Matthew Leczel v. Intrust Building Inc

CourtMichigan Court of Appeals
DecidedJune 15, 2023
Docket362855
StatusUnpublished

This text of Matthew Leczel v. Intrust Building Inc (Matthew Leczel v. Intrust Building Inc) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Matthew Leczel v. Intrust Building Inc, (Mich. Ct. App. 2023).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

MATTHEW LECZEL and FADY CHOLAGH, UNPUBLISHED June 15, 2023 Plaintiffs-Appellees,

v No. 362855 Oakland Circuit Court INTRUST BUILDING, INC., LC No. 2021-187558-CK

Defendant-Appellant.

Before: REDFORD, P.J., and O’BRIEN and FEENEY, JJ.

PER CURIAM.

In this action to compel arbitration pursuant to a residential construction contract, defendant appeals as of right the trial court’s judgment confirming the June 27, 2022 arbitration award in favor of plaintiffs. We affirm.

I. BACKGROUND

On September 26, 2019, plaintiffs and defendant entered into an agreement for the construction of a single-family residence on property purchased by plaintiffs. Defendant agreed to build the residence in accordance with plans and specifications attached to the agreement and to comply with all applicable laws, ordinances, regulations, and codes, and plaintiffs agreed to purchase the completed home for the price stated in the agreement. The agreement required that construction be completed within 14 months and assessed liquidated damages of $100 a day for delays caused by either party. Plaintiffs and defendant agreed to settle any claim, controversy, or dispute arising between them related to the agreement through arbitration pursuant to the Commercial Arbitration Rules of the American Arbitration Association. The arbitrator’s decision would be the parties’ exclusive remedy, and the decision would be final and binding.

On April 21, 2021, plaintiffs filed a complaint in the Oakland Circuit Court asserting that, although the agreement required completion of the project no later than December 1, 2020, the project was far from completion and did not conform to the specifications stated in the agreement. Plaintiffs alleged that defendant had ignored plaintiffs’ requests for updates and clarifications, that they would be responsible for interest payments due to the delay, and that they were forced to rent

-1- space in which to store their furniture and personal property. Plaintiffs requested that the trial court enter an order compelling arbitration pursuant to the parties’ agreement.

One month later, the trial court entered a stipulated order referring the dispute to arbitration under the Uniform Arbitration Act (UAA), MCL 691.1681 et seq. The parties agreed to the appointment of the arbitrator, agreed to general procedures for conducting the arbitration, and agreed that the decision of the arbitrator would be issued through a written opinion. The court dismissed the case without prejudice, but retained jurisdiction to enter a final judgment on the arbitrator’s award.

The arbitrator conducted hearings on May 16, 17, and 26, 2022, and held a closing conference on June 7, 2022. The parties submitted final briefs on June 24, 2022. Three days later, the arbitrator issued an award in favor of plaintiffs. The arbitrator found that construction had not been completed and a balance of $43,850 remained on the contract. He also found reasonable the contracts terms that specified the 14-month construction period, that the residence should have been completed by August 26, 2021, that defendant caused 306 days of delay, and that plaintiffs were entitled to liquidated damages in the amount of $30,600. The arbitrator noted that defendant acknowledged that completion of the work specified in the agreement would cost $12,000; but he concluded, based upon his 45 years’ experience, that defendant understated its estimate and that the cost to complete construction “would more likely be $18,000, especially in light of the current market conditions.” The arbitrator also awarded plaintiffs an additional $5,000 for “time, inconvenience, and uncertainty” and “escalation costs in obtaining a completion of the Residence,” as well as, “the unavailability of a builder’s warranty, which is released by this Award.” After subtracting the amounts awarded to plaintiffs from the contract balance due, the arbitrator calculated the net award to plaintiffs at $14,750.

