Township of Rockland v. Oxnam

164 N.W. 494, 198 Mich. 373, 1917 Mich. LEXIS 893
CourtMichigan Supreme Court
DecidedSeptember 27, 1917
DocketDocket No. 29
StatusPublished

This text of 164 N.W. 494 (Township of Rockland v. Oxnam) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Township of Rockland v. Oxnam, 164 N.W. 494, 198 Mich. 373, 1917 Mich. LEXIS 893 (Mich. 1917).

Opinion

Stone, J.

This is an action of assumpsit to recover damages for the nonperformance of a contract between the plaintiff and the defendants Oxnam and Adair, by which the latter agreed to build a macadam road for the plaintiff. The declaration contained a special count on the contract, and also the common counts. The plea of the defendants Oxnam and Adair was the general issue, with notice that the engineer, Bacco, when he took charge of the work in the spring of 1914, was, fraudulently actuated by a desire not to build the road in accordance with the plans and specifications, but by finding fault with the work of the first engineer, Therrien, and at the expense of said defendants, to build an entirely different and more expensive road; that in making his demands, and in requiring the rebuilding of certain portions of said road, which had been accepted by said former engineer as from 93 per cent, to 97 per cent, completed, he was not acting in good faith; that his conduct constituted a continuing breach of said contract up to the day the work was taken over by said plaintiff; that any delay there may have been was attributable solely to the capricious, wanton and fraudulent demands of said Bacco; and that in issuing his certificate that the work was being unnecessarily delayed he acted in bad faith. There [375]*375was also a notice of set-off. At the trial a verdict was directed in favor of the defendant the Title Guaranty & Surety Company. A reversal is here sought of the judgment in favor of the defendants Oxnam and Adair, but no reversal is sought as to the defendant the Title Guaranty & Surety Company.

It appeared that on July 30, 1913, the plaintiff entered into a written contract with the defendants Oxnam and Adair, whereby the latter agreed to build a macadam road, in conformity with certain specifications attached to said contract, and made a part thereof, for the consideration of $20,592. The specifications called for 5 miles of macadam road between certain designated places — the width of the road to be 20 feet; the macadam to be 9 feet wide, and to be 6 inches thick when rolled. Plans, profiles, and cross-sections were made a part of the specifications. All clearing, grubbing, excavations, etc., were to be done by the contractors, who were also to do all leveling, grading, surfacing, etc., and to lay the stone, furnish the materials, and all machinery and implements except roller and grader, to furnish all labor, and to put the road in complete order for use, and leave the ground in a neat condition. The work was to be done under the supervision of an engineer to be hired by the township board. Variations of location, profile, size, and dimensions might be made, as required by the exigencies of construction, pursuant to determination of the engineer. The macadam was to be formed of three courses of stone; the lower or first course being coarse stone, the second course to be of finer stone, and the third course being of finely broken stone, which was intended to bind or cement the other courses together, and to act as a dressing for the road. The engineer had authority to stop any portion of the work, if in his judgment the weather was such as to prevent the same being properly done. The decision of the engineer, on [376]*376matters in difference between the contractors and the township board, was to be final and conclusive, and the work was to be done according to his directions. Paragraph 43 of the specifications provided that:

“Monthly payments will be made by the township board to the contractor for the work performed upon presentation by him of the proper certificate of the engineer in a sum not to exceed eighty (80%) per cent, of the amount then due; the remainder of the twenty (20%) per cent, will be paid upon acceptance of work by the township board.”

The engineer could order the discharge of incompetent workmen, was authorized to give directions and make determination necessary to give due and full effect to the specifications, and all material and workmanship were subject, at all times, to his inspection, and was required to be repaired or replaced when ordered by him. According to the contract the work was to be completed by December 1,1913. It was provided, however, in the specifications, that extension of time might be allowed, if the work was stopped by the engineer, because of weather conditions. By paragraph 37 of the specifications it was provided:

“If at any time the work under contract should be abandoned, or if at any time the engineer should judge, and so certify in writing, that said work or any part thereof, is unnecessarily delayed, or that the contractor is executing the same in bad faith, then and in that case the township board shall notify the contractor to discontinue all work under this contract. They may employ other parties to complete the work in such manner as they may decide, and charge the expense of said labor and material to the contractor, which expense shall be deducted from the moneys due him under this contract. In case these expenses shall exceed the sum which would have been payable under contract, if the same had been completed by said contractor, his bondsmen shall pay the amount of excess to the township board.”

[377]*377Work was begun on this road in the summer of 1913, and continued until October 21, 1913, at which time the engineer, Therrien, ordered the work stopped for that year, because of weather conditions, and pursuant to the contract the township board was notified to that effect, whereupon the board extended the time for the completion of the contract until July 15, 1914. On October 22,1913, said engineer gave the fifth estimate, in which he stated certain portions of the road were 93 to 97 per cent, complete, and pursuant to which said defendants received their last payment in the year 1913. Work was resumed by said contractors in May, 1914, under a new engineer — one Bacco. He required considerable work to be done on those portions of the road which were estimated as from 93 to 97 per cent, completed in the last estimate given in 1913. It was his claim and that of the township board that this work was necessary to bring the road up to a proper cross-section, and that the road was badly rutted, and that the condition had been brought about through traffic over the road during the fall of 1913 and the spring of 1914, and also to some extent by the hauling of rock over this partially completed portion of the road by the contractors.

It was the claim of the contractors on the trial, and there was testimony to that effect, that the work done from section 129 to section 264, practically three miles, had been constructed under the direction and supervision of thé first engineer, and had been certified by him as being from 93 per cent, to 97 per cent, completed, and that when the second engineer came on the job in the spring of 1914 he required that this work be torn up and done over. Upon this subject defendant Adair testified:

“Q. What did he require you to do to that portion? What did he say and direct you to do to that portion ?
“A. To put the roller on and rebuild the road. We [378]*378had 112 days’ rolling on that the year before. We had one roller running night and day until we got 1Í2 days. We had it rounded up nicely so that we got 93 per cent, and 95 per cent, and 97 per cent, on all those sections. He just took a big roller, and put in the spikes, and ground it up, and knocked out 112 days’ rolling.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hebert v. Dewey
77 N.E. 822 (Massachusetts Supreme Judicial Court, 1906)
Wildey v. Fractional School District Number One
25 Mich. 419 (Michigan Supreme Court, 1872)
Lamson v. City of Marshall
95 N.W. 78 (Michigan Supreme Court, 1903)
Plumb v. Hecla Co.
122 N.W. 208 (Michigan Supreme Court, 1909)
Stuart v. Holt
131 N.W. 1100 (Michigan Supreme Court, 1911)
Ashland Lime, Salt & Cement Co. v. Shores
81 N.W. 136 (Wisconsin Supreme Court, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
164 N.W. 494, 198 Mich. 373, 1917 Mich. LEXIS 893, Counsel Stack Legal Research, https://law.counselstack.com/opinion/township-of-rockland-v-oxnam-mich-1917.