Johnson v. Prineville

196 P. 817, 100 Or. 105, 1921 Ore. LEXIS 100
Oregon Supreme Court·Decided April 5, 1921·Published·Cited by 17 cases

Opinion

BURNETT, C. J.

1. It is argued in the defendant’s brief that—

“A complaint on a contract, which sets out the contract in full but fails to allege plaintiffs’ performance of its conditions, does not state a cause of suit or action, and this objection may be raised for the first time in the appellate court.”

This is sound in principle, but it is not applicable to the pleadings, for we find the allegation already quoted from the complaint, that the work was done by the plaintiffs in accordance with the terms of the contract.

It is contended that the complaint shows that an engineer, Mr. Huson, was selected by the parties to arbitrate the differences from station 0 to station 343, and that he made an award. We do not so construe the complaint. The substance of that pleading, in that respect, is that negotiations were had looking to an arbitration, but that they came to naught and no arbitration was in fact had. Indeed, it is stated in the defendant’s fourth separate defense appearing in its answer that no arbitration was had or agreed upon by the parties.

2. It is urged, also, that the contract was entered into by the plaintiffs as a copartnership and that they had not filed in the office of the county clerk a certificate as required by Section 7777, Or. L. That section reads thus:

“No person or persons shall hereafter carry on, conduct or transact business in this state under any assumed name or under any designation, name or style, corporate or otherwise, other than the real and true name or names of the person or persons conducting such business or having an interest therein, unless such person or all of such persons conducting said business or having an interest therein, shall [114]*114file a certificate in the office of the county clerk of the county or counties in which said business is to be conducted, which certificate shall set forth the designation, name or style under which said business is to be conducted, and the true and real name or names of the party or parties conducting or intending to conduct the same, or having an interest therein, together with the postoffice address or addresses of said person or persons. Such certificate shall be executed and acknowledged by the party or parties conducting, or intending to conduct said business, or having an interest therein, before an officer authorized to take acknowledgment of deeds.”

As already noted, the contracting parties of the second part are E. T. Johnson and H. M. Johnson. The instrument was signed, “E. T. Johnson & Son, by E. T. Johnson.” The attesting clause recites that “E. T. Johnson and H. M. Johnson do sign and seal the same.” This statute is substantially copied from the legislation of our sister state, Washington. In the Sutton Case, 49 Wash. 694 (96 Pac. 428), the firm name under consideration was “A. E. Sutton & Company.” In the Hale-Tindall Case, 66 Wash. 459 (119 Pac. 837), the firm name was “Hale-Tindall Company.” In the Merrill Case, 70 Wash. 482 (127 Pac. 122), the firm name was “George W. Merrill Automobile Company.” In all of those cases the Supreme Court of Washington exempted the partnership thus styled from the effects of the act. The principle is that the true names of the parties appear in the instrument and there is no fictitious name involved. The same doctrine was announced in Patterson v. Byers, 17 Okl. 633 (89 Pac. 1114, 10 Ann. Cas. 810), involving the firm name of Patterson Furniture Company; and in Bolen v. Ligett, 49 Okl. 788 (154 Pac. 547, L. R. A. 1916D, 355), concerning the firm name of Bolen Brothers. In California [115]*115“Lamberson and Lamberson” was sustained as a firm name exempted from tbe operation of tbe statute, in tbe case of Lamberson v. Bashore, 167 Cal. 387 (139 Pac. 817). In Carland v. Heckler, 233 Fed. 504 (147 C. C. A. 390), it is said tbat tbe names of partners given in tbe body of tbe contract take it out of tbe miscbief forbidden by tbe statute. Tbe firm name under consideration there was “Lakeside Dredging Company.” In Missaukee Co. v. Ferriss, 193 Mich. 286 (159 N. W. 490), it was held tbat in equity, where tbe defendants knew with whom they were dealing, tbe statute did not apply. Here, tbe recitation of tbe individual names of tbe partners in the body of tbe contract, and tbe fact tbat there is no assumed name or any other than tbe real, true name of tbe individuals conducting tbe business, take the case entirely out of tbe operation of tbe statute. Only one precedent is cited by tbe defendant on this subject, namely, that of North v. Moore, 135 Cal. 621 (67 Pac. 1037), a California case which has been overruled by tbat court on more than one occasion. Aside from tbe principle tbat no fictitious name is employed, we should be bound by tbp construction of tbe statute given it by tbe courts of tbe state from which we copied it.