On July 1, 2022, plaintiffs moved in the trial court for confirmation of the arbitration award and entry of a judgment reflecting the arbitrator’s decision. Ten days later, defendant moved to set aside or modify the arbitration award. Defendant contended that the award was “grossly disproportionate” and contrary to the terms of the parties’ agreement, asserting that while the arbitrator awarded plaintiffs $30,600 in liquidated damages for defendant’s delays, he failed to award defendant any liquidated damages for the 25 days of delay attributable to plaintiffs. Defendant also asserted that the arbitrator had exceeded his authority by increasing the cost of completion from $12,000 to $18,000 based on his 45 years of experience. Defendant argued further that the arbitrator exceeded his authority by awarding plaintiffs $5,000 in damages for “aesthetics,” because plaintiffs failed to mitigate those damages. Defendant asserted that the arbitrator’s award of $5,000 for time, inconvenience, uncertainty, costs of completion, and in lieu of a warranty duplicated damages already awarded and also contended that the arbitration award violated Michigan law regarding the apportionment of delay damages under a construction contract.

Plaintiffs countered that the arbitrator “clearly understood the issues, listened to the testimony, read the exhibits, and made a ruling based on the evidence presented and consistent with the contract documents.” Plaintiffs contended that the award was consistent with Michigan caselaw, the agreement of the parties, and the evidence submitted at the arbitration hearing. Plaintiffs denied that the arbitrator improperly relied on his experience, asserting that defendant’s

-2- estimation of the cost of completion was unrealistic and refuted by the evidence presented, and contended that the agreement and Michigan law permitted the award of damages.

Waiving oral argument pursuant to MCR 2.119(E)(3), the trial court entered an opinion and order on September 2, 2022. Interpreting defendant’s motion as contending that the arbitrator exceeded his authority by awarding liquidated damages for delay, the court explained that liquidated-damages clauses are generally enforceable, a court cannot substitute its interpretation of a contract for that of the arbitrator, and the parties’ agreement provided for liquidated damages in the event of defendant’s failure to complete the project within the time provided in the agreement. The court disagreed that the award of an additional $5,000 for warranty issues was outside the scope of the arbitrator’s authority. Thus, the trial court granted plaintiff’s motion and confirmed the arbitration award. Six days later, the court entered a judgment reflecting the arbitration award.

II. STANDARD OF REVIEW

A trial court’s decision on a motion to set aside, vacate, or modify an arbitration award is reviewed de novo, without extending any deference to the trial court’s ruling on legal issues. Radwan v Ameriprise Ins Co, 327 Mich App 159, 164; 933 NW2d 385 (2018). “Whether an arbitrator exceeded his or her authority is also reviewed de novo.” Id. (citation and quotation marks omitted).

III. ANALYSIS

On appeal, defendant contends that the arbitrator exceeded his authority by improperly apportioning liquidated damages, awarding a form of damages other than liquidated damages, and injecting his opinion as an expert witness for plaintiffs. We disagree.

Arbitration in Michigan is governed by the UAA. MCL 691.1703(1) provides in relevant part:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re EGBERT R SMITH TRUST
745 N.W.2d 754 (Michigan Supreme Court, 2008)
Miller v. Miller
707 N.W.2d 341 (Michigan Supreme Court, 2005)
Wilkie v. Auto-Owners Insurance
664 N.W.2d 776 (Michigan Supreme Court, 2003)
Holmes v. Holmes
760 N.W.2d 300 (Michigan Court of Appeals, 2008)
Mettler Walloon, LLC v. Melrose Township
761 N.W.2d 293 (Michigan Court of Appeals, 2008)
Grand Rapids Asphalt Paving Co. v. City of Wyoming
185 N.W.2d 591 (Michigan Court of Appeals, 1971)
Mosler Safe Co. v. Maiden Lane Safe Deposit Co.
93 N.E. 81 (New York Court of Appeals, 1910)
Great American Insurance Co. v. E.L. Bailey & Co.
841 F.3d 439 (Sixth Circuit, 2016)
Loretta Gayle Galea v. Fca US LLC
917 N.W.2d 694 (Michigan Court of Appeals, 2018)
Early v. Tussing
148 N.W. 678 (Michigan Supreme Court, 1914)
Board of Education v. Chaussee
177 N.W. 975 (Michigan Supreme Court, 1920)
Woodington v. Shokoohi
792 N.W.2d 63 (Michigan Court of Appeals, 2010)
McCoig Materials, LLC v. Galui Construction, Inc.
818 N.W.2d 410 (Michigan Court of Appeals, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Matthew Leczel v. Intrust Building Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/matthew-leczel-v-intrust-building-inc-michctapp-2023.