Ferro-Concrete Co. v. Northampton County

91 A. 506, 245 Pa. 64, 1914 Pa. LEXIS 832
CourtSupreme Court of Pennsylvania
DecidedApril 13, 1914
DocketAppeal, No. 206
StatusPublished
Cited by1 cases

This text of 91 A. 506 (Ferro-Concrete Co. v. Northampton County) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ferro-Concrete Co. v. Northampton County, 91 A. 506, 245 Pa. 64, 1914 Pa. LEXIS 832 (Pa. 1914).

Opinion

Opinion by

Mr. Justice Stewart,

The action was for the recovery of a balance on the contract price for the erection and construction of a concrete bridge, with steel reenforcements, over the Lehigh river at Easton. Under the contract plaintiffs were to receive for the completed structure $109,950. This sum, less ten per cent, which under the terms of the contract was to become payable upon an inspection of the bridge by viewers appointed by law, and an approval by the court, has been fully paid to the plaintiffs. The controversy is over the ten per cént. retained. The bridge has been fully completed, and accepted by the county, and the demand of plaintiffs is for the payment of the ten per cent, retained. This demand is met by a counterclaim on the part of the county, based on a provision in the contract which requires that the work as outlined in the plans and specifications be completed within 180 days from the time the contract is awarded, and stipu[67]*67lates that in ease of failure to complete the work within the prescribed time the contractors shall pay to the county the sum of fifty dollars for each day after the expiration of the said 180 days that the work remains unfinished, not as penalty but as liquidated damages. The contention on part of the county was that plaintiffs instead of completing the bridge within the time limit, which expired 23d October, 1911, did not complete it until August of the following year, and that for this delay the county was entitled to recover from plaintiffs the sum of $14,800. That the bridge was not completed within 180 days from December, 1911, was admitted. The plaintiffs’ reply to the counter-demand was, first, that the 180-day provision in the contract was not absolute and unconditional, but was dependent on conditions which failed; that the contract by another section (90) provided that in case of such failure of conditions, — rock not being found at the estimated elevation — an extension of time was to be allowed in the same ratio to the time limited as the increased yardage bore to the total yardage above the estimated elevation. It clearly appeared that rock was not found at the estimated elevation, and that in consequence a greater depth had to be reached than that originally contemplated. At the suggestion of the plaintiffs, for reasons which met the approval of the defendant,, for this additional work, piles were substituted for concrete. It is admitted by appellant that had the concrete work been adopted the contractor would have been entitled to an extension of forty-seven days beyond the 180 because of the additional work required. It is not contended that the construction by piles required any less time than would have been required for concrete, but the argument is that this provision for an extension of time relates exclusively to concrete work, and that it was eliminated by the supplemental agreement substituting piles for concrete. The learned trial judge rejected this view of the case, as we think properly, and held that the 180-day limit was de[68]*68pendent on finding rock at the estimated elevation, and that the time of the completion of the bridge was thus automatically extended by the formula prescribed in the contract, and so instructed the jury.

A further claim of extension of thirty-six days was made by plaintiffs for the reason that under the terms of their contract they were required to submit to the Lehigh Coal & Navigation Company, whose canal was to be crossed by the proposed bridge, plans of the two temporary bridges and false work which were to be used in removing the old bridge structure and building the new one before commencing the work, and to build the said temporary bridges and false work in all respects according to the requirements and to the satisfaction of the Lehigh Coal & Navigation Company, with the provision that in case the conditions imposed by the latter company occasioned more expense than it would be reasonable that the plaintiffs should bear, they should be allowed a sum in addition to the contract price as should thereafter be mutually agreed upon. The contention on part of plaintiffs was that they had submitted plans to the Lehigh Coal & Navigation Company, which they were prepared to observe, but that these had to be abandoned later on as the work was progressing because of extraordinary demands made by the navigation company with respect to the width of clearance. The evidence adduced by plaintiffs, if believed, sustained their contention, that because of these demands made by the navigation company, which they were required by their contract to observe, they were delayed thirty-six days in the completion of the work. The evidence adduced by the defendant would have supported a contrary finding. The question was one of fact which does not concern us; the one question for our consideration being whether, conceding the facts to be as claimed by plaintiffs, they were entitled under the terms of their contract to an extension of the time limit in consequence. At the time the contract was entered into, it was not known what the [69]*69requirements of the canal company would be, yet whatever they might be, the plaintiffs obligated themselves to meet and fulfill them. A reasonable implication arising, in view of the time fixed for the completion of the work, would be that plaintiffs were to be made acquainted with the company’s demands in time to permit them to proceed with the work of construction without interruption or delay. They were to build in accordance with these requirements whatever they might be. A change in the requirements involving the undoing of work already done and consequent delay in the completion of the bridge, except as plaintiffs were chargeable with some default in connection therewith, was a contingency not expressly provided against; nevertheless, to deny for this reason the plaintiffs a corresponding extension of the time limit in consequence would be so inconsistent with fair dealing and the general spirit of the contract, that, in the absence of express words requiring it a reasonable construction would be that for delay so occasioned plaintiffs were not to be chargeable. The question of whether plaintiffs were actually delayed on this account without themselves being in blame, and to what extent, was submitted to the jury with the result that the jury made an allowance of thirty-six days additional extension on this account.

Allowing the several extensions above indicated, the period for the completion of the bridge would be ex- . tended to 14th January, 1912. But the bridge was not completed and turned over to the county until 14th August following. To relieve themselves from liability for this further delay, plaintiffs contended and offered evidence to show that on 14th January they were in position to have substantially completed the bridge by the first day of February following; that on the 30th of December previous they were served with a copy of a • resolution adopted by the county commissioners directing and requiring them to suspend the work of concreting until freezing weather had passed, and to forbid [70]*70tlie transit company from crossing the bridge and the use of the arches until certain things had been done; that in consequence of this order the work on the bridge was suspended and not resumed until sometime in April following, and then under conditions and circumstances for which it is claimed they were not responsible, and which need not here be recited, which prevented á completion before the following August.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Electri-Tech, Inc. v. Radnor Twp.
Commonwealth Court of Pennsylvania, 2025

Cite This Page — Counsel Stack

Bluebook (online)
91 A. 506, 245 Pa. 64, 1914 Pa. LEXIS 832, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ferro-concrete-co-v-northampton-county-pa-1914.