3. It may well be conceded tbat at law tbe plaintiffs, suing on a contract containing a clause making tbe engineer tbe arbiter or umpire between tbe parties and giving conclusiveness to bis award, must show tbat tbat provision of tbe contract has been complied with as well as any other. But it is well recognized tbat in equity tbe award may be set aside, where tbe classification is so grossly erroneous as to amount to fraud upon tbe contractor. This principle was enunciated in tbe opinion of Mr. Justice Bean in [116]*116Sweeney v. Jackson County, 93 Or. 96 (178 Pac. 365, 182 Pac. 380). It is also taught in Oregon-Wash. R. & N. Co. v. Spokane, Portland & Seattle Ry. Co., 83 Or. 528 (163 Pac. 600, 989, Ann Cas. 1917C, 991), in an opinion by Mr. Justice McCamant. A careful reading of the contract discloses that the engineer may order a discontinuance of the work for four several causes: First, delay; second, bad faith violation of its terms by the contractor; third, because the same was not begun on time; and, fourth, because it was not completed within the time specified- — in •either of which cases the engineer may cause the contractor to discontinue all work, or in the alternative he may himself enter upon the premises and complete the same and “adjust any difference in price,” or damage, and on all such matters the decision of the engineer shall be final. In respect to this, the contract provides that an appeal may be taken in writing to the city engineer and the city council; that neglect to make such written appeal within the time specified forfeits all claims; and that all such “differences” (meaning evidently the differences arising in case the engineer takes charge of the work) shall be adjusted by arbitration, the contractor and the city engineer to select a third arbiter. Evidently the clause in the contract quoted at the beginning of this opinion refers to a situation where the engineer himself has entered upon and taken charge of the work. Otherwise, we cannot construe as effectual the other clause later in the contract, that ‘ ‘ all prior partial estimates and payments shall be subject to correction in the final estimate and payment.” It is true that according to the admitted stipulations attached to the contract the engineer’s decision as to amount or quantities to be paid for shall be final and conclusive, and [117]

Free access — add to your briefcase to read the full text and ask questions with AI

Johnson v. Prineville, 196 P. 817, 100 Or. 105, 1921 Ore. LEXIS 100 (Or. 1921).

196 P. 817 (Johnson v. Prineville) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Krieg v. UNION PACIFIC LAND RESOURCES CORPORATION
525 P.2d 48 (Oregon Supreme Court, 1974)
Hindman v. United States
223 P.2d 393 (Oregon Supreme Court, 1950)
Halvorson v. Blue Mountain Prune Growers Cooperative
217 P.2d 254 (Oregon Supreme Court, 1950)
Halvorson v. Blue Mt. Prune Growers Co-Op.
217 P.2d 254 (Oregon Supreme Court, 1949)
Rueda v. Union Pacific Railroad Co.
175 P.2d 778 (Oregon Supreme Court, 1946)
Gulick v. Nelson
159 P.2d 817 (Oregon Supreme Court, 1945)
Johnston v. Ellis
285 P. 1015 (Idaho Supreme Court, 1930)
Coston v. Portland Trust Co.
282 P. 442 (Oregon Supreme Court, 1929)
Armishaw v. Kan
260 P. 1011 (Oregon Supreme Court, 1927)
Adams v. Kennard
253 P. 1048 (Oregon Supreme Court, 1927)
Baker v. Multnomah County
246 P. 352 (Oregon Supreme Court, 1926)
Maroulas v. State Industrial Accident Commission
244 P. 317 (Oregon Supreme Court, 1926)
Borg v. Utah Construction Co.
242 P. 600 (Oregon Supreme Court, 1925)
West v. Coos County
237 P. 961 (Oregon Supreme Court, 1925)
Ontario Advancement Co. v. Stevens
231 P. 127 (Oregon Supreme Court, 1925)
Spitzer v. Rolph
218 P. 748 (Oregon Supreme Court, 1924)