigan Court of Appeals, 1967)
Carlini v. United States Rubber Co.
154 N.W.2d 595 (Michigan Court of Appeals, 1967)
Bielski v. Wolverine Insurance
140 N.W.2d 772 (Michigan Court of Appeals, 1966)
W. J. Howard & Sons, Inc. v. Meyer
116 N.W.2d 752 (Michigan Supreme Court, 1962)
School District No. 1 v. Howard
52 P.2d 421 (Wyoming Supreme Court, 1935)
Morley Bros. v. F. R. Patterson Construction Co.
253 N.W. 213 (Michigan Supreme Court, 1934)
Lather v. School District No. 1
219 N.W. 700 (Michigan Supreme Court, 1928)
Wingilia v. Ashman
217 N.W. 909 (Michigan Supreme Court, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
198 N.W. 714, 227 Mich. 55, 1924 Mich. LEXIS 603, Counsel Stack Legal Research, https://law.counselstack.com/opinion/strom-johnson-construction-co-v-riverview-furniture-store-mich-1924.