O. H. Perry Tie & Lumber Co. v. Reynolds & Bro.

40 S.E. 919, 100 Va. 264, 1902 Va. LEXIS 24
CourtSupreme Court of Virginia
DecidedMarch 13, 1902
StatusPublished
Cited by16 cases

This text of 40 S.E. 919 (O. H. Perry Tie & Lumber Co. v. Reynolds & Bro.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O. H. Perry Tie & Lumber Co. v. Reynolds & Bro., 40 S.E. 919, 100 Va. 264, 1902 Va. LEXIS 24 (Va. 1902).

Opinion

Buchanan, J.,

delivered the opinion 'of the court

About the 20th of August, 1898, the plaintiffs in error, who were the plaintiffs in the trial court, entered into a contract with the defendants by which they undertook to furnish two bills of lumber, one for forty thousand feet, and the other for • about one hundred and thirty thousand feet, all to be delivered within thirty days at a wharf on James River on board of vessels to be provided by the defendants. Rone of the lumber was delivered within the time fixed by contract. The smaller bill was delivered on the 4th of October, in time for the purpose for which it was ordered, and about it there is no controversy. Rone of the other bill was delivered until Rovember 6, and then only about one hundred thousand feet thereof, too late to reach Rew York in time for the defendants to comply with the terms of their contract for its sale, of which contract plaintiffs had notice when they agreed to deliver the lumber within thirty days. To recover the value of the lumber actually delivered, the plaintiffs instituted their action of assumpsit. The defendanto filed their plea of non-assumpsit, but the defence relied on was a plea of offset in which they claimed damages which they offered to set off against the plaintiffs’ demand. The damages claimed by the defendants consisted of three items:

1. Demurrage paid the vessel engaged to freight the lumber on' account of delay caused by the plaintiffs’ failure to deliver it in accordance with the terms of their contract.

[267]*2672. The amount of money paid by the defendants to the party to whom they had resold the lumber as damages caused by the plaintiffs’ failure to deliver within the time agreed on.

3. The profits which would have accrued to the defendants on their resale, and which they lost by the failure of the plaintiffs to deliver the lumber according to contract.

The jury, upon'the defendants’ demurrer to the evidence, found that if the law was for the plaintiffs, they were entitled to recover the sum of $1,118.33, with interest from November 7, 1898, but if the law was for the defendants, they were entitled to recover the sum of $156.50, with interest thereon from the 3d day of December, 1898. The court was of opinion that the law was for the defendants, and gave judgment in their favor for the last named sum. To that judgment this writ of error was awarded.

The first assignment of .error is that the acceptance by the defendants of the lumber delivered at a time subsequent to that named in the contract for its delivery is an absolute bar to the recovery of damages for a failure to deliver within the time fixed by the agreement of sale.

The authorities are not agreed as to what is the effect of acceptance as a waiver of default as to the time of delivery. Lord Blackburn, in his work on Sales, p. 524, says that “when the contract was to deliver goods at a certain day, and that date is passed, the vendee may accept the goods and bring his action for any damages he may have actually suffered in consequence of the late delivery. He does not, by accepting a late delivery, waive any claim for damages arising from the delay.”

Prof. Mechera, in his treatise on Sales, says: “Not all of the American cases lay down the rule in so unqualified a form, and much must depend upon the circumstances of each case. In many instances, the buyer is in.such a predicament that he has practically no choice, and the true rule doubtless is that the acceptance does not constitute a waiver of damage for the delay, [268]*268in the absence of circumstances showing that such was the intention.” 2 Mech. on Sales, sec. 1889.

If is unnecessary in this case to determine which of the two rules is based upon the better reason or sustained by the weight of authority, as it is clear that, whether, tested by the one or the other, there was no waiver in this case. The correspondence and conduct of the parties not only fail to show any intention on the part of the defendants to waive the damages which had resulted or might result to them from the failure of the plaintiffs to deliver the lumber within the contract time, 'but, on the contrary, show that there was no such intention.

The next question is as to the validity of the items of damages claimed by the defendants.

