Stiers Bros. Const. Co. v. Broderick

60 F. Supp. 792, 1945 U.S. Dist. LEXIS 2282
CourtDistrict Court, D. Kansas
DecidedApril 7, 1945
DocketCiv. 4922
StatusPublished
Cited by4 cases

This text of 60 F. Supp. 792 (Stiers Bros. Const. Co. v. Broderick) is published on Counsel Stack Legal Research, covering District Court, D. Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stiers Bros. Const. Co. v. Broderick, 60 F. Supp. 792, 1945 U.S. Dist. LEXIS 2282 (D. Kan. 1945).

Opinion

MURRAH, District Judge.

This matter comes on for decision at Kansas City, Kansas, on this 7th day of April, A. D., 1945, on plaintiff’s and defendants’ separate Motions for Summary Judgment and the Court, on January 13, 1945, having heard arguments on said motions for summary judgment by counsel for the respective parties and now having fully examined the pleadings and admissions on file, including the answers to interrogatories filed by the defendants at the request of the plaintiff, and having fully examined the affidavits filed in support of the Motions for Summary Judgment and having fully interrogated counsel finds:

1. That this is an action in which the plaintiff seeks to recover damages of the defendants for alleged breaches of contract, and in which, by counterclaim, defendants seek to recover of plaintiff the amount of an alleged over-payment made by the defendants to the plaintiff in the final settlement of the contract, all of which appears more fully hereinafter.

2. That all matters pertinent to these findings and the judgment hereinafter contained are set forth in the following pleadings and papers all on file with the Court:

a. Amended Complaint to which a copy of the contract between plaintiff and defendants and a rough drawing of the Fume Exhaust System are attached as exhibits.

b. Amended Answer (containing a counterclaim) to which the Findings of Fact of the Contracting Officer, the Ruling of the Contracting Officer, the Appeal of the plaintiff from the Ruling of the Contracting Officer to the Chief of Engineers and the decision of the Chief of Engineers are attached as exhibits A, B, C and D, respectively.

c. Plaintiff’s Reply to Counterclaim.

d. Plaintiff’s motion for Summary Judgment supported by the individual affi *794 davits of D. G. Foutes, M. Gollub, L. J. Stiers and Robert N. Jones.

e. Defendants’ Motion and their Amended Motion for Summary Judgment supported by the affidavit of C. Howard Murphy.

f. Answer of defendants made under oath by I. L. Swearingen, their Office Manager, to Interrogatories Propounded by Plaintiff and served on defendants on or about November 16, 1944.

g. Affidavit on behalf of defendants made by I. L. Swearingen, their Office Manager, in response to Interrogatories Propounded by Plaintiff served on defendants on or about December 19, 1944.

and that the foregoing instruments were all duly filed by the respective parties and in each instance duly served upon opposing parties as required by the Federal Rules of Civil Procedure, 28 U.S.C.A. following section 723c;

3. That at all times mentioned in the foregoing pleadings, motions, etc., the defendants, sometimes designated by the letters “A-B-M”, were and they now are cost-plus-a-fixed-fee contractors of the War Department of the United States under Principal Contract No. W-461-eng10274, and as such were and now are engaged in the construction of the Sunflower Ordnance Works in Johnson County, Kansas, under the supervision and control of a commissioned officer of the Corps of Engineers of the United States Army acting as the Contracting Officer for the United States; that during all times pertinent to this case, such Contracting Officer was Lt. Colonel E. E. Taylor who is variously designated in the pleadings and papers as the “Contracting Officer” and/or the “Area Engineer”; that the Chief of Engineers, referred to in many instances, is a commissioned officer of the Corps of Engineers of the United States Army whose headquarters were and are in Washington, D. C;

4. That the plaintiff was at all times pertinent to this matter, a unit price subcontractor of the defendants under subcontract No. 53 to said Principal Contract No. W-461-eng-10274, under and by the terms of which the plaintiff was required to furnish all labor and equipment and to construct the complete Fume Exhaust System at the Sunflower Ordnance Works and that said subcontract was entered into between plaintiff and defendants with the approval of the Contracting Officer;

5. That said Fume Exhaust System consisted generally of 3 separate vitrified clay pipe lines, 36" in diameter, together with other appurtenances such as plenum chambers, exhaust traps, etc.; that said 3 pipe lines were designated as “B” line, “C” line, and “D” line respectively, and were of an aggregate length of 12,885.84 feet; that said pipe lines were installed for a part of the distance in trenches underground, for another part of the distance on timber trestle work aboveground, and for the remainder of the distance they passed through a tunnel structure under a railroad fill supporting a standard gauge single track railroad; that for a part of the distance, the 3 pipe lines were laid in a single trench underground, and for the remainder of the distance underground, the 3 pipe lines were in separate trenches; that the 3 pipe lines passed under the railroad through a single tunnel and were laid parallel and adjacent to each other in said tunnel;

6. That the subject matter of this lawsuit as disclosed by the Amended Complaint, the Amended Answer including a Counterclaim, and the affidavits in support of the Motions for Summary Judgment concerns only the construction of a part of said Fume Exhaust System, to-wit:

a. The construction by the defendants with their own labor and equipment, and at their own expense, of “C” line between stations 10/70.16 and 29/53, between which stations the line was laid entirely underground in a single trench for a distance of 1882.84 feet;

b. The excavating of an open cut through a railroad fill between stations 8/01 and 8/97 to provide for the construction of a timbered tunnel, the back filling of said open cut after the installation of the timbered tunnel and the incidental removal and replacement of the railroad track on the fill. The work involving the removal of the railroad track, the excavation of the cut, the back filling of the cut after the tunnel was constructed and the replacement of the railroad track was performed by the defendants with their own equipment and labor and at their own expense. The work involved in the actual construction of the timbered tunnel, the placing of a sand bed or “sand fill” in the bottom of said tunnel and the laying of the pipe lines through the tunnel was performed by the plaintiff and the plaintiff has been paid in full therefor;

*795 c. The digging of post holes by the defendants with their own labor and equipment and at their own expense on the remaining parts of “C” line and on “B” and “D” lines, but for which work, plaintiff was fully paid as though it had performed the same;

that as to all other items of construction involved in said Fume Exhaust System, plaintiff did perform the work with its own equipment and labor and at its own expense and was paid in full for such work in the amount of $65,043.48, which amount includes the alleged overpayment of $863.-19 which is the subject matter of defendants’ Counterclaim, and excepting as to the matter of the Counterclaim, there is no dispute between the parties as to the work for which plaintiff has received such payment;

7. a. That as to that portion of “C” line constructed by the defendants (Item a.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
60 F. Supp. 792, 1945 U.S. Dist. LEXIS 2282, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stiers-bros-const-co-v-broderick-ksd-1945.