McKibbin v. Pierce

190 S.W. 1149, 1916 Tex. App. LEXIS 1245
CourtCourt of Appeals of Texas
DecidedDecember 13, 1916
DocketNo. 1065.
StatusPublished
Cited by12 cases

This text of 190 S.W. 1149 (McKibbin v. Pierce) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McKibbin v. Pierce, 190 S.W. 1149, 1916 Tex. App. LEXIS 1245 (Tex. Ct. App. 1916).

Opinion

HENDRICKS, J.

Hall Pierce sued H. F. McKibbin to recover damages for the breach of an alleged contract to deliver possession of a certain building in the town of Vernon, and upon the submission of special issues, and findings by the jury, in response thereto, a judgment! was rendered in favor of Pierce, the landlord, against McKibbin, the tenant.

T. L. Pierce, thei father of Hall Pierce, formerly owned the particular brick building occupied by McKibbin; he leased the same to defendant, MeKibbin, for a term of two years, beginning the 1st day of May, 1910, expiring the 1st day of May, 1912; McKib-bin to pay $600 a year rent, payable in installments of $50 per month. At the end of the two years’ term McKibbin held the premises under T. L. Pierce, under a monthly tenancy; the rent at the beginning of this tenancy having been raised to $60 per month.

On March 19, 1913, T. L. Pierce conveyed the premises to his son, Hall Pierce, the plaintiff herein; the periodic monthly tenancy continued as before, at the same rental of $60 per month.

It is claimed by the plaintiff, Hall Pierce, that about the 20th day of April, 1915, while defendant was holding the premises by the month as aforesaid, that he notified McKib-bin, the tenant, through his agent, T. L. Pierce, that he could not continue to use and occupy the premises longer than the 1st day of May, 1915, unless he (McKibbin) “would enter into a written contract for a definite time; that McKibbin refused to enter into such a contract, and agreed that plaintiff should have possession thereof at any time' he might demand it after that time.”

T. L. Pierce continued to act as the authorized-agent of his son, Hall Pierce, the plaintiff herein, and the claim is further made that on the 17th day of September, 1915, defendant, McKibbin, was notified that plaintiff desired possession of said premises on the 1st day of October, 1915, and demanded possession on that date; -that defendant then requested plaintiff to permit him to continue the possession until October 15, 1915; that defendant was then informed that plaintiff had an opportunity of leasing the premises if he could give possession on the 1st day of October, 1915, but that if he could prevail upon Trevathan, the new tenant, to wait until the 15th of October he would comply with the defendant’s request; that Ttrevathan agreed to wait, and plaintiff then agreed with the defendant for the latter to hold possession until the 15th of October, with the distinct understanding that the possession of said premises would be delivered not later than that date, and, rtelying upon defendant’s promises, he (the plaintiff) entered into a contract with Trevathan, leasing the building to him for one year, agreeing to give Trevathan possession on October 15th, and to pay him $10 per day, as liquidated damages, for each day after! October' 15th that he *1150 might fail to deliver such possession; that defendant had notice of the terms of the Trevathan contract when he promised to surrender the premises.

The jury found, besides other facts, that McKibbin was renting the store building from Pierce by the month, and that McKib-bin informed Pierce that he would vacate the building by the 15th of Oct$>ber, 1915; also found that $650 would “compensate plaintiif for any reasonable necessary loss * * * by not having possession of the building * * * on the 15th of October, 1915”; and further found that the amount ($650) “would compensate plaintiff for any reasonable necessary loss * * 4 by not having possession of the building delivered on the 1st day of November, 1915.”

In answer to a special issue requested by plaintiff, the jury additionally found that Mc-Kibbin was “holding the building at will.”