The first item is $585 for demurrage paid the vessel engaged to carry the lumber. The evidence shows that the defendants made a verbal charter party with the captain of the vessel which they engaged to carry the larger bill of lumber from the point of delivery on James River to Rew York, which contract was afterwards reduced to writing, and was in the usual form. It provided for loading the lumber at the rate of thirty thousand feet per day; for the payment of demurrage at the rate of fifteen dollars pemday for all days beyond that time; and for the payment of dead freight on the difference between one hundred and thirty thousand feet, the agreed cargo, and the amount .actually delivered, at the rate of two dollars and fifty cents per thousand feet. The evidence further shows that the vessel was delayed at least twenty-eight days by the plaintiffs’ failure to deliver the lumber; that the lumber when delivered was thirty thousand feet less than it ought to have been, and that the agreed rate for demurrage and dead freight was reasonable. The demurrage for twenty-eight days, at the rate of fifteen dollars per day, amounted to $420, and the dead freight on thirty thousand feet of lumber, at $2.50 per thousand, amounted to $75, the two sums aggregating $495. Rot only were the de[269]*269f endants bound for this sum by their contract with the captain of the vessel, but the vessel had a lien upon the lumber for it. The Hyperior’s Cargo, 2 Lowell, 294; The Maggie Hammond, 9 Wall. 435. The defendants, having paid this sum, were entitled to recover it from the plaintiffs, or have it set off against their demand, as it clearly appears that it resulted from their failure to deliver the lumber according to the terms of the contract.

It is suggested that the vessel ought to have been used for some other purpose during this long delay, and thus avoided the payment of demurrage in whole or in part.

There would be much force in this suggestion but for the fact that the plaintiffs, after the time fixed by the contract for the delivery of the lumber had expired, by their assurances and representations, from time to time, induced the defendants to believe that the lumber would be delivered in a few days, or by the last of the week, or in a short time, and thus caused them to keep the vessel at the point of delivery ready to receive it.

The assignments of error as to the validity of the other items of damage claimed by the defendants will be considered together.

One of these items is the sum of $654.83 paid by the defendants to their sub-vendee as damages caused by the failure of the plaintiffs to deliver the lumber within the time agreed upon, and the other is $195, the profit which the defendants would have made on their resale of the lumber if the plaintiffs had fulfilled their contract.

The damages which a party may recover for a breach of contract are such as ordinarily and naturally flow from its non-performance, which are proximate and certain, or capable of being made certain, and not remote, contingent, or speculative. Parties are presumed to contemplate the usual and natural consequences of its breach when the contract is entered into.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Virginia Public Service Co. v. Steindler
187 S.E. 353 (Supreme Court of Virginia, 1936)
Mount Rogers Furniture Co. v. Virginia Mirror Co.
154 S.E. 600 (Supreme Court of Virginia, 1930)
Druckman v. Forsyth Furniture Lines, Inc.
22 F.2d 59 (Fourth Circuit, 1927)
Triplett v. Nichols
123 S.E. 339 (Supreme Court of Virginia, 1924)
Richmond Leather Manufacturing Co. v. Fawcett
107 S.E. 800 (Supreme Court of Virginia, 1921)
J. P. Smith Shoe Co. v. Curme-Feltman Shoe Co.
118 N.E. 360 (Indiana Court of Appeals, 1918)
McKibbin v. Pierce
190 S.W. 1149 (Court of Appeals of Texas, 1916)
Grosse v. Petersen
158 P. 511 (California Court of Appeal, 1916)
Scott's v. Chesterman
85 S.E. 502 (Supreme Court of Virginia, 1915)
Richardson Construction Co. v. Whiting Lumber Co.
82 S.E. 87 (Supreme Court of Virginia, 1914)
Lanston Monotype Machine Co. v. Times-Dispatch Co.
80 S.E. 736 (Supreme Court of Virginia, 1914)
Long v. American Surety Co.
137 N.W. 41 (North Dakota Supreme Court, 1912)
Long Pole Lumber Co. v. Saxon Lime & Lumber Co.
62 S.E. 349 (Supreme Court of Virginia, 1908)
Gude & Walker v. Bailey Co.
61 S.E. 135 (Court of Appeals of Georgia, 1908)
State v. Harman
50 S.E. 828 (West Virginia Supreme Court, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
40 S.E. 919, 100 Va. 264, 1902 Va. LEXIS 24, Counsel Stack Legal Research, https://law.counselstack.com/opinion/o-h-perry-tie-lumber-co-v-reynolds-bro-va-1902.