Booth v. . Spuyten Duyvil Rolling Mill Co.

60 N.Y. 487, 1875 N.Y. LEXIS 208
CourtNew York Court of Appeals
DecidedApril 27, 1875
StatusPublished
Cited by95 cases

This text of 60 N.Y. 487 (Booth v. . Spuyten Duyvil Rolling Mill Co.) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Booth v. . Spuyten Duyvil Rolling Mill Co., 60 N.Y. 487, 1875 N.Y. LEXIS 208 (N.Y. 1875).

Opinion

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 489 The point made, that the destruction of the mill by fire was an excuse for the non-performance of the contract by the defendant, is not tenable. In the first place, *Page 491 it does not appear, nor is it found as a fact, that the burning of the mill prevented such performance. The contract was made December twenty-seventh, and the steel caps were to be delivered on the first of April thereafter. The mill burned on the tenth of March; and the proper construction of the finding is, that the defendant was prevented, after that time, from completing the contract, but there was ample time, prior to that event, to have manufactured the caps. A party cannot postpone the performance of such a contract to the last moment and then interpose an accident to excuse it. The defendant took the responsibility of the delay. But the case is not within the principle decided in Dexter v.Norton (47 N.Y., 62), and the authorities upon which it was based. That principle applies when it is apparent that the parties contemplated the continued existence of a particular person or thing which is the subject of the contract, as in the case of the Musical Hall destroyed by fire (3 Best S., 826); in the case of an apprentice who became permanently ill (4 C.P., 1 [L.R.]); and of a woman who, from illness, was unable to perform as a pianist. (6 Ex., 269 [L.R.].) In these and analogous cases a condition is implied that the person or thing shall continue to exist. In Dexter v. Norton (supra), this principle was applied to relieve a party from damages for a failure to deliver property which was burned without his fault, but it has no application to a case of this character. There was no physical or natural impossibility, inherent in the nature of the thing to be performed, upon which a condition that the mill should continue can be predicated. The article was to be manufactured and delivered, and whether by that particular machinery or in that mill would not be deemed material. True, the contract specifies the mill as the place, but it necessarily has no importance, except as designating the place of delivery. For aught that appears, other machinery could have been substituted. The defendant agreed to furnish a certain manufactured article by a specified day, and it cannot be excused by an accident, even if it prevented performance. If it sought protection against such a *Page 492 contingency it should have been provided for in the contract. (12 N Y, 99; 25 id., 272; 25 Conn., 530.) This case belongs to a class clearly distinguishable from those before referred to.

The more important question relates to the proper rule of damages. The referee finds that, prior to the contract with the defendant, the plaintiff had contracted with the New York Central Railroad Company to sell and deliver to it, by the first of June, 400 tons of rails, to be composed of an iron foundation and steel caps, for the invention of which the plaintiff had obtained a patent; and that when the contract was made with the defendant he informed it that he wanted the caps to perform the contract; that if they had been delivered by the first of April the plaintiff could have performed his contract; and he finds, also, facts showing that the plaintiff would have realized the amount of profits for which the recovery was ordered.

