Posen Construction Inc v. City of Dearborn

CourtMichigan Court of Appeals
DecidedJanuary 27, 2015
Docket311214
StatusUnpublished

This text of Posen Construction Inc v. City of Dearborn (Posen Construction Inc v. City of Dearborn) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Posen Construction Inc v. City of Dearborn, (Mich. Ct. App. 2015).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

POSEN CONSTRUCTION, INC., UNPUBLISHED January 27, 2015 Plaintiff,

v No. 311214 Wayne Circuit Court CITY OF DEARBORN, LC No. 09-003465-CK

Defendant/Third-Party Plaintiff- Appellee,

and

NEYER, TISEO & HINDO, LTD., d/b/a NTH CONSULTANTS, LTD.,

Third-Party Defendant-Appellant.

Before: BECKERING, P.J., and JANSEN and BOONSTRA, JJ.

PER CURIAM.

Third-party defendant, Neyer, Tiseo & Hindo, Ltd., d/b/a NTH Consultants, Ltd. (“NTH”), appeals the trial court’s order partially granting summary disposition in favor of third- party plaintiff, City of Dearborn (the City), and denying NTH’s cross-motion for summary disposition with respect to the City’s breach of contract claim against NTH.1 We affirm the trial court’s summary disposition ruling, but modify in order to clarify the scope of NTH’s duties to defend and indemnify the City.

I. PROCEDURAL AND FACTUAL BACKGROUND

This case involves a dispute between the City and NTH regarding NTH’s contractual duties to defend and indemnify the City as set forth in certain agreements between the parties. In

1 This Court originally denied NTH’s application for leave to appeal. In lieu of granting leave to appeal, our Supreme Court remanded the case to this Court for consideration as on leave granted. Posen Const, Inc v City of Dearborn, 495 Mich 983; 843 NW2d 924 (2014).

-1- December 1998, the City sought to redesign its water and sewer systems in order to meet new water quality standards. To facilitate this substantial undertaking, the City issued a revised Request for Proposal (RFP) for consulting engineering firms to provide engineering services for the City’s Combined Sewer Overflow Control Program (hereafter “CSO Project”), which involved limiting the amount of CSO into the Rouge River. Paragraph 23 of the RFP provided, in pertinent part:

When the consultant is successfully selected by the reviewing panel and a mutually satisfactory contract is negotiated, the contract will be submitted to the Mayor and Dearborn City Council for approval. Until the Contract is properly executed by the proposer and the Mayor and a fully executed contract is received by the proposer, the City of Dearborn will have no obligation to proposer.

Paragraph 27 of the RFP required an agreement by the proposer that, “if selected, it will immediately enter into good faith negotiations with the City of Dearborn and faithfully attempt to reach agreement within twenty-one (21) calendar days of the date of the City of Dearborn’s notice of determination.”

The parties’ dispute originates from a “save harmless” provision contained in the RFP. Paragraph 24 of the RFP provides that “[t]he Contractor shall save harmless, defend and indemnify the City against all claims or damages arising as result of its operation under this contract.” This provision, along with an indemnity provision contained in a subsequently- negotiated engineering services agreement (“ESA”) (discussed below), forms the basis of the parties’ dispute in the instant matter.

It is undisputed that NTH was the successful bidder for the CSO project, and that the City and NTH entered into an ESA, dated April 30, 1999, pursuant to which NTH was to provide preliminary analysis and design services. The basic services NTH was to perform under this contract were set forth in Article 1.1 of the ESA, which described specific tasks for NTH to perform, but also expressly incorporated the RFP and other documents, including an exhibit to the ESA. Article 14 provides that the ESA “along with the Request for Proposal published by the OWNER on December 3, 1998, Bulletin No. 1, transmitted by fax on December 23, 1998 and ENGINEER’S response to the Request for Proposal dated January 13, 1999 constitutes the entire agreement as to the PROJECT between the parties.”

Pertinent to this appeal, Article 8 of the ESA sets forth duties for NTH to defend and indemnify the City under specified conditions:

The ENGINEER agrees to be responsible for any loss or damage to property or injury, damage or death to persons due to the negligent performance of the service under this Contract, and further agrees to protect and defend the OWNER against all claims or demands of every kind involving negligent performance by the ENGINEER and to hold the OWNER harmless from any loss or damage resulting from any negligent acts, errors, or omissions in the performance of the services under this Contract. Such responsibility shall not be construed as a liability for damage caused by or resulting from the negligence of the owner, its agents other than the ENGINEER, or its employees.

