Wilson v. Drainage District No. 2

213 P. 635, 113 Kan. 82, 1923 Kan. LEXIS 336
CourtSupreme Court of Kansas
DecidedMarch 10, 1923
DocketNo. 24,170
StatusPublished
Cited by5 cases

This text of 213 P. 635 (Wilson v. Drainage District No. 2) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilson v. Drainage District No. 2, 213 P. 635, 113 Kan. 82, 1923 Kan. LEXIS 336 (kan 1923).

Opinion

[83]*83The opinion of the court was delivered by

Mason, J.:

Marion B. Wilson under a written contract with Drainage District No. 2 of Doniphan county constructed several ditches, roads and levees. At the conclusion of the work he brought this action for the balance alleged to be due him. The district defended upon the ground that in the case of -two ditches he had not excavated the quantity of earth for which he made claim, and that he had in several respects failed to comply with the specifications, particularly in omitting in some places to leave a ten-foot berm— space between the edge of the ditch and the embankment made from the removed earth. After the introduction of evidence by both parties the court directed a verdict for the plaintiff, on which judgment was rendered. The defendant appeals.

Two witnesses for the defendant testified that they had made measurem'ents and calculated the amount of earth necessarily removed (that being all for which by the terms of the contract payment was to be made), the results of which they gave, the total being 1,852.4 cubic yards less than the quantity upon which the plaintiff’s claim was based. Upon cross-examination, matters were developed tending to cast doubt upon the accuracy of their figures and to detract from the weight of their evidence. Their testimony was sufficient, however, to entitle the defendant to go to the jury upon the question as to the quantity of earth for the excavation of which the plaintiff was entitled to pay, unless the contract is to be interpreted as making the engineer’s decision on that matter final, by virtue of a paragraph reading:

“The engineer shall in all cases determine the quantities of the several kinds of work to be paid for under this contract, and he shall decide all questions as to lines, levels, etc. Any doubt as to the plans and specifications will be explained by the engineer and his interpretation shall be final and binding upon the parties hereto.”

It is of course competent for the parties to a contract to agree that the finding- of an engineer or other. designated person upon the quantity and character of work done shall be conclusive, in which case it can only be impeached for bad faith or what amounts to that. (Atchison v. Rachliffe, 78 Kan. 320, 96 Pac. 477; Edwards v. Hartshorn, 72 Kan. 19, 82 Pac. 520; 6 R. C. L. 962-964; 9 C. J. 772-774.) The texts just cited include these statements:

“But it has been said that -to make conclusive-the decision.or,certificate of an architect or engineer requires plain language in the contract, and that an [84]*84estimate of the work done or amount due is not conclusive, in the absence of a provision in the contract to that effect.” (6 R. C. L. 963.)
“It has been held that, if the contract does not provide that the architect or other person’s decisions shall be final and conclusive, a provision to that effect cannot be implied.” (9 C. J. 772.)

In a case involving the finality of an architect’s certificate that work had been completed according to the contract it was said: “To make such a certificate conclusive requires plain language in the contract. It is not to be implied.” (Mercantile Trust Co. v. Hensey, 205 U. S. 298, 309.)

In Illinois Central R. R. Co. v. Manion, 113 Ky. 7, a contract for raising the bed of the railroad contained these provisions, which are strikingly similar to those now under consideration:

“The said work shall be executed in strict conformity to the specifications and such explanatory instructions as may from time to time be given by the said chief engineer dr the engineer in charge of the work. The amount of work performed under this contract shall be determined by the measurements and calculations of the engineer in charge of the work, who shall have full power to condemn and reject any and all work which, in his opinion, does not conform to the requirements hereof. Should any dispute arise between the parties respecting the true construction or meaning of the specifications, the same shall be decided by the said chief engineer, and his decision shall be conclusive and binding upon all parties hereto.” (p. 12.)

The interpretation placed Upon this language is shown by an excerpt from the opinion:

“It is earnestly maintained for the company that the estimates of the engineer in charge are conclusive on Manion, unless fraudulent, or so grossly erroneous as to imply fraud or a failure to exercise an honest judgment. City of Covington v. Limerick (19 R., 330) (40 S. W., 254) and cases cited. The contract in this case is different from that in the Limerick case. That contract provided'that the decisions of the engineer should be final and binding on both parties. There is no such provision in the contract before us. It simply provides that the amount of work performed under the contract shall be determined by the measurements and calculations of the engineer in charge. This is nothing more than a stipulation for a means of determining the amount of the work, and the determination by the engineer is entitled to no more weight than a determination by the concurrent act of the two parties under a provision requiring the amount of Work to be done to be settled in that way. If the engineer Was guilty of fraud or made a mistake, it may be shown. Fraud or mistake is a ground for relief from a settlement made by the parties themselves, and we see no reason why the same rule should not apply to a settlement made for them by the servant of one of them alone, unless the contract expressly provides otherwise.” (p. 12.)

The syllabus in The State v. Construction Co., 91 Kan. 74, 136 [85]*85Pac. 905, contains this language, the phrase which we regard as of importance here being italicised:

“The parties agreed upon the architect as the person upon whose judgment and decision with respect to the character, amount and value of the work payments were to be made. In the absence of fraud or mistake, they are bound by his judgment and decision.” (Syl. ¶ 2 (b).)

The practice of inserting in construction contracts a clause expressly making the decisions of an engineer or architect conclusive, where such is the purpose, is so general that its omission in a particular case suggests an inference that only a prima facie effect was in contemplation. In the present case the omission of the contract to say in so many words that the engineer’s determination of the quantities of the several kinds of work to be paid for should be conclusive is the more significant from the fact that in the second sentence of the same paragraph the engineer’s interpretation of the plans and specifications is explicitly made conclusive. We cannot construe the finality clause as applying to any ruling except upon the meaning of the plans and specifications; nor can we escape the conviction that the failure to incorporate such a clause in the sentence concerning the quantity of work to be paid for must be regarded as making a distinction in this respect between the different kinds of decisions to be made by the engineer. We conclude that the engineer’s determination as to the quantity of earth excavated was not conclusive, and the question of fact in that respect should have been submitted to the jury.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morriss v. Coleman Co.
738 P.2d 841 (Supreme Court of Kansas, 1987)
OK Johnson Electric, Inc. v. HESS-MARTIN CORPORATION
464 P.2d 206 (Supreme Court of Kansas, 1970)
Neale Construction Co. v. Topeka Township Sewage District No. 1
285 P.2d 1086 (Supreme Court of Kansas, 1955)
Kansas Wheat Growers Ass'n v. Bridges
261 P. 570 (Supreme Court of Kansas, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
213 P. 635, 113 Kan. 82, 1923 Kan. LEXIS 336, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilson-v-drainage-district-no-2-kan-1923.