Wm. A. Smith Contracting Company, Inc. And Brown & Root, Inc. v. The United States

412 F.2d 1325, 188 Ct. Cl. 1062, 1969 U.S. Ct. Cl. LEXIS 182
CourtUnited States Court of Claims
DecidedJuly 16, 1969
Docket102-67
StatusPublished
Cited by25 cases

This text of 412 F.2d 1325 (Wm. A. Smith Contracting Company, Inc. And Brown & Root, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wm. A. Smith Contracting Company, Inc. And Brown & Root, Inc. v. The United States, 412 F.2d 1325, 188 Ct. Cl. 1062, 1969 U.S. Ct. Cl. LEXIS 182 (cc 1969).

Opinion

PER CURIAM:

This case was referred to Trial Commissioner Donald E. Lane * with directions to make recommendation for conclusions of law under the order of reference and Rule 99(c) on plaintiffs’ motion and defendant’s cross-motion for summary judgment. The commissioner has done so in an opinion and report filed on March 10, 1969, wherein such facts as are necessary to the opinion are stated. Plaintiffs have filed a request for review under Rule 55(b) (3) and the case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court agrees with the commissioner’s opinion and recommended conclusion of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. Therefore, it is concluded that the decision of the Appeals Board of the United States Department of Commerce is sup *1327 ported by substantial evidence, is not arbitrary or capricious, and is correct as a matter of law. Plaintiffs’ motion for summary judgment is denied, defendant’s cross-motion for summary judgment is allowed and plaintiffs’ petition is dismissed.

OPINION OF COMMISSIONER

LANE, Commissioner:

In this case the court is called upon to review a decision of the Appeals Board of the United States Department of Commerce under the standards prescribed in the Wunder-lich Act, Title 41 U.S.C. §§ 321-322. The decision of the Appeals Board was rendered on August 20, 1964. This case is before the court on plaintiffs’ motion and defendant’s cross-motion for summary judgment.

Plaintiffs are joint contractors, Wm. A. Smith Contracting Company, Inc., a corporation of the State of Missouri, and Brown & Root, Inc., a corporation of the State of Texas. On May 18, 1956, plaintiffs entered into contract, No. 14-26-002-352, with the Alaska Road Commission of the Department of the Interior for the construction of 37.-52 miles of unpaved roadway in the Territory of and now State of Alaska. The roadway to be constructed under the contract constituted a portion of the Denali Highway extending from the MacLaren River westward to the Susit-na River. In 1956, after the contract was formed, the responsibility for road construction in Alaska was transferred from the Department of the Interior to the Department of Commerce pursuant to the Federal-Aid Highway Act of 1956, § 107(b), 70 Stat. 374, 377.

The contract called for excavation work at specified locations along the route of the highway and for placement of suitable excavated material as embankment, subgrade, shoulders, slopes, etc. The contract provided that no excavated material was to be wasted without permission. It further provided that material for embankments was to consist of suitable material approved by the engineer and that the embankments were to contain no muck.

During construction of the roadway, plaintiffs encountered frozen material in certain areas where excavation was required. Plaintiffs requested permission to waste the excavated frozen material and to substitute borrow material in the construction of embankments. The contracting officer did not permit such material to be wasted nor did it permit the substitution of borrow material to be made. Plaintiffs asserted that the frozen material was permafrost and that this was a condition which the defendant had represented would be no problem in the construction of the roadway. Plaintiffs further asserted that the excavated permafrost was not a suitable material for the formation of embankments because the permafrost thawed when excavated and became muck.

The contract contained, in its general provisions, the standard “Changes” and “Changed Conditions” clauses for construction contracts. The “Changed Conditions” clause provides for an equitable adjustment in the event that the contractor encounters subsurface or latent physical conditions differing materially from those indicated in the contract, or unknown physical conditions of an unusual nature differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract. The “Changes” clause authorizes the contracting officer to make changes, by written order, in the drawings or specifications of the contract and to make an equitable adjustment if the changes resulted in an increase or decrease in the amount due under the contract. Both clauses provide that, in case of a dispute concerning the adjustment to be made, the dispute shall be determined in accordance with the “Disputes” clause of the contract. Under the “Disputes” clause, the contracting officer is to decide any dispute concerning a question of fact arising under the contract which cannot be decided by agreement. The contractor is given the right to ap *1328 peal the decision of the contracting officer to the head of the department with which the contract was made, or his duly authorized representative.