-2- NTH and the City executed several addendums to the ESA before this action was filed, including an addendum executed in 2004 that required NTH to provide construction management services and quality control and engineering support for a portion of the CSO Project referred to as “Contract 6.” The City awarded Posen Construction, Inc. (“Posen”) a contract for Contract 6. Article 4 of the contract entitled the City to liquidated damages of $2,500 for each day in which Posen failed to timely complete work in accordance with the terms of the contract. It also allowed the City to retain any liquidated damages from amounts due to Posen under the contract. The general conditions for Posen’s contract with the City provided in Article 9, ¶ 9.08(A), that “Engineer will be the initial interpreter of the requirements of the Contract Documents and judge of the acceptability of the Work thereunder.” Article 10, which addressed work changes and claims, required the engineer to review claims. Under ¶ 10.05(E), the engineer’s decision was final and binding, unless the owner or contractor invoked dispute resolution procedures. But in 2006, Posen and the City amended this general provision to allow the City to conduct a review if Posen wished to pursue a claim that was denied. The amendment also authorized Posen to file a lawsuit to prosecute a claim in an appropriate court if the claim was not resolved.

In February 2009, Posen filed this action against the City for breach of contract, seeking damages for delays and extra work, including corrective work allegedly caused by defective designs, plans, and specifications related to Contract 6. Alternatively, Posen sought compensation for extra work based on a quantum meruit theory of relief. In April 2009, the City filed a third-party complaint against NTH, seeking damages for breach of contract and professional negligence. The City alleged, in pertinent part, that NTH violated Article 8 of the ESA by refusing to defend it against Posen’s allegations that arose out of NTH’s negligent performance. The City also sought indemnification for any damages established by Posen that resulted from NTH’s negligence.

In July 2010, the trial court ordered the parties to participate in facilitative mediation and exchange expert reports for purposes of that mediation. Posen obtained an evaluation of its claims for purposes of mediation from FTI Consulting, Inc, which concluded that Posen was entitled to compensation in the amount of $8,006,455 for costs incurred because of changes, delays, and disruptions due to differing site conditions, contract changes, and/or deficiencies in specifications.

In November 2010, the City informed NTH that it would present a potential settlement to the city council for approval on November 9, 2010. The letter specified that NTH had until November 9, 2010 to comply with its contractual obligations. In an e-mail response dated November 8, 2010, NTH’s counsel claimed that NTH had no duty to the City based on the allegations in Posen’s complaint.

Following mediation, Posen settled with the City and the trial court entered a stipulated order dismissing Posen’s complaint in December 2010.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Winbush
407 F.3d 703 (Fifth Circuit, 2005)
DeFRAIN v. STATE FARM MUTUAL AUTOMOBILE INSURANCE COMPANY
817 N.W.2d 504 (Michigan Supreme Court, 2012)
Loweke v. Ann Arbor Ceiling & Partition Co, LLC
809 N.W.2d 553 (Michigan Supreme Court, 2011)
Shay v. Aldrich
790 N.W.2d 629 (Michigan Supreme Court, 2010)
Sweebe v. Sweebe
712 N.W.2d 708 (Michigan Supreme Court, 2006)
People v. Johnson
712 N.W.2d 703 (Michigan Supreme Court, 2006)
Klapp v. United Insurance Group Agency, Inc
663 N.W.2d 447 (Michigan Supreme Court, 2003)
Chandler v. Muskegon County
652 N.W.2d 224 (Michigan Supreme Court, 2002)
Gibson v. Group Insurance
369 N.W.2d 484 (Michigan Court of Appeals, 1985)
McIntosh v. McIntosh
768 N.W.2d 325 (Michigan Court of Appeals, 2009)
Dean v. Tucker
517 N.W.2d 835 (Michigan Court of Appeals, 1994)
Law Offices of Lawrence J Stockler, PC v. Rose
436 N.W.2d 70 (Michigan Court of Appeals, 1989)
Maiden v. Rozwood
597 N.W.2d 817 (Michigan Supreme Court, 1999)
State v. Erickson
534 N.W.2d 804 (North Dakota Supreme Court, 1995)
Helms v. Lemieux
780 N.W.2d 878 (Michigan Court of Appeals, 2009)
Forge v. Smith
580 N.W.2d 876 (Michigan Supreme Court, 1998)
American Bumper and Manufacturing Co. v. Hartford Fire Ins. Co.
550 N.W.2d 475 (Michigan Supreme Court, 1996)
Ford v. Clark Equipment Co.
274 N.W.2d 33 (Michigan Court of Appeals, 1978)
Adams v. Adams
742 N.W.2d 399 (Michigan Court of Appeals, 2007)
Klever v. Klever
52 N.W.2d 653 (Michigan Supreme Court, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
Posen Construction Inc v. City of Dearborn, Counsel Stack Legal Research, https://law.counselstack.com/opinion/posen-construction-inc-v-city-of-dearborn-michctapp-2015.