Wildey v. Fractional School District Number One

25 Mich. 419, 1872 Mich. LEXIS 123
CourtMichigan Supreme Court
DecidedOctober 8, 1872
StatusPublished
Cited by28 cases

This text of 25 Mich. 419 (Wildey v. Fractional School District Number One) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wildey v. Fractional School District Number One, 25 Mich. 419, 1872 Mich. LEXIS 123 (Mich. 1872).

Opinion

Coolet, J,

This action is brought to recover for tbe construction, of a school building for the defendant. Tbe declaration-contained a special count on the contract, in which it was. averred that the building was completed “in substantial conformity with all the terms and conditions of the said [421]*421contract,” and was “'received and accepted by the said defendant as, and for, a compliance, on the part of the said plaintiff, with all the terms and conditions of the said contract, on the part of the said plaintiff to be observed and performed.” It also contained the common counts. The defendant pleaded the general issue, with notice of a claim to recoup damages for non-performance by the plaintiff.

On the trial, the contract was put in evidence, and it appears thereby that the building was to be “completely finished and so delivered up to the [district], clean, and in good order for use, by the fifteenth day of July, A. D. 1870.” All the work was to be “ executed in the best and most workman-like manner, and agreeably to such directions as may be given from time to time by G-. P. Eandall, architect, or his assistant (who is employed by the [district] to superintend these works), and to his full and entire satisfaction, without referencé thereon to any other person.” The admission or allowance of any claim for alterations, or extras, was to be judged of, determined, and adjusted “solely by the superintendent above named,” and the district was to pay, on the certificate of the architect, or superintendent, for the full and entire completion of the building, according to the plans and specifications, twenty-eight thousand seven hundred dollars, as follows: eighty-five per cent, from time to time, in monthly _ estimates, and the balance when the building should be fully completed.

The plaintiff testified that he constructed the building, and supposed it was entirely finished in August, 1870; the district appointed an overseer to investigate the work as it progressed; at first one Godfrey acted in that capacity; afterwards Joseph Davy, who was there constantly until the building was .erected and enclosed; payments were received from time to time from the district, but no certificate was [422]*422ever given to draw it upon; the district began using the building in September, 1870, and it has been in use for a union school ever since; Mr. Davy found fault with the roof when it Avas mostly on, and the district served on plaintiff a notice that they did not accept the slating of the roof, because not in compliance, with the contract. This notice bears date in December, 1869. The complaint was that the slates, were too large, and of inferior quality. Plaintiff could not find smaller slate in market. AfterAvards another notice was served, of which the following is a copy:

“January 2, 1871.

“A. R. Wildey, Esq.:

“Sir: — The architect of our school building, Gf. P. Randall, of Chicago, Illinois, Avas here on the 28th of December, 1870, and made as thorough an inspection of the work as circumstances Avould alloAv, and has submitted his report, a copy of which is hereivith enclosed. We, therefore, in accordance with his recommendation therein contained, and as provided in the contract, request you to go on and reconstruct, repair, and make such changes and additions to the work as can be done without injury to the building, and as indicated in his report, and, so far as practicable, put the work in such condition as the specifications and plans clearly indicate. Such work as can be done at once, is to be so done, and such as cannot be properly done in cold weather, to be done immediately after the weather shall have become sufficiently favorable for doing such work, and all under the direction of the school board, or such sub-superintendent as may be placed in charge of the work, in accordance with the terms of the contract for this work. Should you neglect or refuse to proceed Avith the work to completion, at or after the expiration of the time indicated in the contract, three days from the serving of this notice, [423]*423the school board will consider themselves at liberty to employ such help as may be necessary, and finish and complete the work themselves, and deduct the expense from the price and amount you were to receive on the full completion of such work.

“(Signed,) “J. Andrews, Director.”

The whole amount paid towards, the building by the district was twenty-four thousand dollars.

