Early v. Tussing

148 N.W. 678, 182 Mich. 314, 1914 Mich. LEXIS 812
CourtMichigan Supreme Court
DecidedOctober 2, 1914
DocketDocket No. 26
StatusPublished
Cited by11 cases

This text of 148 N.W. 678 (Early v. Tussing) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Early v. Tussing, 148 N.W. 678, 182 Mich. 314, 1914 Mich. LEXIS 812 (Mich. 1914).

Opinion

McAlvay, C. J.

The bill in this case was filed by complainants against defendant to set aside a certain award made by arbitrators. A hearing in the case resulted in a decree dismissing the bill of complaint. Complainants have appealed from such decree.

The statement of facts as presented in the brief of appellants is admitted by defendant to be “substantially correct as a history of the case, and probably as full in its recitals as is necessary to a general understanding of the controversy.” We take from complainants’ statement such facts as we consider material for the purposes of this opinion.

This controversy arises out of a contract made and entered into between the parties to this suit September 25, 1909, supplemented by an appendix thereto, whereby on the part of complainants it was agreed under its terms, which provided certain exceptions, to construct upon a certain foundation ready to receive the iron and mason work a certain six-story business block upon a vacant lot at the northwest corner of Washington avenue and Ottawa street, in the city of Lansing, for an expressed consideration of $37,500. Defendant first- obtained a lease of these premises in June, 1907, and in the winter of 1908-09 finally concluded to construct a business block upon them. The excavation for the basement was begun in March, 1909, and the foundation was completed in June or July following. A contract for the sidewalk was entered into by defendant in May, 1909. Another contract with a foundry company for the structural iron to be used in this building was also entered into by defendant in the same month. The foregoing contracts having been already entered into or com[316]*316pleted, on September 25, 1909, as already stated, the contract between these parties was entered into. It will be necessary to state but few of its details. The building was to be completed on or before May 30, 1910. Complainants were “to complete and have ready for occupancy not later than March 1, 1910, all of the mercantile rooms of the basement, first and second floors,” which were parts of the building already leased to a mercantile firm to be ready for occupancy on that date. Concerning that portion of the building the contract contained the following agreement:

“It is further agreed that, should the contractors fail to finish the work of completing the storerooms aforesaid at the time agreed upon, they shall pay to or allow the owner by way of liquidated damages the sum of $25.00 per diem for each and every day thereafter the said works shall remain incomplete.”

' This is the - only provision for liquidated damages provided for in the contract or any later agreement between the parties.

The original contract of September 25, 1909, contained no agreement to arbitrate. Such agreement was contained in an appendix thereto, and only related to the refusal of either party to “accept the arbitrators’ decision in regard to the value of any works added [to] or omitted from the aforesaid plans and specifications.”

Complainants’ contract covered only the mason and carpenter work on this building. Certain material, equipment, and labor were expressly excluded, to wit, excavating basement and area, concrete retaining walls, structural iron, sidewalks, sidewalk lights, fire escapes, electric wiring, piping for compressed air, compressed air plant, gas-fitting, plumbing, steam pipes, and radiators, elevators, and machinery there.of, and the tables, counters, and shelving for the [317]*317store. All of the above-enumerated material, equipment, and labor were to be furnished by defendant. Complainants were to place and imbed in concrete the iron bases for the columns in basement and erect the structural iron for the building; the first installment of this iron to be delivered at the premises for the use of complainants on or before September 29, 1909, and the balance as required by them. Complainants entered upon the construction of the building immediately after the contract was signed. On October 2d following it is admitted that the work of construction was suspended. Defendant claims that complainants stopped work because he refused to give a bond which they arbitrarily required. Complainants contend that the work stopped because of the default of defendant relative to furnishing necessary structural iron as agreed.

Defendant conceded in the case that on January 17th, during the construction of the building, a storm sewer, or drain, on Ottawa street burst at a point on the south side of, and opposite, the building, flooding the entire basement. It is also conceded that the building was not completed within the time fixed by the contract either as to the mercantile apartments or in its entirety. Complainants contend that, notwithstanding the delays which occurred, the walls were up and the building under roof within three days of the time fixed by the contract, and that the mercantile floors were ready for occupancy the first week in June, 1910.

On the contrary, defendant insists that the building was not completed until August 1st. After the building was completed complainants asked for a settlement and payment of a balance due, and after conferences between the parties had in August, September, and October, the parties, being unable to agree, although they had adjusted most of their differences, finally on November 4, 1910, agreed to and [318]*318executed the following agreement to submit to arbitration :

“This agreement, between Thomas Early and Wm. Fitzpatrick, contractors, party of the first part, and Daniel W. Tussing, party of the second part, all of Lansing, Michigan, made and entered into this 4th day of November, nineteen hundred and ten, witnesseth as follows: That whereas the said Early and Fitzpatrick are the parties of the first part under a contract with the said Daniel W. Tussing as second party, dated September 25th, 1909, in which they agreed to build what was termed therein the ‘mason and carpenter jobs’ for the mercantile and office building situated on lot six, block ninety-six, of the said city of Lansing, and known as the Tussing Building; and whereas differences of opinion have arisen between the parties thereto (being the samé parties as are parties hereto), as to th'e amount due to said Early & Fitzpatrick under same contract:
“Now, therefore, it is covenanted and agreed by and between the parties hereto that the terms and conditions of the same contract dated September 25th, 1909, are held to be the true and correct contract under which the same building was erected; that the terrazza floors mentioned therein were by agreement of the parties not built; and that the contract, price for furnishing materials therein required to be furnished and the labor was $30,500.00, plus the cost of joist as stated in said contract.
“It is further covenanted and agreed by and between the paxties hereto that the said contract, in its true spirit and meaning shall be and is hereby unchanged; but it shall be, and is herein agreed that the claims of the parties hereto where disagreement has arisen upon questions involved in said contract of September 25th, 1909, shall be arbitrated by a committee of arbitration chosen according to the method agreed upon- in said contract. Provided always that the. arbitrators so chosen shall make the said contract of September 25th, 1909, as herein stated the basis of said arbitration.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matthew Leczel v. Intrust Building Inc
Michigan Court of Appeals, 2023
Abhe & Svboda Inc v. State of Michigan
Michigan Court of Appeals, 2017
Great American Insurance Co. v. E.L. Bailey & Co.
841 F.3d 439 (Sixth Circuit, 2016)
Hartford Electric Applicators of Thermalux, Inc. v. Alden
363 A.2d 135 (Supreme Court of Connecticut, 1975)
Grand Rapids Asphalt Paving Co. v. City of Wyoming
185 N.W.2d 591 (Michigan Court of Appeals, 1971)
Hall v. Gargaro
17 N.W.2d 795 (Michigan Supreme Court, 1945)
Palmer v. Patrons' Mutual Fire Insurance
186 N.W. 511 (Michigan Supreme Court, 1922)
Jackson v. State Mutual Rodded Fire Insurance
186 N.W. 514 (Michigan Supreme Court, 1922)
Board of Education v. Chaussee
177 N.W. 975 (Michigan Supreme Court, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
148 N.W. 678, 182 Mich. 314, 1914 Mich. LEXIS 812, Counsel Stack Legal Research, https://law.counselstack.com/opinion/early-v-tussing-mich-1914.