The contractor submitted a claim to the contracting officer, pursuant to the “Disputes” clause of the contract, for additional compensation in the amount of $434,347.72 for the excavation and placement of the frozen material which it asserted was permafrost. The contracting officer decided that the contractor was not entitled to any adjustment in payment under the terms of the contract. An appeal from the decision of the contracting officer was filed with the Board of Appeals for the Department of Commerce. The Board of Appeals, after consideration of the proofs submitted by the contractor and the Government, held that the contractor, on the basis of its past experience and the information available to it regarding the conditions of the soil, should have anticipated that permafrost or frozen conditions would be encountered in the excavation work. The Board of Appeals denied the contractor’s claim for additional compensation.

The contractor then filed a petition in this Court for a review of the decision of the Board of Appeals under the Wun-derlich Act, Title 41 U.S.C. §§ 321-322. The plaintiffs assert that the Board was in error in denying their claim for adjustment under the “Changes” and “Changed Conditions” clauses of the contract. Further, plaintiffs assert that they are entitled to relief, outside the provisions of the contract, for breach of contract.

In order to evaluate the Board’s decision, it is necessary to consider the circumstances existing prior to the formation of the contract. The work to be performed under the contract consisted of roadway construction in Alaska. Prior to the solicitation of bids for the contract, the Government issued a pre-bid notice advising prospective bidders of its intention to let a contract for the roadway construction in April 1956. The pre-bid notice was issued on August 25, 1955, in order to permit interested contractors an opportunity to inspect the construction area before the severe winter weather of Alaska made inspection impossible. It advised the contractors of the limited access to the construction area by small aircraft.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Metric Construction Co. v. United States
81 Fed. Cl. 804 (Federal Claims, 2008)
Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
Navcom Defense Electronics, Inc. v. England
53 F. App'x 897 (Federal Circuit, 2002)
H.B. Mac, Inc. v. United States
41 Cont. Cas. Fed. 77,028 (Federal Claims, 1996)
Hardwick Bros. v. United States
41 Cont. Cas. Fed. 76,972 (Federal Claims, 1996)
Hendry Corp. v. Metropolitan Dade County
648 So. 2d 140 (District Court of Appeal of Florida, 1995)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
A.S. McGaughan Co. v. United States
37 Cont. Cas. Fed. 76,239 (Court of Claims, 1991)
J. Parr Construction & Design, Inc. v. United States
37 Cont. Cas. Fed. 76,167 (Court of Claims, 1991)
Al Johnson Construction Co. v. United States
36 Cont. Cas. Fed. 75,850 (Court of Claims, 1990)
Petrochem Services, Inc. v. The United States
837 F.2d 1076 (Federal Circuit, 1988)
North Slope Technical Ltd. v. United States
34 Cont. Cas. Fed. 75,430 (Court of Claims, 1988)
Shank-Artukovich v. United States
34 Cont. Cas. Fed. 75,372 (Court of Claims, 1987)
Baltimore Contractors, Inc. v. United States
34 Cont. Cas. Fed. 75,267 (Court of Claims, 1987)
Iconco v. United States
32 Cont. Cas. Fed. 72,720 (Court of Claims, 1984)
P.J. Maffei Building Wrecking Corp. v. United States
31 Cont. Cas. Fed. 71,307 (Court of Claims, 1983)
Afgo Engineering Corp. v. United States
28 Cont. Cas. Fed. 81,388 (Court of Claims, 1981)
Robert McMullan & Sons, Inc.
650 F.2d 292 (Court of Claims, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
412 F.2d 1325, 188 Ct. Cl. 1062, 1969 U.S. Ct. Cl. LEXIS 182, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wm-a-smith-contracting-company-inc-and-brown-root-inc-v-the-united-cc-1969.