The damages for which a party may recover for a breach of contract are such as ordinarily and naturally flow from the non-performance. They must be proximate and certain, or capable of certain ascertainment, and not remote, speculative or contingent. It is presumed that the parties contemplate the usual and natural consequences of a breach when the contract is made; and if the contract is made with reference to special circumstances, fixing or affecting the amount of damages, such special circumstances are regarded within the contemplation of the parties, and damages may be assessed accordingly. For a breach of an executory contract to sell and deliver personal property the measure of damages is, ordinarily, the difference between the contract-price and the market-value of the article at the time and place of delivery; but if the contract is made to enable the plaintiff to perform a sub-contract, the terms of which the defendant knows, he may be held liable for the difference between the sub-contract-price and the principal contract-price, and this is upon the ground that the parties have impliedly fixed the measure of damages themselves, or, rather, made the contract upon the *Page 493 basis of a fixed rule by which they may be assessed. The authorities cited on both sides recognize these general rules. (16 N.Y., 489; 114 C.L.R., 445; 7 C.P., 587 [L.R.]; 26 L. and Eq., 398; 34 N.Y., 364; 40 id., 422; 96 C.L.R., 82; 54 N.Y., 586; 3 Q.B., 181 [L.R.]; 102 E.C.L. [1 Ell. Ell.], 602; 3 C.P., 499 [L.R.]; 8 C.P. [L.R.], 131.) The difficulty is in properly applying general rules to the facts of each particular case. Here it is found, in substance, that the contract was made to enable the plaintiff to perform his contract with the railroad company, and that this was known to the defendant. It is insisted, however, that as the price which the railroad company was to pay the plaintiff for the rails was not communicated to the defendant it cannot be said that it made the contract with reference to such price. It is expressly found that there was no market-price for the steel caps, and it does not appear that there was any market-price for the completed rail. The presumption is, from the facts proved, that there was not. It was a new article, and the contract was made to bring it into use. The result of the able and elaborate argument of the learned counsel for the defendant is, that in such a case, that is when, although the contract is made with reference to and to enable the plaintiff to perform a sub-contract, yet if the terms of the sub-contract, as to price, are unknown to the vendor, and there is no market-price for the article, the latter is not liable for any damages, or, what is the same thing, for only nominal damages. I have examined all the authorities referred to, and I do not find any which countenances such a position, and there is no reason for exempting a vendor from all damages in such a case. It is not because the vendee has not suffered loss, as he has lost the profits of his sub-contract; it is not because such profits are uncertain, as they are fixed and definite, and capable of being ascertained with certainty; it is not because the parties did not contract with reference to the sub-contract, when it appears that the contract was made for the purpose of enabling the vendee to perform it. If the article is one which has a market-price, *Page 494 although the sub-contract is contemplated, there is some reason for only imputing to the vendor the contemplation of a sub-contract at that price, and that he should not be held for extravagant or exceptional damages provided for in the sub-contract. But the mere circumstance that the vendor does not know the precise price specified in the contract will not exonerate him entirely. He cannot, in any case, know the precise market-price at the time for performance. Knowledge of the amount of damages is impracticable, and is not requisite.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Eurospark Industries, Inc.
288 B.R. 177 (E.D. New York, 2003)
Senior Estates, Inc. v. Bauman Homes, Inc.
539 P.2d 142 (Oregon Supreme Court, 1975)
Bay Aviation Services Co. v. Southland Aviation, Inc.
211 F. Supp. 125 (W.D. Arkansas, 1962)
Murarka v. Bachrack Bros.
111 F. Supp. 295 (S.D. New York, 1953)
Czarnikow-Rionda Co. v. Federal Sugar Refining Co.
173 N.E. 913 (New York Court of Appeals, 1930)
Maidment v. Charles A. Krause Milling Co.
225 A.D. 492 (Appellate Division of the Supreme Court of New York, 1929)
Edwards Mfg. Co. v. Bradford Co.
294 F. 176 (Second Circuit, 1923)
Mitsubishi Shoji Kaisha, Ltd. v. Davis
291 F. 57 (Second Circuit, 1923)
Southwestern Coal Co. v. Gunn
1921 OK 428 (Supreme Court of Oklahoma, 1921)
Hood v. Community High School District No. 304
223 Ill. App. 451 (Appellate Court of Illinois, 1921)
Dreyer Commission Co. v. Fruen Cereal Co.
182 N.W. 520 (Supreme Court of Minnesota, 1921)
Newman v. Pierson
195 A.D. 407 (Appellate Division of the Supreme Court of New York, 1921)
Chapman v. . Fargo
119 N.E. 76 (New York Court of Appeals, 1918)
J. P. Smith Shoe Co. v. Curme-Feltman Shoe Co.
118 N.E. 360 (Indiana Court of Appeals, 1918)
Horace Turner & Co. v. Munson S. S. Line
77 So. 61 (Alabama Court of Appeals, 1917)
McConnell v. United States Express Co.
146 N.W. 428 (Michigan Supreme Court, 1914)
Morris Coal Co. v. Thompson
24 Ohio C.C. Dec. 627 (Ohio Court of Appeals, 1913)
Mead v. Kalberg
127 P. 185 (Washington Supreme Court, 1912)
Davis v. Mobile & O. R.
194 F. 374 (Fifth Circuit, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
60 N.Y. 487, 1875 N.Y. LEXIS 208, Counsel Stack Legal Research, https://law.counselstack.com/opinion/booth-v-spuyten-duyvil-rolling-mill-co-ny-1875.