The plaintiff then called as a witness, a builder of large experience, who testified that he examined the building with the plans and specifications before him, and compared the ■ work with the specifications. The plaintiff then offered to prove by the witness the value of the work, item by item, and also that it corresponded with the specifications. This offer was objected to, and overruled, because it did not include the production of the certificate of the architect, which the court held to be the best evidence of the completion of the contract, and a condition precedent to the right to recover.

The plaintiff also offered to show extra work, and materials, 'done and furnished, on the request of the authorized officers of the district, to the value of one thousand dollars; which was objected to, and rejected, on the same ground above stated. .

Also, that Randall, the architect, resided in Chicago, and was not present when the building was completed, nor until three months after-the district took possession of the building; which was objected to, and excluded, as constituting no sufficient excuse for the failure to procure the architect’s certificate.

Also, in addition to, and connection with, the facts previously stated, that the defendant took possession of the building in September, 1870, and, under the direction of the school board, exercises were held, which were called by [424]*424them a dedication of the building, wheu, by invitation of the board, public addresses were made, congratulating the people of the district, who were present in large numbers, on the completion of the building, etc.; which was also objected to, and excluded.

And the circuit judge charged the jury, that, for the purposes of this trial, and in order that the question might be passed upon by the supreme court, he had ruled in substance that, to entitle the plaintiff to recover, he must either show the certificate of Mr. Randall, the architect, or give some reasonable excuse for its non-production; and, no evidence of that kind having been offered, they must render a verdict in favor of the defendant.

We think these rulings of the circuit judge do not correctly interpret the contract. The architect was not made the sole inspector or judge of the work as it progressed, but, on the contrary, as he resided at a considerable distance, and a superintendent was expected to be, and was, in fact, chosen by the district, it is a reasonable inference, that the superintendent was expected to supervise the work as it proceeded, and to express his dissent with any portion not in compliance with the specifications. His powers were made, by the contract, as broad as those of the architect, and there is no consent in the contract that his decision should be subject to reversal or review by his nominal superior.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A-G-E Corp. v. State Ex Rel. State Department of Transportation
2006 SD 66 (South Dakota Supreme Court, 2006)
W. J. Howard & Sons, Inc. v. Meyer
116 N.W.2d 752 (Michigan Supreme Court, 1962)
Antonoff v. Basso
78 N.W.2d 604 (Michigan Supreme Court, 1956)
In Re the Estate of Bishop
37 Haw. 111 (Hawaii Supreme Court, 1945)
Strom-Johnson Construction Co. v. Riverview Furniture Store
198 N.W. 714 (Michigan Supreme Court, 1924)
Oakley v. Duluth Superior Dredging Co.
194 N.W. 123 (Michigan Supreme Court, 1923)
Stewart v. Breckenridge
169 P. 543 (Supreme Court of Colorado, 1917)
Township of Rockland v. Oxnam
164 N.W. 494 (Michigan Supreme Court, 1917)
Leonard v. Home Builders
161 P. 1151 (California Supreme Court, 1916)
Pippy v. Winslow
125 P. 298 (Oregon Supreme Court, 1912)
City St. Improvement Co. v. City of Marysville
101 P. 308 (California Supreme Court, 1909)
Young v. Stein
116 N.W. 195 (Michigan Supreme Court, 1908)
Mosaic Tile Co. v. Chiera
95 N.W. 537 (Michigan Supreme Court, 1903)
Vanderhoof v. Shell
72 P. 166 (Oregon Supreme Court, 1903)
Kangas v. Boulton
86 N.W. 1043 (Michigan Supreme Court, 1901)
Johnson v. Henry
86 N.W. 1027 (Michigan Supreme Court, 1901)
Morgan v. Nowlin
85 N.W. 468 (Michigan Supreme Court, 1901)
Sheldon v. Leahy
69 N.W. 76 (Michigan Supreme Court, 1896)
Hanley v. Walker
8 L.R.A. 207 (Michigan Supreme Court, 1890)

Cite This Page — Counsel Stack

Bluebook (online)
25 Mich. 419, 1872 Mich. LEXIS 123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wildey-v-fractional-school-district-number-one-mich-1872.