Grand Rapids Asphalt Paving Co. v. City of Wyoming

185 N.W.2d 591, 29 Mich. App. 474, 1971 Mich. App. LEXIS 1985
CourtMichigan Court of Appeals
DecidedJanuary 19, 1971
DocketDocket 7377
StatusPublished
Cited by12 cases

This text of 185 N.W.2d 591 (Grand Rapids Asphalt Paving Co. v. City of Wyoming) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grand Rapids Asphalt Paving Co. v. City of Wyoming, 185 N.W.2d 591, 29 Mich. App. 474, 1971 Mich. App. LEXIS 1985 (Mich. Ct. App. 1971).

Opinion

Holbrook, P. J.

This appeal involves an action by plaintiffs on a road construction contract entered into with defendant, City of Wyoming, to recover $5,625 withheld from plaintiffs by defendant as liquidated damages for failure of plaintiffs to timely complete performance under the contract. The case was tried in the Kent County Circuit Court without a jury, and judgment was entered for plaintiffs in the amount of money withheld as liquidated damages by defendant plus interest from July 11, 1966, to date of trial, May 18, 1968, and a judgment of no cause of action, not relevant to this appeal, was entered for defendant regarding plaintiffs’ further *476 claims of entitlement to additional sums representing the cost of alleged additional gravel used and additional labor on manholes, over and above payments made by defendant under the contract. Defendant appeals as of right.

On April 12, 1965, defendant, City of Wyoming, entered into a contract with plaintiffs for the undertaking by plaintiffs of street improvements involving storm and sanitary sewer installation, paving, and sidewalk construction within defendant city. The original contract price was $275,078.45. The contract, silent as to the date when construction was to commence, called for a completion date of November 15, 1965, and, failing completion on that date, defendant city was authorized, pursuant to the contract, to withhold, as liquidated damages, the sum of $25 for each day overdue. The contract, which was admitted into evidence, stated in part:

“The work to be performed under this contract shall be completed and ready for use on or before November 15, 1965. Should the contractor be obstructed or delayed in the prosecution or completion of his work by any act, neglect or default of the owner, then the time herein fixed for completion of the work shall be extended for a period equivalent to the time lost by reason of such delay for the causes herein mentioned. The duration of such extension shall be determined by the owner. It is agreed that in the event the work is not completed by the date specified herein and/or the date to which an extension is granted by the owner liquidated damages shall be charged to the contractor in the amount and in the manner set forth in the proposal.”

The proposal, a part of the contract in question, further stated in part:

*477 “The undersigned [plaintiffs] agrees to complete the same, on or before the completion date or time limit named in this proposal [November 15, 1965]. If the undersigned does not finish the work within the time specified, the city manager, or his duly authorized representative, is, because of the difficulty in estimating damages, authorized to retain out of the money which may be due or become due, the sum of twenty-five (25.00) dollars for each calendar day by which the Contractor shall fail to complete the work, said sum to constitute liquidated damages and not a penalty.”

Plaintiffs commenced operations under the contract on April 27, 1965, and completed them on July 12, 1966, including, in the work completed, additional sidewalk and driveway approach work, not a part of the original plans. .It is not clear from the record whether plaintiffs were t Tmpensated for the additional work. It does appear that defendant in assessing liquidated damages, reduced the damages by 14 days in consideration of the additional work completed. Liquidated damages, therefore, were assessed for a total period of 225 days, including in this figure the winter months when it was impossible to lay asphalt. It was the testimony of defendant’s city engineer that he would not allow plaintiffs to lay the finish course of asphalt on the project area in cold weather and that the defendant city had extended itself by allowing the base course of asphalt, completed the first part of December 1965, to be applied in cold weather. The Michigan State Highway Department Standard Specifications for Road and Bridge Construction, 1963 Edition, a part of the contract in question, states in part (p 212):

“The bituminous surfacing shall be performed in the Lower Peninsula during the period May 15 to *478 November 1 and in the Upper Peninsula during the period June 1 to October 1, unless otherwise authorized by the engineer.”

Any extension in the allowable period of bituminous surfacing, beyond that agreed upon in the contract, would, pursuant to the foregoing provision, require the approval of the engineer.

The record reveals that, in September of 1965, a meeting was called by defendant’s city engineer, at which plaintiffs, and defendant’s city engineer and construction engineer were represented. The purpose of the meeting was to review the progress of the job and attempt to get the construction completed in 1965 or, failing that, to get the base course of asphalt on all of the construction area. At that meeting, no mention of liquidated damages for completion of the project beyond the contract date appears to have been made. The application of the base course of asphalt, completed in December 1965, appears to have been done at that time at the insistence of the city engineer, just as the application of the finish course of asphalt was required in the spring of 1966, rather than in January of that year, at the city engineer’s insistence. In the interim between the first part of December 1965, and the spring of 1966, plaintiffs were prevented, both by the State Highway Department Standard Specifications and by defendant city, from completing the construction project.

Plaintiffs, in their complaint, allege delays and additions to the contract by defendant city in the following particulars, which prevented plaintiffs from completing the work by November 15, 1965:

“A. The defendant city requested plaintiffs to not do work near an outlet located at the Pennsylvania Railroad crossing until the City of Wyoming obtained permission to cross the railroad track; this *479 permission was not obtained by the city in time for the plaintiffs to do the work and caused a delay of at least one month.

“B. The defendant held up completion of the water main alterations at the corner of Long Street and Alger until the City of Grand Rapids could be consulted; this caused a delay of up to three weeks.

“C. Additional sidewalk work was added to the contract after work was commenced; the value of the added work was $12,147 and this caused up to three weeks’ extra delay.

“D. The storm drainage sewers were required to be one to one and a half feet below the depth shown in the specifications, making a total depth of about 23.75 feet; this caused extra delay of at least nine days.

“E. Special manholes (different than provided for in the contract) took eight extra days.”

Defendant city, in its answer, denied the foregoing allegations as to delays.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matthew Leczel v. Intrust Building Inc
Michigan Court of Appeals, 2023
Saleem Chaudhary v. Jds Pump N Go LLC
Michigan Court of Appeals, 2023
Abhe & Svboda Inc v. State of Michigan
Michigan Court of Appeals, 2017
Great American Insurance Co. v. E.L. Bailey & Co.
841 F.3d 439 (Sixth Circuit, 2016)
Midfield Concession Enterprises, Inc. v. Areas USA, Inc.
130 F. Supp. 3d 1122 (E.D. Michigan, 2015)
M & a Associates, Inc. v. Vcx, Inc.
657 F. Supp. 454 (E.D. Michigan, 1987)
Associated Engineers & Contractors, Inc. v. State
567 P.2d 397 (Hawaii Supreme Court, 1977)
City of St. Ignace v. McFarlane
206 N.W.2d 226 (Michigan Court of Appeals, 1973)
Fick v. Fick
196 N.W.2d 18 (Michigan Court of Appeals, 1972)
Village of Bellaire v. Pankop
194 N.W.2d 379 (Michigan Court of Appeals, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
185 N.W.2d 591, 29 Mich. App. 474, 1971 Mich. App. LEXIS 1985, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grand-rapids-asphalt-paving-co-v-city-of-wyoming-michctapp-1971.