Scott's v. Chesterman

85 S.E. 502, 117 Va. 584, 1915 Va. LEXIS 74
CourtSupreme Court of Virginia
DecidedJune 10, 1915
StatusPublished
Cited by9 cases

This text of 85 S.E. 502 (Scott's v. Chesterman) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scott's v. Chesterman, 85 S.E. 502, 117 Va. 584, 1915 Va. LEXIS 74 (Va. 1915).

Opinion

Cardwell, J.,

delivered the opinion of the court.

This action was instituted by W. A. Chesterman, upon a notice and an amended notice under the statute—section 3211 of Code, 1904—to recover of John G. Scott, as executor of W. H. Scott, deceased, the sum of $3,851.13, with interest thereon, alleged to be due by the defendant to the plaintiff according to an account filed with said notices, under two certain contracts in writing by which the plaintiff agreed to erect and complete within stated periods of time, and in accordance with plans and specifications prepared by certain architects, four store houses, at the southwest corner of Sixth and Marshall streets, in the city of Richmond. The account filed sets forth the aggregate of the contract prices, the ¿mount of extra work claimed to have been done, and the compensation alleged to be due therefor as well as the aggregate of the payments on the contract prices, and showing the balance due thereon to be the sum above stated.

In the original notice it was alleged: “That each and all of the houses mentioned therein have been constructed and completed in accordance with the terms and conditions of said contracts, except as modified under your instructions and have been accepted by you.”

The amended notice added two common counts in assumpsit, both claiming the right to a judgment for the same amount, alleged to be due the plaintiff under the two writ[588]*588ten contracts as stated in the account filed with the original notice, and for extra work, etc.

The two contracts are designated in the record as Nos. 1 and 2. By contract No. 1, the three stores nearest to the corner of said streets were to be completed by March 15, 1912, for the sum of $14,757; and by contract No. 2 the remaining store, No. 4, was to be completed on or before August 1, 1912, for the sum of $5,300, provided possession of the lot should be delivered to the contractor, the plaintiff, by May 1, 1912, or within 90 days from the date that the lot was actually given to him, this lot and the building thereon then being in the possession of a tenant, and upon the delivery of the possession of the lot to the contractor the building thereon was to be taken down by him to make place for the new store. Possession of lots Nos. 1, 2, 3, was given at once to the contractor, but he did not complete the stores thereon until about 7% months after the 15th of March, 1912, the date fixed for their completion in the contract; and as to store No. 4, to have been erected and completed under contract No. 2 on or before August 1, 1912, provided possession of the lot should be delivered to the contractor by May 1, 1912, or within 90 days after possession given, it appears that possession of the premises was obtained by the owner, Scott, from his tenant and turned over to the contractor in advance of May 1, 1912, namely, on February 2, 1912; but the new store thereon was not completed until about the 1st of November following, and when completed it, as well as the other three stores, did not, it is claimed, receive the approval of the owner or the architects, though the owner took possession of all of them about November 1, 1912.

The provisions of the two contracts, are practically the same, with respect to the time and manner of doing the work and the payment of the contract prices therefor, and with respect to questions involved in this litigation the [589]*589contracts provided: Chesterman, the contractor, was, for the consideration therein named, well and properly to erect said stores, furnishing all the materials and labor therefor according to the plans and specifications, and within the time agreed on, in a good workmanlike and substantial manner to the satisfaction of the party of the first part (Scott, the owner) and under the supervision and direction of the architects, Anderson, Cain & Shepherd; (b) that the owner, in consideration of the covenants and agreements of the contract being strictly performed and kept by the contractor, would pay between the first and tenth of each month, upon monthly estimates, eighty-five per cent, of the value of the work installed and materials delivered the preceding month; and (c) “Final payment to be made on the completion of the buildings, to the entire satisfaction of the party of the first part and of the architects; provided that in each of said cases a certificate shall be obtained and signed by the said Anderson, Cain & Shep herd.”

Each contract contained these further provisions: “Should the owner at any time during the progress of the said building, request any alteration, deviation, additions or omissions from said contract, authority of same to be in writing, he shall be at liberty to do so. * * * Should any dispute arise respecting the true construction or meaning of the drawings or specifications, the same shall be decided by Anderson, Cain & Shepherd and their decision shall be final and conclusive; * * * The tenants shall be allowed to install insulation and cold storage plants during the construction of the building. The construction not to interfere with the time of completion of building.”

As stated, there was an original and an amended notice in this action, the plaintiff claiming judgment against the defendant for a balance of $3,851.13 due under the two written contracts, including charges for extra work, etc., [590]*590as shown by an account filed with the original notice. The defendant appeared and made defense to the original notice by the plea of the general issue and a special plea; and to the amended notice he filed the plea of the general issue and a special plea or answer in writing.

In substance, the defense made by the defendant was, (1) that the work done on the buildings contracted for was bad, in certain particulars; (2) that the defendant was entitled to damages for failure to complete the houses by the times set forth in the respective contracts; (8) that the plaintiff was not entitled to sue for the balance due on the original work, because he did not have the required certificate or certificates from the architects, approved by th¿ defendant, that the work and labor done and the materials furnished for the store-houses contracted for were done and furnished in accordance with the contracts between the parties; and (4) that said stores were built to be rented to tenants then ready and waiting to occupy them, at annual rentals (which were stated), and that by reason of the default of the plaintiff in the performance of the conditions and requirements of said contracts, the defendant had suffered damages to the amount of $8,186.61, for which he prayed judgment against the plaintiff.

No objection was interposed to these pleas, but issue was joined thereon, and upon a trial of the case the jury, after hearing the evidence and receiving the instructions of the court, returned the following verdict: “We, the jury, upon the issues joined find for the plaintiff and assess the damages at two thousand and nine hundred and nineteen dollars and fifty-seven cents ($2,919.57).” Whereupon, the defendant moved the court to set aside said verdict upon the following grounds: (1) That it was not responsive to the issues made by the pleadings, and subsequently moved in arrest of judgment; (2) that it was contrary to the law and the evidence; (8) because of misdirection of [591]*591the jury; and (4) because it was excessive.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gaines v. Commonwealth
574 S.E.2d 775 (Court of Appeals of Virginia, 2003)
Sweeney Co. v. Engineers-Constructors, Inc.
823 F.2d 805 (Fourth Circuit, 1987)
State Highway & Transportation Commissioner v. Allmond
257 S.E.2d 832 (Supreme Court of Virginia, 1979)
Mann v. Clowser
59 S.E.2d 78 (Supreme Court of Virginia, 1950)
Flanagan v. Harvey
168 S.E. 448 (Supreme Court of Virginia, 1933)
Arkla Lumber & Manufacturing Co. v. West Virginia Timber Co.
132 S.E. 840 (Court of Appeals of Virginia, 1926)
Berry v. Berry's
89 S.E. 242 (Supreme Court of Virginia, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
85 S.E. 502, 117 Va. 584, 1915 Va. LEXIS 74, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scotts-v-chesterman-va-1915.