Paul N. Howard Company v. Puerto Rico Aqueduct Sewer Authority v. Insurance Company of North America, Third-Party

744 F.2d 880, 1984 U.S. App. LEXIS 17788
CourtCourt of Appeals for the First Circuit
DecidedOctober 11, 1984
Docket83-1824
StatusPublished
Cited by67 cases

This text of 744 F.2d 880 (Paul N. Howard Company v. Puerto Rico Aqueduct Sewer Authority v. Insurance Company of North America, Third-Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paul N. Howard Company v. Puerto Rico Aqueduct Sewer Authority v. Insurance Company of North America, Third-Party, 744 F.2d 880, 1984 U.S. App. LEXIS 17788 (1st Cir. 1984).

Opinion

COFFIN, Circuit Judge.

This dispute arises out of an unsuccessful attempt to lay a 66-inch diameter concrete sewer pipe along a route almost two miles long in Mayaguez, Puerto Rico. The plaintiff, Paul N. Howard Company (“How *882 ard”), was hired by the defendant, the Puerto Rico Aqueduct and Sewer Authority (“PRASA”), to construct the pipeline. Howard claims that due to an unexpected site condition it was impossible to build the sewer in compliance with contract specifications. Howard brought this suit seeking partial rescission of the contract and compensation for extra costs incurred as a result of design changes ordered by PRASA after construction began.

The district court for the District of Puerto Rico entered a judgment in favor of Howard in the amount of about $4 million. The district court also awarded Howard attorney’s fees “in view of the temerity and obstinacy displayed by [the] defendant”.

PRASA appeals, arguing that the district court erred in holding that the terrain at the foot of the embankment of P.R. Highway No. 2 constituted a differing site condition and in holding that it was impossible to lay the sewer along the straight line specified in the contract. PRASA also challenges the district court’s award of costs incurred by Howard as a result of PRASA’s decision to increase the required load capacity of the sewer’s supporting piles and argues that the district court abused its authority in awarding attorney’s fees. Finally, PRASA argues that as an instrumentality of the government of Puerto Rico it is immune from a suit for damages in federal court under the Eleventh Amendment. We reject each of these claims and affirm the judgment of the district court.

Differing Site Condition

The original contract called for Howard to lay the sewer line parallel to P.R. Highway No. 2 for a distance of over 500 meters. Howard was expected to dig a ditch about forty feet deep at the toe of the highway embankment,’ drive piles to support the pipeline, place the pipeline on top of the piles at the bottom of the ditch, and then backfill the ditch with earth, burying the pipeline. It was Howard’s obligation under the contract to design and use a sheet piling system which would support the wall of the excavation during construction. Howard did design and use such a system, but shortly after Howard began excavation at the toe of the highway embankment it settled, pushing the sheet piling system into the excavation and causing the highway itself to settle. Howard then backfilled the trench to prevent further damage to the highway, and notified PRASA that it had encountered a “differing site condition” 1 , requiring modification of the contract terms. PRASA ordered Howard to further backfill the excavation to an elevation higher than the surrounding ground level, but disputed Howard’s claim that the tendency of the highway embankment to slide constituted a differing site condition.

Both parties retained soil experts to investigate the cause of the settlement of the highway embankment. In their discussions PRASA insisted that the settlement was caused by Howard’s use of an inadequate sheet piling system, while Howard argued that given the structure of the highway embankment and the nature of the soil conditions at the site, it would be impossible to lay the pipeline as planned without causing some settlement of the highway and displacement of the pipeline.

After an impasse of more than four months, PRASA and Howard agreed that Howard would make another attempt to lay the pipeline along the highway. This time Howard limited its excavation, removing only enough earth to allow it to install one section of pipe at a time. Howard’s soil consultant was at the site and directed a significant portion of this second excavation. Between February 18, 1980 and March 3, 1980, Howard installed nine sections of pipe without experiencing any lateral displacement. Highway settlement *883 was limited to a maximum of ih" during that period. But after the sheet piling was removed, as required by the contract, the highway settled 15" and the pipeline was displaced laterally. At the time the parties believed that the pipeline was 14" off center. More recent measurements indicate that the lateral displacement did not exceed 7".

