Meyer v. Haven

70 A.D. 529, 75 N.Y.S. 261
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 15, 1902
StatusPublished
Cited by10 cases

This text of 70 A.D. 529 (Meyer v. Haven) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meyer v. Haven, 70 A.D. 529, 75 N.Y.S. 261 (N.Y. Ct. App. 1902).

Opinion

Davy, J.:

The defendant Haven, on the 12th of May, 1892, entered into a contract in writing with the New York Central and Hudson River Railroad Company to construct and complete certain shops at Depew, N. Y. Haven sublet the structural iron work for erecting shops “ A ” and “ B,” so called, to the plaintiffs. The brick work on the walls of shop B ” was erected by the defendant to the height of twenty-six feet. The work was then suspended, for the reason that- the plaintiffs were not. in readiness to erect the iron trusses. This condition of things continued with respect to shop B ” until the fifth or sixth day of the following September, when plaintiffs requested the defendant to complete the Walls of shop “ B ” to the required height of thirty-four feet, as they were ready [531]*531to place upon the walls of said building the iron trusses. In compliance with this request, Haven commenced and prosecuted the work, so that on Friday, the 9th of September, 1892, he .had the walls of shop B ” completed to the height of thirty-four feet. On that day he gave notice to the plaintiffs in writing that the walls of shop “B,” had been erected and were ready for the trusses, and that he should hold them responsible for any damages which he might sustain by reason of their failure to furnish the trusses and iron work as agreed upon, and that the walls were in such a condition that they were liable to be blown down or injured by the elements, unless the iron trusses were at once placed thereon.

On the night of the 13th of September, 1892, the walls of shop “ B,” between the point where the trusses had been placed upon them, and the point where the walls had been raised to the height of thirty-four feet, were blown down.

The defendant Haven procured an order of the Supreme Court discharging the plaintiffs’ lien, upon executing a bond in the sum of $17,500, conditioned for the payment of any judgment which might be rendered against the property. The action was brought to foreclose a mechanic’s lien for $13,789.10, and interest thereon. An answer was interposed, alleging that, by reason of the failure of the plaintiffs to perform their agreement with the defendant, in omitting to place upon the walls of said buildings the iron trusses in time to prevent the destruction of the walls by wind, the defendant was damaged in a large amount, which is set up as a counterclaim to the plaintiffs’ demand. The issues were tried at the Erie County Special Term, and the court found as conclusions of law:

. I. That the plaintiffs are liable to the defendant Haven for the damages suffered by him, because of the failure of plaintiffs to erect the trusses on the walls of shop “ B ” as soon as the walls were in readiness for said trusses, owing to which failure said walls were left in an exposed and unprotected condition and were blown down by the wind.

II. That the amount of said damages not clearly appearing on the trial, the defendant Haven is entitled to a reference to some referee, to be appointed by the court, to take proof of, ascertain and determine the amount of damages sustained by him through the failure of said plaintiffs to erect said trusses.

[532]*532III. That the amount of said damages being so ascertained and determined,, the same shall be applied upon the said sum- of $13,019.04, remaining unpaid from defendant Haven to plaintiffs an reduction thereof. -

IV. That plaintiffs are entitled to recover any balance which may appear to be owing and -unpaid from said defendant Haven to the plaintiffs herein, after applying said damages as aforesaid.

The interlocutory judgment was entered thereon. An appeal was taken therefrom to this court, which was affirmed. (37 App. Div. 202.) A referee was then appointed, and after taking the testimony, he found that the defendant Haven was entitled to recover-from the plaintiffs the sum of $8,660,82, and that the damages, estimated as directed by the interlocutory-judgment and the order of reference, were the necessary expenses of repairing and rebuilding the walls that were blown down, the value of the property destroyed, the amount expended in removing the debris of the fallen walls, in cleaning the brick and the cost of the work required to lay the new walls, amounting in the aggregate to the said sum of $8,660.82. He also found as a conclusion of law that, under the interlocutory judgment and the order of reference, he was limited to the question of damage growing directly out of the failure of the plaintiffs to put the trusses upon said walls, and the falling of the same in consequence thereof. .

The referee, in his supplemental report, found that -the failure of the plaintiffs to perform their contract prevented the defendant from performing his contract with the railroad company until June 25, 1893; that- under the ten per cent clause in the contract with said company the defendant Haven lost, the use of $27,800 from December' 12, 1892, until June 25, 1893, which amounted to the sum of $834; that Havén was compelled to perform and complete a large portion of the work during the winter season, at an increased expense, amounting to at least $2,435; that he was ■ required to retain the services of the engineers, foreman, bookkeepers and timekeepers employed on the work, at a salary and wages amounting to the sum of $4,166 ; that defendant was also compelled to devote his time and personal services to the performance and completion, of the-work, which were reasonably worth the sum of $2,000.' The referee, in his supplemental report, found as conclusions of law that, [533]*533under the decision of the trial judge, the interlocutory judgment entered thereon and the orders of reference entered therein, he had no legal authority or right to pass upon the question of the allowance to the defendant of the foregoing items of damages-. He also found that said items of damages were not such as were contemplated by the plaintiffs and defendant when they entered into the contract, and that the same were uncertain, remote and contingent, and could not be allowed to the defendant.

The principal question involved upon this appeal is, whether the defendant Haven is entitled to all or any portion of the damages referred to in the referee’s supplemental report.

The referee, in his opinion which accompanied his report, states that “ By reference to the opinion of Judge Lambert (the learned justice who tried the case), we find this expression: ‘The principal question arising for a determination upon the issues litigated is, whether the plaintiffs should pay the reasonable costs made necessary in re-erecting the walls blown down, and the damage done to property as a consequence.’ * * * That upon no other theory than that indicated in the opinion of Judge Lambert could the learned judge who wrote for the Appellate Division in this case have said : ‘ There is no question about the measure of damages, providing the plaintiffs’ responsibility is established. Those damages would be the necessary expense of repairing and rebuilding the walls that were blown down.’ (Meyer v. Haven, 37 App. Div. 201.)”

The referee construed this language as binding upon him and as limiting his authority to determine the cost of reconstructing the walls and the value of the property destroyed. This rule of estimating damages would not fully compensate the defendant for all the injuries sustained by him from the falling of the walls.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Menorah Nursing Home, Inc. v. Zukov
153 A.D.2d 13 (Appellate Division of the Supreme Court of New York, 1989)
Veverka v. Spinella
60 Misc. 2d 529 (New York Supreme Court, 1969)
Panzieri-Hogan Co. v. Bender
202 A.D. 94 (Appellate Division of the Supreme Court of New York, 1922)
Allers v. Allers
194 A.D. 96 (Appellate Division of the Supreme Court of New York, 1920)
Southern Ferro Concrete Co. v. Federal Terra Cotta Co.
84 So. 171 (Supreme Court of Florida, 1920)
Volga Realty Corp. v. Chauncey Holt Co.
104 Misc. 581 (Appellate Terms of the Supreme Court of New York, 1918)
McKibbin v. Pierce
190 S.W. 1149 (Court of Appeals of Texas, 1916)
Fairchild v. City & County Contract Co.
153 A.D. 277 (Appellate Division of the Supreme Court of New York, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
70 A.D. 529, 75 N.Y.S. 261, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meyer-v-haven-nyappdiv-1902.