Iowa Mfg. Co. v. B. F. Sturtevant Co.

162 F. 460, 18 L.R.A.N.S. 575, 1908 U.S. App. LEXIS 4466
CourtCourt of Appeals for the Eighth Circuit
DecidedMay 25, 1908
DocketNo. 2,705
StatusPublished
Cited by5 cases

This text of 162 F. 460 (Iowa Mfg. Co. v. B. F. Sturtevant Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Iowa Mfg. Co. v. B. F. Sturtevant Co., 162 F. 460, 18 L.R.A.N.S. 575, 1908 U.S. App. LEXIS 4466 (8th Cir. 1908).

Opinion

ADAMS, Circuit Judge.

The Sturtevant Company sued the Iowa Company for a balance due on a contract for the sale and delivery of machinery. Defendant admitted the sale and delivery, pleaded a payment of $4,020 on account, and set up a counterclaim for damages occasioned by plaintiff’s failure to deliver the machinery according to contract. The trial resulted in a verdict for plaintiff for the balance due on the contract, a verdict for the defendant on its counterclaim for an item of $871.90 for loss of laborers’ time occasioned by plaintiff’s delay, and a denial by direction of the court of defendant’s further claim for an item of $1,475. Defendant prosecutes error solely on account of that denial.

Was there any substantial evidence entitling the defendant to go to the jury on that item? The facts are these: The defendant, the Iowa Company, on May 27, 1905, made a contract in writing with the state of Missouri to equip the State Normal School at Cape Girardeau with machinery and appliances for lighting, heating, and ventilating the building. The contract obligated defendant to complete and fully install the work on or before October 15, 1905, and contained a stipulation requiring the payment of $25 per day to the state for each and every day’s delay in performance after the date so fixed. The learned trial judge ruled in view of the circumstances attending the case that this stipulation was enforceable as between the parties to that contract as a reasonable and proper provision for liquidated damages as distinguished from a penalty, and no contention is now made to the contrary. Defendant not being a manufacturer of the required machinery and appliances, on June 6, 1905, entered into a written contract with plaintiff, the Sturtevant Company, whereby the latter obli[462]*462gated itself to furnish and deliver the samé f. o. b. cars at Cape Girar-deau within one month thereafter, that is, on or before July 6, 1905. Plaintiff failed to perform its part of the contract within the stipulated time. It shipped nothing until October, and then only a part of the machinery. The balance followed, some in November and some as late as January, 1906. On the completion of the work defendant was required to allow $25 per day, the stipulated liquidated damages for 59 days’ delay, or a total sum of $1,475 which -was in settlement deducted from the amount otherwise due the defendant from the state of Missouri according to the terms of the contract. The trial judge sustained objections to some of the evidence offered in support of defendant’s right to recover this item from plaintiff, and all of it was ultimately by direction of the court withdrawn from the consideration of the jury.

The court assigned as grounds for its action (1) that it was not provided in the contract between plaintiff and defendant that there should be any damages in case of failure to furnish the machinery within the stipulated time; and (2) that it did not appear that defendant had been charged with this.item in settling with the state of Missouri or that it had sustained any loss by reason of the delay. The first ground is clearly untenable. The rule governing the recovery of special damages for the breach of a contract has been frequently stated by this court, and most recently in the case of Taber Lumber Co. v. O’Neal (C. C. A.) 160 Fed. 596, where it is said:

“Sueli damages, as distinguished from those ordinarily sustained, can be recovered only when they are the result of special circumstances known to the parties at the time the contract was made, when they are the natural and direct result of a breach and when they can be ascertained with reasonable accuracy.”

To the same effect are the cases of McDonald v. Kansas City Bolt & Nut Co., 149 Fed. 360, 79 C. C. A. 298, 8 L. R. A. (N. S.) 1110, and the many other cases cited. There was, in our opinion, ample evidence tending to bring the defendant’s claim within the protection of this rule.

' Defendant’s secretary and general manager testified that at the time of executing the contract between plaintiff and defendant he informed the plaintiff that his company was under contract obligation to finish the entire work of installing the machinery in the Normal School on or before October 15, 1905, and also that it was liable to pay $25 per day for each day’s delay thereafter. This evidence taken in connection with the stipulation in the contract requiring plaintiff to ship all the machinery before July 6th tends to show knowledge by plaintiff of -such special circumstances ás might occasion unusual damages to defendant if the former failed to deliver the machinery in due time, and also tends to show that such damages would be the direct and natural consequences.of such failure. It is of no consequence, in our opinion, that a statement of the circumstances was not contained in the formal contract itself. Knowledge of them' brought to plaintiff in any manner at the time of entering into the contract served the required purpose of warning it of the special peril which might attend [463]*463the failure to keep its engagements and subjects it to the special damages likely to follow and reasonably to be apprehended from such failure. Plaintiff made the contract in contemplation of the special circumstances so known to it, and, in case of breach, is liable for the natural and proximate result'thereof.

Does it so clearly appear that defendant sustained no loss by plaintiff’s delay as to justify the court’s action in withdrawing the claim therefor from the consideration of the jury? The evidence is uncon-tradicted that the defendant did not complete its work until 77 days after the limit of time prescribed in its contract with the state. The state conceded that it was itself responsible for the delay to the extent of 18 days and charged to defendant the agreed sum per day for the balance, 59 days, amounting in the aggregate to $1,413. Prima facie the failure to perform within the time limited created a liability against the defendant in favor of the state for the agreed amount of the liquidated damages; but this, of course, would not create any liability against plaintiff unless it had, with the knowledge of the special circumstances, in some way occasioned the delay. If plaintiff did so occasion the delay, it ought to be and is responsible for its consequences. The evidence is within a narrow compass. Defendant’s secretary and general manager testified that the delay in getting the machinery and appliances from plaintiff within the time fixed by the contract alone caused the delay in the execution of its contract with the state. Pie also testified, in substance, that his company could not finish its work until the Sturtevant engines and other machinery arrived. Suffice it to say that there rvas evidence amply sufficient to go to the jury tending to show that the failure of the Sturtevant Company to make delivery of its machinery within the agreed time occasioned some if not all of the delay in the performance by defendant of its contract with the state.

The learned trial judge said that it does not appear that defendant has been charged with the item in question by the state, but that it does appear that plaintiff has a pending claim against the state for the item in question as the balance due on the contract price. We think this statement discloses a misapprehension of the facts of the ease. The only evidence on this subject is that given by the secretary and manager.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L. B. Menefee Lumber Co. v. Davis-Johnson Lumber Co.
13 S.W.2d 962 (Court of Appeals of Texas, 1929)
J. M. Hays Wood Products Co. v. Simmons Saddlery Co.
255 S.W. 973 (Missouri Court of Appeals, 1923)
McKibbin v. Pierce
190 S.W. 1149 (Court of Appeals of Texas, 1916)
Campfield v. Sauer
189 F. 576 (Sixth Circuit, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
162 F. 460, 18 L.R.A.N.S. 575, 1908 U.S. App. LEXIS 4466, Counsel Stack Legal Research, https://law.counselstack.com/opinion/iowa-mfg-co-v-b-f-sturtevant-co-ca8-1908.