PRASA did not consider this deviation from the design specifications acceptable and refused to approve or pay for Howard’s work in this area of the project. Howard abandoned the construction site in December, 1980 after having spent more than five months in an unsuccessful attempt to obtain a change order from PRASA. This lawsuit followed.

The district court held in Howard’s favor, concluding that it was not possible for Howard to construct the pipeline along the route designated by PRASA in the manner specified in the contract without causing settlement of the highway embankment and displacement of the pipeline. The district court found that the instability of the highway embankment constituted a differing site condition justifying rescission of that part of the contract that required Howard to lay the pipeline along the highway embankment and rejected PRASA’s contention that it was the design of Howard’s sheet piling system that was responsible for Howard’s difficulties. In coming to this conclusion, the district court relied on expert testimony that the tendency of the highway embankment to slide was unusual and unpredictable, and that only by changing the course of the pipeline or leaving the sheet piling in place could lateral displacement of the pipeline be prevented. The court also relied on testimony describing the difficulties another construction company encountered when it attempted to lay this section of the pipeline several years after Howard had abandoned its attempt.

On appeal PRASA attacks the district court’s conclusion that the conditions encountered by Howard were unusual and unpredictable and that construction of the pipeline according to the design plans was impossible. After reviewing the record, we reject PRASA’s contentions. It is not our task to reweigh the evidence presented to the district court. We may alter that court’s judgment only if it applied an erroneous legal standard or committed a clear error in its findings of fact. We have not been referred to, nor have we found, any evidence indicating that the district court made either of these errors.

As noted by the trial judge in his findings of fact, there was expert testimony to the effect that the instability of the highway embankment was unusual and unexpected:

“It is my opinion that the designers of this project did not anticipate the events which we have observed. And I do not mean that to be critical because I do not think they should be severely faulted for that. The condition which we find is not common. I do not think that the contractor anticipated the occurrences which we observed. I do not think that the soil consultant anticipated the conditions which we observed. In short, I don’t [think] anybody anticipated what we have observed.
“[I]n October of 1979, we all suddenly learned a lesson.” Testimony of Sydney M. Johnson, VI Joint Appendix 1736-37.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Katherine Frederick v. NH DHHS
2017 DNH 089 (D. New Hampshire, 2017)
Bergemann v. Rhode Island
676 F. Supp. 2d 1 (D. Rhode Island, 2009)
Aholelei v. Department of Public Safety
488 F.3d 1144 (Ninth Circuit, 2007)
Ramos-Pinero v. Commonweath of PR
453 F.3d 48 (First Circuit, 2006)
Padilla Roman v. Hernandez Perez
381 F. Supp. 2d 17 (D. Puerto Rico, 2005)
In Re HMCA (Carolina), Inc.
301 B.R. 764 (D. Puerto Rico, 2003)
NH v. Blind Vendors
2003 DNH 054 (D. New Hampshire, 2003)
Maysonet-Robles v. Cabrero
323 F.3d 43 (First Circuit, 2003)
Padilla Cintron v. Rossello Gonzalez
247 F. Supp. 2d 48 (D. Puerto Rico, 2003)
Iravedra v. Public Building Authority
196 F. Supp. 2d 104 (D. Puerto Rico, 2002)
State Contracting Engineering v. Florida
258 F.3d 1329 (Federal Circuit, 2001)
State Contracting & Engineering Corp. v. Florida
258 F.3d 1329 (Federal Circuit, 2001)
May v. Missouri Department of Revenue (In Re May)
251 B.R. 714 (Eighth Circuit, 2000)
Nell Neinast v. State Of Texas
217 F.3d 275 (Fifth Circuit, 2000)
Neinast v. State of Texas
217 F.3d 275 (Fifth Circuit, 2000)
Varela-Fernandez v. Burgos
81 F. Supp. 2d 297 (D. Puerto Rico, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
744 F.2d 880, 1984 U.S. App. LEXIS 17788, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paul-n-howard-company-v-puerto-rico-aqueduct-sewer-authority-v-insurance-ca1-1984.