W. J. Howard & Sons, Inc. v. Meyer

116 N.W.2d 752, 367 Mich. 300, 1962 Mich. LEXIS 415
CourtMichigan Supreme Court
DecidedSeptember 7, 1962
DocketDocket 5, Calendar 49,183
StatusPublished
Cited by8 cases

This text of 116 N.W.2d 752 (W. J. Howard & Sons, Inc. v. Meyer) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. J. Howard & Sons, Inc. v. Meyer, 116 N.W.2d 752, 367 Mich. 300, 1962 Mich. LEXIS 415 (Mich. 1962).

Opinion

*302 Carr, C. J.

Defendant in this case, being- the owner of a farmhouse in Novi township, Oakland county, Michigan, desired to remodel it. To that end he employed an architect, Norman Simmons, to prepare plans therefor. Because of the nature of the project, and the unknown factors that might develop in the course of the operation, no specifications were prepared. In accordance with the advice of the architect, plaintiff corporation was selected as the contractor. Plaintiff had previously done work for Simmons and also for a company owned by defendant. In the absence of specifications it was determined that the work should be done on a cost basis.

A written contract was prepared on a standard form of agreement issued by the American Institute of Architects for use when a stipulated sum forms the basis of payment. The record indicates that plaintiff filled out the form by typing in certain provisions in accordance with the agreement reached by the parties. The following provisions of the instrument as signed by plaintiff and defendant are material in the instant controversy:

“Article 3. The contract sum—The owner shall pay the contractor for the performance of the contract, subject to additions and deductions provided therein, in current funds as follows: Labor and material costs, including supervision, plus 15 % overhead and profit. Monthly requests for payment will included recapitulation of labor costs and duplicate material invoices. All payments subject to approval of Mr. Norman Simmons.
“NOTE: Owner and designer to be furnished schedule of prevailing labor rates. * * *
“Article 4. Progress payments—The owner shall make payments on account of the contracts as provided therein, as follows:
“On or about the 5th day of each month 100% of the value, based on the contract prices of labor and materials incorporated in the work and of materials *303 suitably stored at the site thereof up to the 30th day of that month, as estimated by the architect, less the aggregate of previous payments; and upon substantial completion of the entire work, a sum sufficient to increase the total payments to .... percent of the contract price..........
“Article 5. Acceptance and final payment—Final payment shall be due 15 days after substantial completion of the work provided the work be then fully completed and the contract fully performed.
“Upon receipt of written notice that the work is ready for final inspection and acceptance, the architect shall promptly make such inspection, and when he finds the work acceptable under the contract and the contract fully performed he shall promptly issue a final certificate, over his own signature, stating that the work provided for in this contract has been completed and is accepted by him under the terms and conditions thereof, and that the entire balance found to be due the contractor, and noted in said final certificate, is due and payable.
“Before issuance of final certificate the contractor shall submit evidence satisfactory to the architect that all payrolls, material bills, and other indebtedness connected with the work have been paid.
“If after the work has been substantially completed, full completion thereof is materially delayed through no fault of the contractor, and the architect so certifies, the owner shall, upon certificate of the architect, and without terminating the contract, make payment of the balance due for that portion of the work fully completed and accepted. Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute a waiver of claims.”

In accordance with its usual method of procedure plaintiff engaged subcontractors for certain portions of the work and paid them on the bases of statements rendered thereby. Statements covering charges made by plaintiff against defendant were *304 submitted from time to time to Architect Simmons. The first 6 requests for payment were approved by Simmons, the first 5 being paid in full by defendant, and the sixth request paid in part. The record indicates that the reason for such partial payment was due to a cash shortage at the time on the part of defendant. Three subsequent statements were-submitted but because the aggregate cost of the project exceeded the estimated expense of remodeling,, approval was delayed, but, after certain adjustments, Simmons ultimately certified to their Correctness-Defendant, however, declined to make payment, and the instant suit has resulted from such refusal.

It is not disputed that the statements as prepared and served by plaintiff from time to time indicated specifically the expenditures that it had made and for which it sought payment from defendant. It is not claimed on behalf of defendant that he, or his architect, was in any way misled with reference to-plaintiff’s claim that it was entitled to be reimbursed and to receive payment of compensation for the-various items set forth in each statement rendered. In other words, there is no claim of concealment on-plaintiff’s part, and apparently the controversy resulting in the litigation was due to the cost of the-project over and above the estimated expense thereof. As before noted, no specifications were prepared and the basis for arriving at the estimated cost does not appear in the record.

Plaintiff in its declaration asserted the right to' recover pursuant to the contract on the basis of the-requests for payment, or invoices, periodically served on the architect and on defendant, on which the-latter refused payment. As noted, Simmons ultimately approved the last 3 statements, and he testified in substance that the hesitancy in giving his-approval was due to the overall costs of the project-He further testified that he had no specific objec *305 tions to any of the items listed in plaintiff’s invoices other than on 1 or 2 minor matters which were adjusted to his satisfaction. Defendant by answer to the declaration denied that the statements rendered from time to time by plaintiff were correct or in accordance with the contract as drawn, and alleged that overpayments in the aggregate sum of $11,018.69 had been made, the allowance of which sum in his favor he asserted in a plea of set-off and recoupment. Plaintiff claimed the right to recover the total amount of $7,830.40.

The case was tried before the circuit judge without a jury. After listening to the proofs and the arguments of counsel the judge came to the conclusion that under the contract as written there was “some area of ambiguity as to the items to he included in costs.” He further concluded that by their conduct the parties had given a practical interpretation to the language of the agreement as prepared in the manner above indicated, that Architect Simmons was granted authority by defendant to pass on the propriety of the statements submitted by plaintiff, that Simmons acted on behalf of defendant throughout the entire transaction, and that his acts in approving the statements for payment were binding on defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dumas v. Auto Club Ins. Ass'n
473 N.W.2d 652 (Michigan Supreme Court, 1991)
Vowels v. Arthur Murray Studios of Michigan, Inc.
163 N.W.2d 35 (Michigan Court of Appeals, 1978)
Turner v. Bituminous Casualty Co.
244 N.W.2d 873 (Michigan Supreme Court, 1976)
Gaydos v. White Motor Corp.
220 N.W.2d 697 (Michigan Court of Appeals, 1974)
Sam Levitz Furniture Co. v. Safeway Stores, Inc.
464 P.2d 612 (Arizona Supreme Court, 1970)
Redinger v. Standard Oil Company
148 N.W.2d 225 (Michigan Court of Appeals, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
116 N.W.2d 752, 367 Mich. 300, 1962 Mich. LEXIS 415, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-j-howard-sons-inc-v-meyer-mich-1962.