The amount found by the jury as reasonable compensation for plaintiff’s loss is not complained of by appellant. It probably could not be questioned but that, where one party has defaulted with another on account of a third party’s default with him, if there is proof of knowledge to the third party at the time of his contract of special circumstances which make different damages, other than those ordinarilyi implied by the contract, the natural and probable effect of the breach, such damages, as consequential damages, are recoverable, whether liquidated or otherwise. Northwestern Steam Boiler & Mfg. Co. v. Great Lakes Engineering Co., 181 Fed. 89, 104 C. C. A. 52; Iowa Mfg. Co. v. Sturtevant Mfg. Co., 162 Fed. 460, 89 C. C. A. 346, 18 L. R. A. (N. S.) 575; Halstead Lumber Co. v. Sutton, 46 Kan. 192, 26 Pac. 444; Feland v. Berry, 130 Ky. 328, 113 S. W. 425; Meyer v. Haven, 70 App. Div. 529, 75 N. Y. Supp. 261; Sutton v. Wanamaker, 95 N. Y. Supp. 525; Illinois C. R. Co. v. Southern Seathing & Cabinet Co., 104 Tenn. 568, 58 S. W. 303, 50 L. R. A. 729, 78 Am. St. Rep. 933; O. H. Perry Tie & Lumber Co. v. Reynolds, 100 Va. 264, 40 S. E. 919; Modem Steel Construction Co. v. English Construction Co., 129 Wis. 31, 108 N. W. 70; Shurter v. Butler, 43 Tex. Civ. App. 353, 94 S. W. 1084.

The last case cited (Shurter v. Butler, supra, 43 Tex. Civ. App. 353, 94 S. W. 1084) was one where a subcontractor delayed furnishing brick to a principal contractor; the latter having been required to pay liquidated damages to a city because of a failure to complete á sewer within a certain time. It appeared that the subcontractor knew when his contract was made that the work had to be completed within a certain time, and that the completion of the sewer depended upon his furnishing the brick promptly.

The other cases cited apply the same principle, and involve a similar state of facts, except that in some of them the augmented damages, arising out of the special course of circumstances, were not measured by a collateral contract for a liquidated amount.

A repeated consideration and analysis of the facts as to the character of the contract of tenancy discloses, we think, this condition: When the two-year term was ended there was a tenancy from month to month, the rent payable monthly in advance. Assuming that Pierce’s theory is supported by the record, that in April, 1915, on account of McKibbin’s refusal to enter into a written contract, it was then agreed that McKibbin would surrender and Pierce could receive the building on demand; however, the record further shows that thereafter, to October 1, 1915, McKibbin continued to pay the rent monthly in advance as before. We think the tenancy was then reconverted into a periodic monthly tenancy. During the period from April, 1915, to October, of the same year, on account of the rent having been paid in advance by McKibbin, Pierce could'not call for the building at any intervening period in the month for the purpose of repossessing the same on demand — this could not occur until the expiration of the monthly period. Chancellor Walsworth of New York, quoting the syllabus, which reflects the opinion, held:

“Where a party enters into the possession of premises under an agreement to accept a lease for twenty months, and subsequently refuses to accept the lease, he becomes by such refusal a tenant at will, or by sufferance, and may be ejected immediately. But if the landlord subsequently accepts rent from the tenant monthly, according to tie original agreement, a tenancy from month to month is created, commencing from the time of entry.” Anderson v. Prindle, 23 Wend. (N. Y.) 616.

While the facts are not the same, we think, though, the principle is applicable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Bank of Waco v. Thompson
660 S.W.2d 831 (Court of Appeals of Texas, 1983)
Mark v. Belrose Corp.
367 S.W.2d 368 (Court of Appeals of Texas, 1963)
Gregory v. Tyler Grain and Storage Company
341 S.W.2d 221 (Court of Appeals of Texas, 1960)
Luettich v. Putnum
287 S.W.2d 727 (Court of Appeals of Texas, 1956)
Martin v. Southern Engine & Pump Co.
130 S.W.2d 1065 (Court of Appeals of Texas, 1939)
Sellers v. Spiller
64 S.W.2d 1049 (Court of Appeals of Texas, 1933)
Capitol Hotel Co. v. Rittenberry
41 S.W.2d 697 (Court of Appeals of Texas, 1931)
L. B. Menefee Lumber Co. v. Davis-Johnson Lumber Co.
13 S.W.2d 962 (Court of Appeals of Texas, 1929)
J. I. Case Threshing MacH. Co. v. O'Keefe
259 S.W. 222 (Court of Appeals of Texas, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
190 S.W. 1149, 1916 Tex. App. LEXIS 1245, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mckibbin-v-pierce-texapp-1916.